Merritt v. Crane Co.

80 N.E. 103, 225 Ill. 181
Illinois Supreme Court·Decided December 22, 1906·Published·Cited by 1 cases

Opinion

Mr. Justice Hand

delivered the opinion of the court:

A motion was entered in this court by the Crane Company to dismiss the appeal as to it, which was reserved to the hearing, upon the ground that its claim was less than $1000, and that no appeal would lie from the judgmeñt of the Appellate Court affirming the decree of the superior court establishing a lien in its favor, without a certificate of importance, which had not been granted by the Appellate Court.

The statute provides that in actions ex contractu, where the amount involved is less than $1000, no appeal will lie from the Appellate Court to this court, in the absence of a certificate of importance. (1 Starr & Cur. Stat.—2d ed.—■ chap. 37, sec. 8, p. 1153.) The right to an appeal is purely statutory, and unless a party brings himself within the terms of the statute no’ appeal will lie. (Hileman v. Beale, 115 Ill. 355.) In this case the claim of the Crane Company was for less than $1000 and no certificate of importance was granted. Its claim was separate and distinct from and in no way connected with the claim of either of the other appellees. We think it clear, therefore, that no appeal, without such certificate, would lie from the Appellate Court to this court against the Crane Company.

In Davis v. Upham & Stone, 191 Ill. 372, which was a mechanic’s lien case, the original petition was filed by the Rittenhouse & Embree Company to establish a lien for $527.19, and in the same case intervening petitions were filed by James R. Scott for $2486.50, William E. Palmer, a sub-contractor, for $1775, Upham & Stone, sub-contractors under Palmer, for $245.53, and the Gould Manufacturing Company, a sub-contractor, for $646.37. The Rittenhouse & Embree Company, Upham & Stone and Palmer were allowed liens. The property owner prosecuted an appeal to the Appellate Court, where the decree as to Up-ham & Stone and Palmer was affirmed and reversed as to the Rittenhouse & Embree Company, and a further appeal was prosecuted to this court by the appellant in the Appellate Court, and' in this court a motion was made by. Upham & Stone to dismiss the appeal as to them on the ground of want of jurisdiction in this court to hear and determine the appeal, on the ground that their claim was -less than $1000 and no certificate of importance had been granted by the Appellate Court. The motion was allowed and the appeal dismissed. The court, on page 373, said: “Upham & Stone make a motion to' dismiss this appeal as to them. Their contention is, that the action of the Appellate Court in reference to their claim for lien, in the absence of a certificate of importance, is not subject to review here because the amount is less than" $1000 and because it is a separate and distinct claim from those of the other petitioners. The intervening petitions are on behalf of separate parties, to enforce distinct liabilities. One claim is in no manner connected with the other. As is said in the case of Farwell v. Becker, 129 Ill. 261, (p. 269): ‘Where the amount against each defendant is separate and distinct, as is the case here, the two amounts cannot be united so as to confer jurisdiction, but each must be treated as a separate suit; and if the amount involved as to either one is not large enough to confer jurisdiction, the appeal must fall,’—citing Paving Co. v. Milford, 100 U. S. 147; see, also, Stettauer v. Boldenweck, 183 Ill. 187.”

The same motion was made in Pugh Co. v. Wallace, 198 Ill. 422, which was also a mechanic’s lien case,, and in disposing of the motion the court, on page 427, said: “A sec-' ond ground for the motion is, that the claim of said company amounted to only $724.04, and that without a certificate of importance from the Appellate Court this court is without jurisdiction to pass upon the same. The motion as to the California Manufacturing Company is also based upon this last ground,—that is, that its claim is for less than $1000. We held in Davis v. Upham, 191 Ill. 372, that intervening petitioners for mechanics’ liens or material-men’s liens filed on behalf of separate parties must be treated as separate suits, and the several amounts allowed as liens cannot be added together in order to make the jurisdictional amount necessary to authorize an appeal from the Appellate Court to the Supreme Court.”

It seems to be thought \>y the appellants' that the present appeal can be distinguished from those appeals on the ground that in this case the same evidence is relied 'Upon to defeat the Crane Company lien as is relied upon to defeat the lien of P. T. Maloney and the lien of the Kellogg-MackayCameron Company, the other appellees, whose claims are each in excess of $1000. It is not the evidence by which a debt is sought to be established or defeated which determines whether or not the case is appealable from the Appellate Court to this court, but the “amount involved,” and as the amount involved in the Crane Company case is less than the jurisdictional amount this court is without jurisdiction to entertain this appeal as against the Crane Company. (Farwell v. Becker, 129 Ill. 261; Aultman & Taylor Co. v. Weir, 134 id. 137; Stettauer v. Boldenweck, 183 id. 187; Davis v. Upham & Stone, supra; Pugh Co. v. Wallace, supra; Hutmacher v. Anheuser-Busch Brewing Ass. 198 Ill. 613.) The appeal, as to the Crane Company, will therefore be dismissed.

Free access — add to your briefcase to read the full text and ask questions with AI

Merritt v. Crane Co., 80 N.E. 103, 225 Ill. 181 (Ill. 1906).

80 N.E. 103 (Merritt v. Crane Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Seeds v. Chicago Transit Authority
101 N.E.2d 84 (Illinois Supreme Court, 1951)