Williams v. Rittenhouse & Embree Co.

64 N.E. 995, 198 Ill. 602
CourtIllinois Supreme Court
DecidedOctober 25, 1902
StatusPublished
Cited by14 cases

This text of 64 N.E. 995 (Williams v. Rittenhouse & Embree Co.) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williams v. Rittenhouse & Embree Co., 64 N.E. 995, 198 Ill. 602 (Ill. 1902).

Opinion

Mr. Justice Boggs

delivered the opinion of the court:

One of the appellees, the Rittenhouse & Embree Company, filed in the circuit court of Cook county its bill in chancery to establish and enforce a mechanic’s lien on six certain lots abutting on Vincennes avenue, in the city of Chicago, in the sum of §1900.97, for lumber and building material furnished, as a sub-contractor, by the said company in the construction of six dwelling houses which had been erected on said lots. The bill made Ebenezer Ryder, William H. Barry and James E. Fellows, owners of the premises; the appellee firm of Stevens & Sherbrook, the original contractors for the carpenter and mill work; the firm of O. L. Webster & Son, principal contractors for the stone and brick work of the buildings, and the appellants, as holders of indebtedness Secured by mortgages on the premises, defendants to. the bill, together with other persons and firms who now have no interest in this proceeding-. Barry, Fellows and Ryder, owners of the fee of the premises, suffered default. Answers were filed by the other defendants and replications filed to the answers. The firm of C. L. Webster & Son, defendants to the bill, also filed a cross-bill, in which one F. B. Pease, to whom, as trustee, said Webster & Son had assigned their claim, joined, as cross-complainant. The cross-bill asked for the establishment of a lien in favor of said Webster & Son and said Pease, as their trustee. The cross-bill was answered, replications thereto filed and the cause referred to a master. The master reported the evidence taken, and his conclusions as to matters of law and fact, together with many objections and exceptions taken and preserved by the respective parties. The master recommended a decree establishing liens in favor of the contractors and sub-contractors, and declared the lien so established to be superior to that of the appellants, as mortgagees. The chancellor, on a hearing of the report of the master and the proofs and exliibits, declined to accept the conclusions reached by the master, but found that said contractors, sub-contractors and material-men aforesaid, “under the law and the evidence so taken and submitted by the said master in chancery with and as a part of his report, are not, nor are any or either of them, entitled to a lien on said premises, or any part thereof, under and in pursuance of the statute relating to mechanics’ liens,” and decreed that the original bill and the cross-bill be dismissed for want of equity. The contractors, sub-contractors and material-men aforesaid, prosecuted an appeal to the Appellate Court for the First District, and the decree of the circuit court was reversed by the said Appellate Court and the cause was remanded, with directions to the circuit court to enter a decree establishing liens as prayed in favor of each of such contractors, sub-contractors and material-men. This is an appeal from the judgment of the Appellate Court.

On the 6th day of May, 1896, William H. Barry and James E. Fellows, who had acquired the title to the six lots in question, entered into a verbal contract with the firm of Stevens & Sherbrook to do the carpenter work and furnish the lumber and mill work necessary to build six houses, one on each of said six lots. Stevens & Sherbrook had constructed three houses on other lots for Barry & Fellows, and the six to be constructed under this contract were to be duplicates of the others. The Eittenhouse & Embree Company entered into a verbal contract with Stevens & Sherbrook to furnish the lumber to be used in the construction of the said houses. C. L. Webster & Son entered into a written contract with Barry & Fellows to construct the stone and brick work for the buildings and furnish the material of that character necessary to be used therein.

We think the circuit court correctly decided the liens did not attach under any of these agreements. It may be conceded for the purpose of the disposition of the question as to the right of Stevens & Sherbrook to a lien, that, as claimed by their counsel, it was shown by the testimony they entered into an oral contract with the owners, Barry & Fellows, whereby they agreed to do all carpenter work for the buildings in question and furnish all the material therefor for $6000; that all such material and labor were to be furnished in a reasonable time within one year from the date of said contract, payment to be made as the work progressed, final payment to be made on completion. It may also be conceded for the purpose of making disposition of the claim of the Rittenhouse & Embree Company for a lien, that, as claimed by the counsel for that company, “the proof shows conclusively that a verbal contract was entered into on May 9, 1896, between Stevens & Sherbrook and Rittenhouse & Embree Company whereby the latter agreed to furnish all the lumber for the improvements. They entered upon the performance of their contract the same day it was made and delivered material, continuing from day to day thereafter to the following- August 8, 1896, when the last material was furnished. The understanding between the parties was that they were to receive their pay as the work progressed and final payment on final delivery. Of course, being a sub-contractor of Stevens & Sherbrook, the time for completion and final payment as to the contract of Stevens & Sherbrook would naturally and necessarily control as to the sub-contract for materials with Rittenhouse & Embree Company.”

The written contract between Webster & Son and said Barry & Fellows contained the following provisions with reference to the time in which the work was to be performed and the material furnished, viz.:

“Article 6. The contractor shall complete the several portions and the whole of the work embodied in this agreement by and at the time or times hereinafter stated, to-wit: to have the brick walls ready for the roof joists in thirty days from the date hereof, and the balance of the work as soon as practicable thereafter.”

Article 7 of the contract provided that if the said Webster & Son should be delayed in the completion of the contract by the default of the owners, architects or any other contractor, or by the action of the elements, the time fixed for the completion of the work should be extended for a period equivalent to that lost by the delay. As to the time of payment, and the manner thereof, this written contract provided “that the sum to be paid by the owner to the contractor for said work shall be §4800, payable in installments, eighty-five per cent as the work progresses. The final payment shall be made within thirty days after this contract is fulfilled.”

The liens, if any attached under these contracts, must have been by virtue of the provisions of an act entitled “An act to revise the law in relation to mechanics’ liens,” approved and in force June 26, 1895. (Hurd’s‘Stat. 1899, p. 1104.) Section 6 of the act is as follows: “If the work is done or materials are furnished under a verbal contract, no lien shall be had by virtue of this act unless the work shall be done or materials furnished within one year from the date of the contract, and final payment therefor is to be made within such time. If the contract be written, no lien shall be had by virtue of this act, if the time stipulated for the' completion of the work or furnishing materials is beyond three years from the date of the contract, or the time of payment beyond one year from the time stipulated for the completion thereof.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State ex rel. Granite Investment Co. v. Superior Court
131 Wash. 20 (Washington Supreme Court, 1924)
Natural Carbon Paint Co. v. Fred Bredel Co.
193 F. 897 (Seventh Circuit, 1911)
Kelly v. Johnson
95 N.E. 1068 (Illinois Supreme Court, 1911)
Weidle v. Elgin, Joliet & Eastern Railway Co.
152 Ill. App. 292 (Appellate Court of Illinois, 1910)
Berry Bros. v. Fairbanks, Morse Co.
112 S.W. 427 (Court of Appeals of Texas, 1908)
Snitzler v. Filer
135 Ill. App. 61 (Appellate Court of Illinois, 1907)
Garthwait v. Bloomington Hotel Co.
130 Ill. App. 418 (Appellate Court of Illinois, 1907)
Cooke v. Haungs
113 Ill. App. 501 (Appellate Court of Illinois, 1904)
Smith v. Central Lumber Co.
113 Ill. App. 477 (Appellate Court of Illinois, 1904)
Henry v. Applegate
111 Ill. App. 13 (Appellate Court of Illinois, 1903)
VonPlaten v. Winterbotham
203 Ill. 198 (Illinois Supreme Court, 1903)
Pierce v. Barnes
106 Ill. App. 241 (Appellate Court of Illinois, 1903)
Richardson v. Central Lumber Co.
105 Ill. App. 358 (Appellate Court of Illinois, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
64 N.E. 995, 198 Ill. 602, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williams-v-rittenhouse-embree-co-ill-1902.