Buckely v. Commercial National Bank

171 Ill. 284
CourtIllinois Supreme Court
DecidedFebruary 14, 1898
StatusPublished
Cited by8 cases

This text of 171 Ill. 284 (Buckely v. Commercial National Bank) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Buckely v. Commercial National Bank, 171 Ill. 284 (Ill. 1898).

Opinion

Mr. Justice Wilkin

delivered the opinion of the court:

The only question for our decision is, whether or not the court below erred in refusing to sustain appellants’ alleged lien.

First—Are appellants, under the facts of the case, entitled to a single lien against the entire property? We think it clear that each of the houses and lots described in the bill must be treated as a separate and distinct piece of property. The houses are not so built as to constitute one block of buildings, as in the case of James v. Hambleton, 42 Ill. 308. It also appears that appellants and the owner did not, in their contract, treat the buildings as one block. The contract showed the amount of work to be performed and material furnished on each building, ranging from $544.13 to $322.76. It has been uniformly held by this court that a single lien for work or material done or furnished upon several distinct buildings on separate lots cannot be established. Thus, it was said in Culver v. Elwell, 73 Ill. 536, (on p. 540): “We understand these premises to be distinct and separated from each other, and under separate roofs. This being so, the rule in Steigleman v. McBride, 17 Ill. 300, applies, where it is said, if the work done or material furnished are upon distinct premises the lien must be against each of the several premises according to the value of the work and material on each.” This language applies with full force to the present case.

Second—Should the Superior Court have decreed a lien in favor of appellants against the property for the whole amount claimed, to be apportioned against the several lots and buildings? The fact that a single contract is entered into for labor or material to be performed or furnished on several lots and buildings will not prevent the enforcement of a lien, provided the mechanic or material-man has put himself in a position to have the same enforced against each piece of the property to the extent of labor done or materials furnished for it. All that is required in such case is that “the lien must be against each of the several premises according to the value of the work and material on each.” Steigleman v. McBride, supra; Culver v. Elwell, supra.

The difficulty with appellants’ case is, that the statement or account of their demand filed with the clerk of the circuit court is wholly insufficient to authorize a decree apportioning the lien. Section 4 of the statute under which this proceeding was had provides: “Every creditor or contractor who wishes to avail himself of the provisions of this act shall file with the clerk of the circuit court of the county in which the building, erection or other improvement to be charged with the lien is situated, a just and true statement or account or demand due him, after allowing all credits, setting forth the times when such material was furnished or labor performed, and containing a correct description of the property to be charged with the lien, and verified by an affidavit,” etc. And section 28 of the same act further provides: “No creditor shall be allowed to enforce a lien created under the provisions of this act, as against or to the prejudice of any other creditor or encumbrance or purchaser, unless a claim for a lien shall have been filed with the clerk of the circuit court, as provided in section 4 of this act, within four months after the last payment shall have become due and payable. Suit shall be commenced within two years after filing such claim with the clerk of the circuit court, or the lien shall be vacated.” (Laws of 1887, p. 219.)

Each of these houses and lots being a' separate and distinct piece of property, and the law being that appellants could only enforce a lien against each for the work and material furnished on it, it would seem to follow that a reasonable compliance with the foregoing sections of the statute required appellants to in some way indicate in their statement the amount which they claimed against each. Manifestly, the purpose of requiring the statement to be filed is that third persons dealing with the property shall have notice of the amount, nature and character of the lien, as well as the times when the material was furnished or labor performed, and thus enable them “to know, from the claim itself, that it is such as can be enforced.” (McDonald v. Rosengarten, 134 Ill. 126.) Turning to the statement here relied upon as a compliance with section 4, supra, nothing is there found to in any way indicate how much of the item of $2664 for painting, glazing, etc., on all the buildings, is claimed1 against each, nor is there anything in it from which it can be even inferred that an equal amount of work was done upon each of the seven buildings,—which, as a matter of fact,, was not the case. A party purchasing or receiving a mortgage upon either of these separate pieces of property cannot be fairly chargeable with notice, from this statement of the claim of lien, of any certain amount against that particular house and lot, and to hold it sufficient would be to ignore the reasonable purpose and object of the statute.

There is another fatal objection to this statement. It will be seen that section 4 requires it to “set forth the times when such material was furnished or labor performed.” Ho attempt is made to comply with this requirement. The only statement as to when the work was done is, “work on the aforesaid buildings was commenced January 20,1893, and completed August 18,1893,” —a period of about seven months. What information does this give as to when the work was done upon any particular building? For anything shown, either one of them may have been completed in the month of January, 1893, (unless it be the whitewashing of the basement of No. 75 and No. 77 Lake View avenue,) and yet the statement and affidavit thereto be literally true. In fact, the master found that the work was substantially finished as early as May or June, 1893, only a slight amount of it being done as late as August. The statute provides (section 28) that a lien shall not be good, as against creditors, unless the statement is filed within four months after the last payment is due. In the absence of any showing to the contrary, payment was due for this work when it was completed, but the statement was not filed until December 16, 1893. To meet this requirement it was attempted to show by the statement that the work was not completed until August 18. Therefore, if any of the buildings were completed more than four months prior to filing the statement,—which, as we have seen, may have been true for anything appearing therein,—no lien could be enforced as to those buildings, against appellee.

Speaking of a statement for mechanic’s lien, in Campbell v. Jacobson, 145 Ill. 389, we said (p. 403): “But a more serious difficulty with the statements is, that they wholly fail to set forth ‘the times when such material was furnished or labor performed. ’ That it should set forth these facts seems to be an imperative requirement of the statute. "x" * * But there is no attempt to give the date or dates of furnishing the material or the performance of the labor, nor is there anything in the statements from which those facts can be ascertained.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Automated Building Components, Inc. v. New Horizon Homes, Inc.
514 N.W.2d 826 (Court of Appeals of Minnesota, 1994)
Schwulst Gerling Co. v. Frost
269 Ill. App. 213 (Appellate Court of Illinois, 1933)
McMillan v. Joseph P. Casey Co.
231 Ill. App. 422 (Appellate Court of Illinois, 1923)
Schmidt v. Anderson
97 N.E. 291 (Illinois Supreme Court, 1911)
Shields v. Sorg
129 Ill. App. 266 (Appellate Court of Illinois, 1906)
Aurand v. Martin
58 N.E. 926 (Illinois Supreme Court, 1900)
Metzger v. McCann
92 Ill. App. 109 (Appellate Court of Illinois, 1900)
Aurand v. Martin
87 Ill. App. 337 (Appellate Court of Illinois, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
171 Ill. 284, Counsel Stack Legal Research, https://law.counselstack.com/opinion/buckely-v-commercial-national-bank-ill-1898.