Seeman v. Biemann

84 N.W. 490, 108 Wis. 365, 1900 Wisc. LEXIS 208
CourtWisconsin Supreme Court
DecidedDecember 7, 1900
StatusPublished
Cited by31 cases

This text of 84 N.W. 490 (Seeman v. Biemann) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seeman v. Biemann, 84 N.W. 490, 108 Wis. 365, 1900 Wisc. LEXIS 208 (Wis. 1900).

Opinion

MaRshall, J.

The principal question presented for adjudication is raised by exceptions to the findings of fact respecting the cause of action pleaded by the owner of the building against defendants Jones and Forster for a reformation of the bond indorsed upon the back of the building contract making it run to such owner iiistead of to his architect, Dohmen. The evidence upon which the conclusions of the trial court are based has been examined without disclosing any warrant for this court to say they are clearly against the preponderance of such evidence. Olear and satisfactory evidence of mutual mistake, or of mistake upon one side and fraud upon the other in reducing a contract to writing, is required to -warrant changing such writing with a view to express the actual agreement of the parties. The direct evidence here is substantially all to the effect that the obligors [372]*372knew when they signed the bond that Dohmen was the ob-ligee therein named. They were told that he wanted a bond from the builders and signed the paper upon a request to become bondsmen for him, as they understood it, and in a measure because of their acquaintance with and regard for. him. Forster wrote the name of Dohmen in the bond as obligee, which leaves no room to doubt that he knew its import when he signed it and that he became a party thereto with full understanding that he thereby became obligated only to Dohmen. True, there is some reason to say the bondsmen must have known that the object of the bond, so far as the owner of the building and the contractor were concerned, was to secure the former; but that does not militate against the theory that they did not intend to become parties to effecting'such purpose. If they did not sign the paper for the benefit of the owner of the building or perpetrate any fraud upon him, whereby he, in the exercise of ordinary care, was induced to accept such paper in the belief that it ran to him as obligee, it cannot be properly changed so as to carry out his purpose. There is no evidence to sustain fraud and no satisfactory evidence of mutual mistake.

The court, in failing to charge the contractors, Biemann & Co., with damages for delay in completing the building by the time named in the contract, must have entirely overlooked the provision thereof that “unless the contractor shall notify the architecfcin writing, in each instance, of his intention to claim an extension of time, within twenty-four hours from the time of the occurrence of the alleged cause of delay, he shall thereby waive all right to said extension.” Parties have a right to make such a stipulation in a building contract, and if they do so they are bound by it the same as by any other part of their agreement. If a contractor agree in writing to construct a building without taking reasonable time therefor, or agree that relief from delays caused by unforeseen causes shall depend on claims being [373]*373made therefor in a particular manner and within a specified time, he must comply with such conditions or he will be held to have waived such relief.

The building was to have been completed by May 22, 1897. It was not finished till July 15, 1897. There was a ■delay of one month and twenty-three days. There was no •evidence of any claims being made for allowances of time as provided in the contract, so the contractors were clearly liable to the appellant Farr, upon the proper rule for computing his damages under the agreement.

That brings us to the necessity of determining, whether the parties agreed upon $10 a day as the amount to be allowed as damages for each day’s delay, or whether that clause in the contract was intended as a mere security for the completion of the building by the time agreed upon, hence should be considered as a penalty and the recoverable damages be limited to such as proof shows Farr actually ■sustained.

The law is too well settled to permit any reasonable controversy in regard to it at this time, that where parties stipulate in their contract for damages in the event of a breach of it, using appropriate language to indicate that the damages are agreed upon in advance, and such damages are ■unreasonable considered as liquidated damages, the,stipulated amount will be construed to be a mere forfeiture or penalty and the recoverable damages be limited to those actually sustained. "While courts adhere to the doctrine that the intention of the parties must govern in regard to whether damages mentioned in their contract are liquidated, they uniformly take such liberties in regard to the matter, based ■on.arbitrary rules of construction, so called, as may be neces.sary to effect judicial notions of equity between parties, guided of course by precedents that are considered to have the force of law, sometimes calling that a penalty which the .parties call stipulated damages, and that which the parties [374]*374call a penalty stipulated damages, where otherwise an unconscionable advantage would be obtained by one person -over another. The judicial power thus exercised cannot properly be justified under any ordinary rules of judicial construction. Such rules permit courts to go as far as possible to effect the intent of the parties where it is left obscure by their language so long as such intent can be read out of the contract without violating the rules of language or of law. But in determining whether an amount agreed upon as damages was intended as liquidated damages or as a penalty, rules of language are ignored and the expressed intent of parties is made to give way to the equity of the particular-case, having due regard to precedents as before indicated. Here the damages are said by the parties to be agreed upon at $10 per day for each day’s delay, to be deducted from the contract price, indicating about as clearly as language can that they intended that such damages should be considered as irrevocably stipulated damages; yet the uniform rule is. that such circumstance does not absolutely control.

This court, in harmony with the weight of authority, early adopted the arbitrary rule that where damages may be readily computed and the stipulated damages, so called, are-largely in excess of actual damages, the court will disregard what the parties say they intended, and presume that they intended what is fair and reasonable under the circum-however much that may violate their language. Pierce v. Jung, 10 Wis. 30; Fitzpatrick v. Cottingham, 14 Wis. 219. In Berrinkott v. Traphagen, 39 Wis. 219, there is-found quoted with approval from 3 Parsons, Cont. 156, language to the effect that parties may contract for stipulated damages at their pleasure, but such damages only as the law says are liquidated according to the artificial rules which have been adopted to justify courts in saying what the parties intended are in fact to be regarded as such damages-The most significant of such rules is the one above referred [375]*375to. Applying it to the case before us, the stipulation of $10 per day for delay must be held to be a penalty merely, and not necessarily recoverable to the whole amount. The rental value of the property as found by the court was $38 per month. That is the true measure of actual damages, since there were no special circumstances shown by the evidence, brought home to the knowledge of the contractor at the time of the making of the contract, from which we can say the damages which the parties then had in contemplation as the probable result of a breach of the contract as to time of completing the building were other than loss of use for the period of delay. Guetzkow Bros. Co. v. A. H.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wassenaar v. Panos
331 N.W.2d 357 (Wisconsin Supreme Court, 1983)
H. & M. HEATING CO. v. Andrae
150 N.W.2d 379 (Wisconsin Supreme Court, 1967)
Case v. Case
124 N.E.2d 856 (Hamilton County Probate Court, 1955)
State Ex Rel. Switzer v. Overturff
33 N.W.2d 405 (Supreme Court of Iowa, 1948)
Feiges v. Racine Dry Goods Co.
285 N.W. 799 (Wisconsin Supreme Court, 1939)
Terry v. United States Fidelity & Guaranty Co.
82 P.2d 532 (Washington Supreme Court, 1938)
Minn Billiard Co. v. Schwab
190 N.W. 836 (Wisconsin Supreme Court, 1922)
Sheffield-King Milling Co. v. Jacobs
175 N.W. 796 (Wisconsin Supreme Court, 1920)
Grant Marble Co. v. Marshall & Ilsley Bank
165 N.W. 14 (Wisconsin Supreme Court, 1918)
Elzey v. City of Winterset
172 Iowa 643 (Supreme Court of Iowa, 1915)
W. H. Pipkorn Co. v. Tratnik
152 N.W. 141 (Wisconsin Supreme Court, 1915)
Hume v. Seattle Dock Co.
137 P. 752 (Oregon Supreme Court, 1914)
Kelleher v. Reedal
143 N.W. 193 (Wisconsin Supreme Court, 1913)
J. I. Case Threshing Machine Co. v. Souders
96 N.E. 177 (Indiana Court of Appeals, 1911)
Herron v. M. Rumley Co.
1911 OK 267 (Supreme Court of Oklahoma, 1911)
Kelly v. Johnson
95 N.E. 1068 (Illinois Supreme Court, 1911)
Foss v. Heineman
128 N.W. 881 (Wisconsin Supreme Court, 1910)
Grant Marble Co. v. Abbot
124 N.W. 264 (Wisconsin Supreme Court, 1910)
West Allis Lumber Co. v. Wiesenthal
124 N.W. 498 (Wisconsin Supreme Court, 1910)
Rieser v. Commeau
129 A.D. 490 (Appellate Division of the Supreme Court of New York, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
84 N.W. 490, 108 Wis. 365, 1900 Wisc. LEXIS 208, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seeman-v-biemann-wis-1900.