Henry v. Applegate

111 Ill. App. 13, 1903 Ill. App. LEXIS 187
CourtAppellate Court of Illinois
DecidedOctober 8, 1903
DocketGen. No. 4172
StatusPublished
Cited by1 cases

This text of 111 Ill. App. 13 (Henry v. Applegate) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Henry v. Applegate, 111 Ill. App. 13, 1903 Ill. App. LEXIS 187 (Ill. Ct. App. 1903).

Opinion

Mr. Justice Farmer

delivered the opinion of the court.

This was a bill filed by James L. Applegate, defendant in error, against Fannie J. Henry, plaintiff in error, together with other defendants, to enforce a mechanic’s lien. Plaintiff in error was the owner of property in the city of Monmouth upon which there was an old dwelling house which she desired to remodel and improve, and on ' August 4, 1897, she entered into a written contract with defendant in error to do the work according to plans and specifications furnished' by him, for $975. The bill alleges that defendant in error completed the performance of said contract and at the request and under the instruction of plaintiff in error performed additional work and furnished additional material in the construction of additional improvements and making additional repairs on said premises, beyond and in excess of what was provided for in the original contract. The bill further alleges that no ' particular amount of material or labor beyond that included in the original contract was specifically contracted for, nor was the time for the completion of the extra work definitely fixed, but that the plaintiff in error directed the performing of the additional work and furnishing the additional material therefor, and that it was understood between the parties that in addition to the amount provided for under the written contract, plaintiff in error should pay defendant in error such compensation for the ■ additional improvements and repairs as they were reasonably worth. Further alleges, that he performed additional Avork and furnished additional material to the amount shoAvn by Exhibit A, attached to his bill, which was $223.54. The bill further alleges that immediately after the completion of the work, and on the 10th day of November, 1897, plaintiff in error accepted the premises, took possession thereof and has ever since occupied the same as a dwelling house; that she has paid only the sum of $960.52, and that there Remains due from her the sum of $238.02, which she neglects and refuses to pay, and prays for a lien on the premises in accordance Avith the provisions of the’ statute. By an amendment to the bill it was alleged that the extra work and material were “ to be paid for upon completion of the work and the Avork to be completed within one year from the time of ordering such alterations.” By a further amendment to the bill it was averred that on the 24th day of February, 1898, and within four months from the time of the completion of the contract and within four months from the time the final payment for said work and materials was due and payable according to the terms of the original contract, defendant in error filed in the office of the clerk of the Circuit Court his claim for lien verified by affidaArit as provided by Iuav.

There is no averment in the bill that any time was fixed ■ by the original contract for the completion of the Avork or the payment therefor. The nearest approach to an averment of that kind will be found in the second amendment above mentioned. The allegations in that amendment are simply that the defendant in error filed his claim for a lien in the office of the Circuit Clerk “ within four months from the time of the completion of said contract and within four months from the time the final payment for said work and materials was due and payable according to the terms of the original contract and of the subsequent verbal contract.” Plaintiff in error by her answer denied that there was any time fixed by the contracts within which the work was to be completed or the material furnished or within which payment was to be made. The cause was referred to the master to take the proofs of the respective parties and to report the same together with his conclusions to the court.

The master reported that the defendant in error had completed the original contract and had performed additional work and furnished additional materials at the request of defendant in error not provided for in the original contract. He further finds and reports that subsequent to the execution of the original contract it was agreed between the parties that the work provided for by said contract should be completed within three or four months from the date of the contract, but that the time for the completion of the additional and extra work and the furnishing of the extra material was not definitely fixed. He does not find that any time was fixed within which the work and materials were to be paid for under either the original or subsequent verbal contract. The master reported a balance due defendant in error on the original contract of §14.48 and other items for extra work and material amounting to $76.09, making a total of $90.57. He further reported that plaintiff in error was entitled to a credit on this amount of $30.75, moneys paid by her to other parties for the performance of certain work and the furnishing of certain materials that should have been performed and furnished by defendant in error under the original contract, leaving a balance due defendant in error of §59.82. Objections and exceptions to the master’s report were overruled by the court and a decree entered that the complainant was entitled to a lien on the premises for §59.82, directing the defendant to pay the same within ten days and that upon a failure to do so the premises be sold.

The written contract for the original work is very brief and provides neither time for the completion of the work nor for the payment of the money. By it the defendant in error agreed to do the work according to plans and specifications for $975. $100 was to be paid when the foundation was completed; $500 when the building was ready for plastering; $100 when the carpenter work was completed,' and the remaining $275 when the work was finished, hlo time however is fixed when any of these things were to be completed, and we do not find the master’s conclusion “ that subsequent to the making of the contract it was agreed between the parties that the work was to be completed within three or four months from the date thereof,” is sustained by the evidence. The only testimony on this point was that of plaintiff in error, and defendant in error and his brother William L. Applegate. Plaintiff in error testified that the work was to be completed within thirty days, but was directly contradicted by defendant in error and his brother William L. Defendant in error testified as follows :

“ Q. What was the understanding between you and her (plaintiff in error) as to the time the original building was to be finished ?

A: Three or four months.

Q. From when ?

A. Well I suppose from the time I commenced the job.

Q. When was it to be paid for Í

A. I don’t know as there was anything said about when she was to pay for the extras. There was nothing in the contract about the extras. We had no understanding when she was to pay me for the extra work. She was to pay for the job when it was completed.”

William L. Applegate testified that he was present when his brother and plaintiff in error were making the contract and that plaintiff in error wanted the building quicker than it would be reasonable to expect the' work to be done. That it was explained to her that it would take in the neighborhood of three or four months to do the work and she seemed satisfied.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ohrenstein v. Howell
227 Ill. App. 215 (Appellate Court of Illinois, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
111 Ill. App. 13, 1903 Ill. App. LEXIS 187, Counsel Stack Legal Research, https://law.counselstack.com/opinion/henry-v-applegate-illappct-1903.