City of Staunton v. Cole & Fauber

254 Ill. App. 377, 1929 Ill. App. LEXIS 213
CourtAppellate Court of Illinois
DecidedJune 11, 1929
DocketGen. No. 8,303
StatusPublished
Cited by2 cases

This text of 254 Ill. App. 377 (City of Staunton v. Cole & Fauber) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Staunton v. Cole & Fauber, 254 Ill. App. 377, 1929 Ill. App. LEXIS 213 (Ill. Ct. App. 1929).

Opinion

Mr. Justice Shurtleff

delivered the opinion of the court.

This is an appeal from a decree of the circuit court of Macoupin county on a bill in chancery in the nature of an interpleader, brought by the City of Staunton as complainant.

The bill sets out that a contract had been let by the city to Cole & Fauber, contractors, for the construction of a water supply system; that the Federal Surety Company signed the contractors’ bond; that the original contractors, after working about a year, had defaulted and abandoned the work; that the Surety Company had continued with the work, and had substantially completed it; that the city had paid to the contractors $190,815.18, and to the Surety Company $7,300 and that it had on hand, applicable to the contract, and in the bank the sum of $28,024.14; that various persons had filed lien notices under the statute, claiming to have furnished labor and materials to the contractor and claiming rights in the fund; that the contractors and the Surety Company were claiming some interest in the fund; and prayed that the court decree' the rights of the parties.

The defendants named in the bill included, in addition to the contractors and the Surety Company, the claimants who up to that time had filed notices of liens with the city.

In a supplemental bill filed by the city the same allegations were made; but additional lien claimants, those filing after the time of the first bill, were named as additional defendants. From time to time various others not named as defendants in either bill filed inter-veiling petitions or voluntarily entered their appearance; Neither the contractor .nor the Surety Company made any claim to the fund.

The cause was referred to the master in chancery, who took the evidence and filed a report of his findings and conclusions, and which report, with one exception (wherein the master had recommended a judgment against the Federal Surety Company), was approved and confirmed. This appeal is by two of the defendants — lien claimants.

The appeal of the Alton Brick Company is based solely on the fact that the master and the court allowed participation in the fund to various claimants who were not entitled to participation.

The allowances appealed from on the grounds that they were not for lienable items, or that they are for improper amounts, came under four heads:

1. Staunton National Bank, $4,539.37, given lien for money loaned to the contractors.

2. Doctors D. L. Bley, C. H. Zohlen and A. C. G-off given liens totalling $91.50 for medical services rendered to employees of contractors.

'3. A. C. Kurz, a lien in the amount of $16.50 for printing and stationery; Staunton Telephone Company, a lien in the amount of $55.60 for telephone service.

4. James P. Clow & Sons, claim excessive by $400. It is claimed the effect of the above allowances is to reduce materially the share of the appellants and of other valid lien claimants in the funds in the hands of the city.

, The appeal of the Mount Olive Oil Company is based on three grounds:

1. The allowance ox a lien against the fund to the Staunton National Bank for money loaned to the contractor.

2. The recognition by the master and the court of an assignment by one Danklef, a subcontractor (to whom the Mount Olive Oil Company sold gasoline, etc.)) to one C. Clavin of Danklef’s participation in the account to the exclusion of the Mount Olive Oil Company’s claim.

3. Failure of the master to allow a lien claim to the Mount Olive Oil Company for gasoline, etc., sold to Danklef, the subcontractor.

As to the claims of Dr. D. L. Bley, Dr. C. H. Zohler and Dr. A. C. Groff, given liens amounting to the sum of $91.50 for medical services rendered to employees of contractors, the court was in error in allowing each of these items, as liens are not allowed by statute .for services of that kind. (McMillan v. Casey Co., 231 Ill. App. 422, 311 Ill. 584; Hoier v. Kaplan, 313 Ill. 448; Rittenhouse & Embree Co. v. Brown & Co., 254 Ill. 549 and Siemer Milling Co. v. Moritz, 227 Ill. App. 459.)

It was likewise error to allow the claim of A. C. Kurz, amounting to $16.50, for printing and stationery, and the claim pf the Staunton Telephone Company, amounting to $55.60, for telephone service.

As to the- claim for a lien by the Mount Olive Oil Company, appellants ’ statement in their brief as to the facts is unchallenged by appellees. That statement is as follows:

The evidence with respect to the Mount Olive Oil Company is that this company had furnished oils, greases and gasoline to William J. Danklef, who had a contract with Cole & Fauber for moving the earth for the reservoir dam. Their evidence established an undisputed balance due from Danklef to the amount of $1,156.39. It was also undisputed from the evidence that Danklef did this work on the job and that the materials sold by the Mount Olive Oil Company had been consumed on the job in the process.

However, an assignment from Danklef of all of his claim out of the fund (which the master found to be $5,295.65) to one C. Clavin appears. This assignment finds its way somehow in the exhibits attached to the master’s report. There is no place in the transcript showing that it was introduced. There was no evidence concerning it whatsoever. The assignment is dated March 10, 1927, which is a date long after Cole & Dauber quit the contract, and long after Danklef had done the work, and long after the indebtedness to the Mount Olive Oil Company from Danklef accrued.

The master recognized this assignment, holding in his report and being sustained by the trial court, that Clavin was entitled to receive this money.

As to this claim appellees contend that the Mount Olive Oil Company, being merely a subcontractor and having had no dealings with Cole & Dauber, is not entitled to any allowance and that the claim in full was properly allowed to Clavin, assignee of William J. Danklef. In this, counsel and the court below are in error. (Siemer Milling Co. v. Moritz, supra; Alexander Lumber Co. v. Farmer City, 272 Ill. 264, 275.) The full claim of William J. Danklef amounted to $5,295.65 and by the decree was ordered paid to his assignee, C. Clavin. This.was error. The claim of the Mount Olive Oil Company, amounting to $1,156.39, should have been allowed and the same amount deducted from the Danklef claim allowed to Clavin.

A claim was allowed to James B. Clow & Sons in the sum of $3,916.35. It is substantially conceded by all parties that this was the amount of the claim of James B. Clow & Sons as originally submitted, and that there should be a deduction of $400 from this allowance which is hereby ordered.

Appellants assign error upon the allowance of the sum of $4,539.37 to the Staunton National Bank. As to the situation surrounding the merits of this claim the record shows the following state of facts

At the time Cole & Dauber were awarded the water supply contract they entered into negotiations with the bank officials supposedly looking toward temporary financing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Texas Co. v. Schriewer
38 S.W.2d 141 (Court of Appeals of Texas, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
254 Ill. App. 377, 1929 Ill. App. LEXIS 213, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-staunton-v-cole-fauber-illappct-1929.