Carey-Lombard Lumber Co. v. Jones

58 N.E. 347, 187 Ill. 203, 1900 Ill. LEXIS 2553
CourtIllinois Supreme Court
DecidedOctober 19, 1900
StatusPublished
Cited by32 cases

This text of 58 N.E. 347 (Carey-Lombard Lumber Co. v. Jones) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carey-Lombard Lumber Co. v. Jones, 58 N.E. 347, 187 Ill. 203, 1900 Ill. LEXIS 2553 (Ill. 1900).

Opinion

Mr. Justice Wilkin

delivered the opinion of the court:

Section 1 of the Mechanic’s Lien law of this State in force June 26, 1895, (Hurd’s Stat. 1897, p. 1034,) provides: “That any person who shall by any contract with the owner of a lot or tract of land, or with one whom such owner has authorized or knowingly permitted to improve the same, furnish or specially manufacture and prepare materials, fixtures, apparatus, or machinery for the purpose of, or in building, altering, repairing or ornamenting any house or other building, * * * shall be known under this act as a contractor, and shall have a lien upon'the whole of such tract of land or lot and upon the adjoining or adjacent lots of such owner constituting the same premises, * * * for the amount due to him for such material, fixtures, apparatus, machinery, services or labor, and interest from the date the same is due.’’

The very gist of the petitioner’s case, as made by the averment, is, that it contracted to furnish the materials for which it claims a lien with parties (Kane and Meyer) whom the owner (J. Russell Jones) had “authorized or knowingly permitted to improve” the premises. If that allegation is not either admitted, or proved by the petitioner, its case must fail; but if admitted by the answer or established by the evidence, then by the plain provisions of the statute its right to a lien is established to the whole of the premises, to the same extent as though the agreement under which the lumber was furnished had been made with the owner himself. Conceding there was upon the hearing an issue of fact as to whether there was such authority or permission, as counsel for appellees assume there -was, and also conceding that without a bill of exceptions or certificate of evidence we are not to presume, in support of the decree, that evidence was heard outside of the contract of leasing between the lessor and lessees, and looking to that contract alone, the petition is, in our opinion, amply sustained.

We understand counsel for appellees to contend that by the terms of the lease Kane and Meyer became original contractors for the erection of the buildings and the improvements placed upon" the lots, and that the lumber company was at most but a sub-contractor under them. Extended arguments are submitted on either side of these propositions, but we regard them of very easy solution. It cannot be seriously claimed that under the agreement the lessees contracted with Jones to furnish materials or perform any of the labor or services named in the foregoing section of the statute, by the doing of which they would, by that section, be known as “a contractor.” The statute is, as its title indicates, for the security of mechanics and those who furnish material for buildings, etc., therein named. Agreements made under its provisions are known in the law as building contracts, sometimes termed “working contracts.” The clause in the lease which obligates the lessees to erect improvements upon the leased premises is' in no sense a building contract. That clause means no more than that by the terms of the lease the tenants are to cause to be made such improvements as the landlord shall approve of, not to exceed in value $6000, that sum to be re-paid by the landlord, either in the use of the premises, or in money, if he should decide to cut short the term of five years, the improvements to be a part of the real estate and to belong to him.

A.contractor has been defined to be “one who, as an independent business, undertakes to do specific jobs of work without submitting himself to control as to the petty details.” (3 Am. & Eng. Ency. of Law, 822.)' It would scarcely be contended that under the provisions of our statute there could be such a thing as a sub-contractor’s lien unless there existed a lien in favor of an original contractor, and we assume that no one would contend that Kane and Meyer, under their contract with Jones, could have enforced a lien against the leased property for any improvements placed upon it by them under this agreement. Similar contracts have been before the courts in proceedings to enforce mechanics’ liens, and have, without exception, so far as we are advised, been held to amount to authority or consent from the owner to a vendee or lessee to make the improvements, and, in the absence of some stipulation in the agreement to the contrary, to give a lien upon the interest of the owner for materials furnished or labor performed under contracts with the vendee or lessee. In fact, it is impossible to see how it can reasonably be said that one who agrees with another that he shalkplace buildings or other improvements upon certain property does not thereby “authorize or knowingly permit” the other to improve that property.

The case of Henderson v. Connelly, 123 Ill. 98, was one in which the Hendersons sold to one S.harp certain premises, the former agreeing that when Sharp should have expended $325 in the erection of a dwelling house on the premises they would advance him, as the progress of the building justified in their opinion, $875 to aid in its completion. Sharp contracted with Connelly to do certain work upon the building, which he did. Sharp having failed to comply with his contract of purchase, the Hendersons took possession of the property and completed the house. Connelly sought to enforce a lien upon the premises for the labor performed by him, and the Hendersons resisted that claim. The decree was in favor of the petitioner, and directed the master to sell the property, and after paying the costs to pay, first, the amount due the petitioner, and the surplus to the Hendersons. On appeal the latter insisted the decree was erroneous in that it did not give them priority, at all events, for the contract price of the property, relying on Hickox v. Greenwood, 94 Ill. 266. Holding the position not well taken and the case relied on not in point, we said (p. 102): “Here it was understood in the contract of sale between the vendors and purchaser that the latter should go on and build upon the premises, and for the purpose of a cousummation of this understanding a clause was inserted in the contract of sale by which the vendors agreed to advance the purchaser $875 to assist him in the erection of a building on the premises, as the building progressed. ' The only reasonable and fair construction to be placed on this clause of the contract is, that the purchaser was authorized and empowered by the vendors to enter into contracts with builders to furnish material and erect a building on the premise's to which they held the legal title.” The doctrine of this case is recognized as being applicable to cases of leasing as well as sales in Williams v. Vanderbilt, 145 Ill. 238, where we said: “Where a lessor agrees to pay to the lessee a gross sum toward the erection of a house on the demised premises, the estate of the lessor is .bound by the mechanic’s lien,”—citing Leiby v. Wilson, 40 Pa. St. 63, and Boiler v. Aspen, 99 id. 313.

In Lumber Co. v. Nelson, 71 Mo. App. 110, the case is stated and decided as follows: “One of the stipulations in the lease from Nelson was that the lfessees should expend $20,000 in making improvements upon the leased premises, according to plans and specifications which had been agreed to. These improvements were to become the property of the lessor at the termination of the lease. In this state of the evidence it may be truthfully said the improvements on the Nelson lot, and the material necessary to make them, were made and furnished by his consent and for his benefit. He not only consented to them, but contracted with his lessees for them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Leveyfilm, Inc. v. Cosmopolitan Bank & Trust
653 N.E.2d 875 (Appellate Court of Illinois, 1995)
American Islam Society, Inc. v. Bob Ulrich Decorating Inc.
132 N.E.2d 620 (Indiana Court of Appeals, 1956)
Edward Solomon, Inc. v. Padorr
282 Ill. App. 269 (Appellate Court of Illinois, 1935)
Mackey v. Sherman
263 Ill. App. 109 (Appellate Court of Illinois, 1931)
James H. Tower Iron Works v. B. R. Realty Co.
4 R.I. Dec. 15 (Superior Court of Rhode Island, 1927)
Mancourt v. Wissel
146 N.E. 911 (Indiana Court of Appeals, 1925)
McMillan v. Joseph P. Casey Co.
231 Ill. App. 422 (Appellate Court of Illinois, 1923)
New Farley Nat. Bank v. Montgomery County
85 So. 31 (Alabama Court of Appeals, 1919)
Wood v. Isgrigg Lumber Co.
123 N.E. 702 (Indiana Court of Appeals, 1919)
Storm v. Thompson
185 Iowa 309 (Supreme Court of Iowa, 1919)
Loeff v. Meyer
209 Ill. App. 382 (Appellate Court of Illinois, 1918)
Ogburn Gravel Co. v. Watson Co.
190 S.W. 205 (Court of Appeals of Texas, 1916)
Arctic Lumber Co. v. Borden
211 F. 50 (Ninth Circuit, 1914)
Stewart v. Talbott
146 P. 771 (Supreme Court of Colorado, 1913)
Dierks & Sons Lumber Co. v. Morris
156 S.W. 75 (Missouri Court of Appeals, 1913)
Boyer v. Keller
101 N.E. 237 (Illinois Supreme Court, 1913)
McGuinn v. Federated Mines & Milling Co.
141 S.W. 467 (Missouri Court of Appeals, 1911)
Chicago Brick Co. v. McLester
165 Ill. App. 114 (Appellate Court of Illinois, 1911)
Halstead v. Stahl
94 N.E. 1056 (Indiana Court of Appeals, 1911)
Potter v. Conley
112 P. 608 (Supreme Court of Kansas, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
58 N.E. 347, 187 Ill. 203, 1900 Ill. LEXIS 2553, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carey-lombard-lumber-co-v-jones-ill-1900.