McMillan v. Joseph P. Casey Co.

231 Ill. App. 422, 1923 Ill. App. LEXIS 175
CourtAppellate Court of Illinois
DecidedJuly 10, 1923
DocketGen. No. 7,575
StatusPublished
Cited by8 cases

This text of 231 Ill. App. 422 (McMillan v. Joseph P. Casey Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McMillan v. Joseph P. Casey Co., 231 Ill. App. 422, 1923 Ill. App. LEXIS 175 (Ill. Ct. App. 1923).

Opinion

Mr. Justice Shurtlefe

delivered the opinion of the court.

E. S. McMillan & Son filed a bill in equity in the circuit court of Vermilion county for the foreclosure of a mechanic’s lien, under section 23 of the statutes concerning liens, pertaining to public improvements. [Cahill’s Ill. St. ch. 82, fl 23.]

The county of Vermilion and also, among others, the Mid-Western Company, and Chase Harding, W. F. Slattery, P. H. Slattery and W. I. Buchanan were made parties defendant. After answering,' the Mid-Western Company and Chase Harding separately filed cross-bills in which they claim liens as subcontractors against the same funds.

One of the original parties defendant is the RankinWhitham State Bank, incorporated, which is also made party defendant to each of the cross-bills.

During the pendency of the suit all controversies between the other parties complainant and defendant appear to have been adjusted, and when the case finally came on for hearing, the contest narrowed itself down to one between the two cross complainants above named and the bank as to whether, the cross complainants had a hen and hence a superior right to a balance of funds in the hands of the county. The trial court held with cross complainants, giving them each a lien, and the bank appeals.

The material facts are these: On May 14, 1919, the Joseph P. Casey Company, incorporated, was awarded two contracts for the construction of several sections of hard road, in Vermilion county, known and designated in the written contracts as subdivision A-l of division No. 1; subdivision A-3 of division No. 3, which were parts of a system known as the Vermilion County Bond Issue Roads.

Casey & Company, under the contract for subdivision A-l of division No. 1, were to receive a consideration of $36,902.70, the county furnishing the cement, payments to be made on estimates to amount of eighty per cent and twenty per cent to be retained until final completion and acceptance of the work. Casey & Company started work on subdivision A-l and continued work until September 17, 1919, when it abandoned the job and the contract was forfeited, and the work was completed by William Cutler at an expense of $2,602.90. When the county finally accepted the road in question, there was a balance unpaid on the contract price, after paying Cutler, of $16,174.99.

This suit was started September 19, 1919, and the Rankin-Whitham State Bank on June 9, 1920, applied to the county board, representing itself to be the assignee of all moneys due to Casey & Company, under the above contract, by written assignments dated prior to the forfeiture of the contract, and offering to indemnify the county against all liability should any claims of subcontractors be thereafter established against the county. This proposition was accepted, an indemnity bond was given, and the county paid over the money a few days later to the bank, aggregating the sum of $16,174.99. Casey & Company never did any work upon the second contract and the same was forfeited and canceled. The claim of the bank rests upon three written assignments, the first dated June 11, 1919, filed with the county clerk June 12, 1919; the second dated July 3, 1919, and filed with the clerk the same day, and the third dated July 18, 1919, and filed with the clerk on that day, and these assignments are based upon loans made in excess of the amount of said balance. No decree was entered against the county of Vermilion, and by all parties the Rankin-Whitham State Bank and the fund in its hands by such assignments has been treated as the real defendant.

After these contracts were obtained from the county, Joseph P. Casey, president of the Casey Company, purchased from the Mid-Western Company, the cross complainant, one 10-ton Case roller and 1 grader for the purpose of using the same in constructing the roads mentioned in the two above-mentioned contracts, at an agreed price of $2,100, on which $700 was paid in cash, and for the balance two notes were given, one for $700, dated July 12, 1919, payable September 22,1919, and one for $500, dated July 14,1919, payable October 14, 1919, both notes drawing interest at six per cent, and by way of security a chattel mortgage was taken upon these machines.

A few days later he purchased also a pair of wheels and an axle for $165 on open account, to be used in connection with one of the above machines. These articles were shipped to Vermilion county and were actually in use by the Casey Company so long as it continued on the job.

The court found by its decree that the equitable assignments above mentioned and the notice thereof, to the county, were prior in point of time to the forfeiture of the contract and prior to the giving of notice by each of the cross complainants.

The notice of the Mid-Western Company was delivered to the county clerk and county treasurer on September 17, 1919. Two notices were served on Vermilion county authorities by the Mid-Western Company on September 17, 1919. The notices contained a description of the articles furnished by the Mid-Western Company to Casey & Company and the amount due, $1,360, for the balance of the purchase price of said machinery. In the first notice it is stated that the machinery was used for the construction of certain hard roads in Vermilion county, known as division No. 3, subdivision A-l. The second notice was the same, except it described the road as division No. 3, subdivision A-3. This notice says that the same machinery was furnished for use under the second contract.

The record also shows that a firm styled Harding & Slattery, composed of James A. Harding, Patrick H. Slattery, William P. Slattery and W. I. Buchanan, several years before the time in question in this suit, had held a contract with Vermilion county for the construction of a portion of the roads in question here which they never had completed. One of the partners, James A. Harding, died in the year 1916 and cross complainant Chase Harding was appointed his administrator, and took charge also of the affairs of the partnership. This firm had some small tools, some sheds, pumps, engines, etc.

It is shown that Harding & Slattery made a written contract with the Joseph P. Casey Company to sell them the above-mentioned articles for use in building the hard roads in Vermilion county. This was in form a conditional sale for a price of $1,690 and expressly reserved title to all articles sold. The transaction was evidenced also by a note in that amount, dated June 13, 1919, due in seventy days with interest at seven per cent. A few days later some well casings and screens were sold at a price of $210. On the back of this contract appears this indorsement: “Assigned to Chase Harding to apply on his mortgage.” Signed, Harding & Slattery, by P. H. Slattery. On the back of the note appears a blank indorsement signed in the same manner.

The Chase Harding cross-bill was originally filed in his name alone, but during the trial it was amended, over the objection of the defendant, so as to make as additional cross complainants, Patrick H. Slattery, William F. Slattery and W. I. Buchanan.

This cross-bill alleges that Chase Harding, Patrick H. Slattery, William F. Slattery and W. I. Buchanan, copartners, trading as Harding & Slattery, furnished to the Joseph P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moseman Construction Co. v. Shappert Engineering Co.
780 F. Supp. 1218 (C.D. Illinois, 1992)
Chicago Wood Piling Co. v. Anderson
39 N.E.2d 702 (Appellate Court of Illinois, 1942)
Edwin Pratt's Sons' Co. v. Schafer
7 N.E.2d 901 (Appellate Court of Illinois, 1937)
Backs v. Nelson Construction Co.
271 Ill. App. 137 (Appellate Court of Illinois, 1933)
City of Staunton v. Cole & Fauber
254 Ill. App. 377 (Appellate Court of Illinois, 1929)
New Erie Coal Co. v. H. McMullen & Sons
247 Ill. App. 515 (Appellate Court of Illinois, 1928)
Standard Oil Co. of Indiana v. Vanderboom
158 N.E. 151 (Illinois Supreme Court, 1927)
Acker v. Vanderboom
235 Ill. App. 417 (Appellate Court of Illinois, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
231 Ill. App. 422, 1923 Ill. App. LEXIS 175, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcmillan-v-joseph-p-casey-co-illappct-1923.