Alexander Hendry Co. v. Mooar

242 Ill. App. 516, 1926 Ill. App. LEXIS 130
CourtAppellate Court of Illinois
DecidedDecember 21, 1926
DocketGen. No. 31,048
StatusPublished
Cited by7 cases

This text of 242 Ill. App. 516 (Alexander Hendry Co. v. Mooar) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alexander Hendry Co. v. Mooar, 242 Ill. App. 516, 1926 Ill. App. LEXIS 130 (Ill. Ct. App. 1926).

Opinion

Mr. Presiding Justice Gredley

delivered the opinion of the court.

In a mechanic’s lien proceeding, commenced October 4, 1923, the master in his. report, filed May 11, 1925, recommended the allowance of two original contractors’ liens upon the premises, one in favor of Alexander Hendry. Company, complainant, for the sum of $270, with interest from February 5, 1923, and the other in favor of S. M. Hunter, defendant and intervening petitioner, for the sum of $397.30, with interest from May 24, 1923. Objections to the report, filed by Morris and Minnie Fink, defendants to complainant’s bill and to Hunter’s intervening petition, were ordered to stand as exceptions before the court. The Finks had become the owners of the premises by purchase subsequent to the making of the separate contracts for materials and labor furnished by said contractors. On October 30, 1925, after a hearing upon the exceptions, the court confirmed the master’s report as to the claim of Hendry Company, and decreed that, unless the Finks paid the amount of its claim, the premises be sold, etc., but the court disallowed the claim of Hunter and decreed that his intervening petition be dismissed, and further decreed that the costs be taxed one-third against the Finks, one-third against Hunter and one-third against another unsuccessful intervening petitioner, whose claim is not now involved. From the decree Hunter prayed and perfected within apt time the present separate appeal.

It appears from the decree that the Finks also prayed a separate appeal, which was allowed, conditioned upon their filing a bond within 30 days, but it does not appear that they perfected their appeal or made any attempt to do so. After the transcript on Hunter’s appeal had been filed, the Finks, by their attorneys, presented a motion, supported by affidavit and showing that notice of the motion had been served on Hunter’s attorneys (but not on the Hendry Company), asking that they be permitted to file a supplemental transcript of the record, “and also to assign cross-errors herein.” This court allowed the supplemental transcript to be filed. It merely shows that on May 11,1925, the circuit court had ordered that all objections filed to the master’s report stand as exceptions. This Appellate Court also allowed the other portion of the motion, viz, that the Finks might “assign cross-errors herein,” which thereafter were assigned. Upon reviewing them it appears that they relate solely to alleged errors of the circuit court (a) in decreeing that the Hendry Company has a mechanic’s lien upon the premises for $270 and interest, and ordering the Finks to pay the amount or, in default thereof, that the premises be sold, etc., and (b) in taxing any part of the costs against the Finks.

From stipulations and oral and documentary evidence introduced before the master, it appears that prior to January 24,1923, one Stella Hazzard was the owner in fee of the premises, improved with an apartment building; that Harry L. Mooar had been her duly authorized agent to enter into contracts for her with mechanics or material men for the improvement of the premises and to direct all work; that on said date, Miss Hazzard entered into a contract, recorded February 8,1923, with Esther M. Johnson and Burt Johnson, her husband, for the sale of the premises to them, and that they took possession on February 1, 1923, and thereafter collected the rents; that on February 14, Miss Hazzard conveyed the premises by warranty deed, duly recorded, to David L. Golden, and also assigned all of her right, title and interest in the Johnson contract to him; that on February 23, Golden and wife conveyed the premises by warranty deed, duly recorded, to the Finks, and also assigned their interest in the Johnson contract to them; that the contract interest in the premises, which the Johnsons had acquired, was transferred by them to Mrs. Beulah Fritz about March 20, and she took possession; and that afterwards, about May 8, 1923, she transferred said contract interest to Mrs. H. J. Anderson and husband, and they at once took possession and were living on the premises at the time of a hearing before the master in October, 1924.

As to the lien of appellant, Hunter, it appears that he was in the business of doing carpentry work and contracting; that about the last day of September, 1922, he entered into a verbal contract with Mooar (acting for Miss Hazzard) to furnish certain materials and do certain carpentry labor on the apartment building, according to a certain plan then shown him and instructions to be given from time to time by Mooar; that the work was substantially completed about December 1, 1922, and was of the value of $697.80; and that he was paid on account the total sum of $300.50, made in three instalments in October, 1922, and in February and March, 1923, leaving a balance unpaid of $397.30. He did not file as an original contractor his statement of claim for lien with the clerk of the circuit court, in accordance with section 7 of the Mechanics’ Liens Act [Cahill’s St. ch. 82, [[7], until August 8, 1923, which is more than four-months after the substantial completion of his contract, and he did not file his intervening petition in the cause until November 3, 1923. It was contended in the trial court by the Finks that, as against them as purchasers of the premises, Hunter had lost his lien, if any he had, because of said statement of claim for lien not having been fifed in time. Hunter testified on direct examination that his last work on the premises was done on May 24, 1923, at Mooar’s request. On cross-examination he testified that he did no work after December 1, 1922, except that on May 24, 1923, “We adjusted the door and fixed the lock” —one hour’s time — at the front entrance, which door and lock “had been put on in October or November, 1922.” Mooar testified that he “didn’t have charge of the building after February 1, 1923,” on which day the Johnsons took possession, and he (Mooar) went with them and notified the tenants that they (the John-sons) would thereafter be in possession and would collect the rents. And Mrs. H. J. Anderson testified: “From May 8, 1923, when I took possession, to the present time (October, 1924) there has been no work done in the repairing of the building of any nature or description by anybody. * * * I manage the building, collect the rents, hire the janitor, and order everything done. * * * There has been no carpenter work done by anybody since that time.”

In view of the evidence we think that the court was fully warranted in disallowing Hunter’s claimed lien, as against the Finks, subsequent purchasers, and in dismissing his intervening petition. Even if it be considered that Hunter, by one of his employees, actually did the claimed adjusting work on May 24, 1923, we regard it as an unwarranted attempt to revive a lien which had been lost by failure to comply in time with the provisions of section 7 of the Lien Act [Cahill’s St. ch. 83, ft 7]. Hunter’s verbal contract with Mooar had been substantially completed in November, 1922, and he did not file within four months from that time any statement of claim for lien, in compliance with said section of the Lien Act. And it does not appear that Mooar ordered this particular adjusting work done as extra or additional work on the original contract, and the work, if done, was of a trivial and inconsequential character, and rather in the nature of new and separate repair work, and we do not think it can properly be “tacked on” as a part of the original contract made with Mooar. (Stone v. Juvinall, 125 Ill. App. 562, 564; Schaller-Hoerr Co. v. Gentile, 153 Ill. App. 458, 461; Davis v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Merchants Environmental Industries, Inc. v. SLT Realty Ltd. Partnership
731 N.E.2d 394 (Appellate Court of Illinois, 2000)
M. Ecker & Co. v. La Salle National Bank
645 N.E.2d 335 (Appellate Court of Illinois, 1994)
Daily v. MidAmerica Bank & Trust Co.
474 N.E.2d 788 (Appellate Court of Illinois, 1985)
Du Page Bank & Trust Co. v. Du Page Bank & Trust Co.
462 N.E.2d 25 (Appellate Court of Illinois, 1984)
Capital Plumbing & Heating Co. v. Snyder
275 N.E.2d 663 (Appellate Court of Illinois, 1971)
Hindman v. Off
246 Ill. App. 528 (Appellate Court of Illinois, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
242 Ill. App. 516, 1926 Ill. App. LEXIS 130, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alexander-hendry-co-v-mooar-illappct-1926.