Garthwait v. Bloomington Hotel Co.

130 Ill. App. 418, 1907 Ill. App. LEXIS 322
CourtAppellate Court of Illinois
DecidedJanuary 22, 1907
StatusPublished

This text of 130 Ill. App. 418 (Garthwait v. Bloomington Hotel Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Garthwait v. Bloomington Hotel Co., 130 Ill. App. 418, 1907 Ill. App. LEXIS 322 (Ill. Ct. App. 1907).

Opinion

Mr. Justice Baume

delivered the opinion of the court. •

This is a bill for a mechanic’s lien under the statute of 1895, filed April 4, 1903, by F. M. Gartfiwait, appellant, against the Bloomington Hotel Company, the owner, and Marshall K. Howe, a mortgagee, appellees. The written contract, dated October 17, 1901, for the construction by appellant of a hotel building in the city of Bloomington, contains among other provisions, the following: That the work shall be delivered to the owner a complete and finished job of its kind and free.from all claims, liens or charges, on or before August 1, 1902; that in case of his failure to complete the work on the day specified, the contractor will pay to the owner, as liquidated damages, the sum of $20 for each and every day thereafter, until said work shall be completed (Sundays excepted), said damages to be retained out of any money due the contractor under the contract or to be recovered at law; provided, that in case the contractor shall be hindered by any act or default of the owner, or of any other contractor on the work, or by strikes, or by the elements, he shall be given a just amount of extra time in which to finish the contract, said amount of extra time cto be fixed by the architect, and allowed only when the contractor shall have given the architect written notice of such hindrances, immediately upon their occurrence; that the contractor shall remove from the premises all objectionable material upon an order from the architect, and substitute therefor such material, as in the opinion of the architect is called for by the' drawings and specifications, or in case said work is allowed to remain, to deduct for its inferiority a proper amount of money to be estimated and fixed by the architect; that the owner shall pay to the contractor the sum of $129,000 upon written certificates issued by the architect, as the work progresses, for a sum not to exceed eighty-five per cent, of the value of the materials used and labor performed, as estimated b|y the architect, the owner to pay said certificates immediately upon their presentation and to make final settlements for the remainder and extras, if any, twenty days after the work shall be completed as covenanted and agreed and the architect shall have certified thereto in writing. The contract further provides that no oversight in superintendence by the architect or certificates issued by him shall release the contractor from any obligation to do and complete the work as covenanted and agreed; that no changes or alterations shall be made in the work indicated by the drawings and specifications, except upon a written order from the architect, and in case such changes or alterations involve an "increased or diminished cost, said cost shall be estimated by the architect and shall be added, to or deducted from the contract price, as the case may be; that the contractor waives all claim for extra time in" which to complete the work unless demand for the same was made as hereinbefore specified; that all disputes as to the true intent and meaning of the drawings and specifications shall be referred to the architect, and that the' amount of all claims for allowance of extra time and money by the contractor^ or for deduction by the owner, shall be estimated and fixed by the architect, and that his decision shall be final and binding upon both parties; that should the contractor at any time during the progress of the work allow any indebtedness to accumulate for labor or material to subcontractors or others that may become liens on the building or premises, and shall' fail to pay such indebtedness within five days after demand for same by the creditors, the owner shall have the right to withhold any money due the contractor until he has discharged said obligations, and apply the same to the payment thereof; that when the work is completed the contractor shall notify the owner that he is ready for a final settlement, and both the contractor and the owner shall file with the architect all statements, claims or bills that they may wish to make before the architect renders his final certificate.

Appellant entered upon the performance of the contract immediately following its execution. During the progress of the work extensive and varied changes were made in the plans and specifications and many extras were ordered by the owner and by its tenant. On November 16, 1901, appellant wrote to the architect, R. T. Newberry, stating that the iron contractor was claiming that on account of changes made in the plans he was delayed ten days in getting out new drawings, and that a still greater delay might be occasioned in getting material from the mill, and concluded his letter, as follows: “I write to protect myself in case the owner makes any claim for delay should there be any on the building.”

August 16, 1902, appellant wrote the architect, as follows:

“Regarding the delay in getting the Hotel Building finished by August 1, 1902, as per contract, I wish to say that I have been delayed to the extent of thirty-one (31) days on account of extreme cold weather. For this I can give you the exact date and temperature for each day. I have been delayed more or less on account of rainy weather through the months of May, June and July. I have also been delayed to an extent of thirtv (30) days on account of changes made in the building by the owners. Kindly allow me an extension of time on account of above delays.

“In regard to the progress of the building at the present time, I am hiring every man I can get. Am advertising in the papers here and even paying men’s fares to Bloomington, but it seems almost impossible to get men on account of the amount of work now going on.”

March 8, 1902, the Bloomington Hotel Company leased the premises to F. B. Ewins, the lease to become operative when the lessee took possession. November 1, 1902, the lessee commenced to move his furniture into the building, and on December 6, 1902, the hotel was opened to the public. Shortly prior to December 24, 1902, the architect issued to appellant a certificate for $8,000, for work done and materials ' furnished under the contract, which certificate was paid by the owner January 16, 1903, and is not here a matter of controversy.

Wednesday, January 8, 1903, the architect, Hanna, the president of the hotel company, Pillsbury, the local superintendent of construction, and appellant met together in Bloomington, for the purpose of considering all claims of the respective parties to the contract and adjusting the same. As a result of that meeting the architect gave to áppellant a certificate, as follows:

“Bldg. No. 601. $12,531.15. Jan. 12, 1903.

Certificate No. 21. To Bloomington Hotel Company.

Contract price..........................$129,000.00

Extra work...........................-. 11,131.15

Total.......................$140,131.15

Former certificates..................... 127,600.00

Present certificates..................... 12,531.15

Balance $

This is to certify, that F. M. Garthwait, Contractor, for the general work of yonr building, Blooming-ton, 111., is entitled- to a payment of twelve thousand five hundred and thirty-one & 15-100 Dollars, by the terms of contract.

B. T. Newberry, Architect.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Williams v. Rittenhouse & Embree Co.
64 N.E. 995 (Illinois Supreme Court, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
130 Ill. App. 418, 1907 Ill. App. LEXIS 322, Counsel Stack Legal Research, https://law.counselstack.com/opinion/garthwait-v-bloomington-hotel-co-illappct-1907.