Goodman v. Baerlocher

60 N.W. 415, 88 Wis. 287, 1894 Wisc. LEXIS 52
CourtWisconsin Supreme Court
DecidedOctober 2, 1894
StatusPublished
Cited by17 cases

This text of 60 N.W. 415 (Goodman v. Baerlocher) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Goodman v. Baerlocher, 60 N.W. 415, 88 Wis. 287, 1894 Wisc. LEXIS 52 (Wis. 1894).

Opinion

Pinney, J.

1. The original contractors, Gross & Heimer, had not performed their contract when the first building, being in an incomplete condition, was destroyed. It had not been delivered to or accepted by the owner, and was therefore at the risk of the contractors, and the destruction of the building did not excuse them from performing the contract. Dermott v. Jones, 2 Wall. 1; Adams v. Nichols, 19 Pick. 275; Tompkins v. Dudley, 25 N. Y. 272; School Trustees v. Bennett, 27 N. J. Law, 515. In Tompkins v. Dudley, supra, it was held that the owner of the lots might recover back from his contractor payments in such case which he had made on account of the building. In this case the building had not only not been completed, but it had been utterly destroyed, so that the owner of the ground had received no benefit from the materials and work and labor employed in attempting to build it, and the original contractors could not have recovered anything or enforced [292]*292a lien for what had been furnished or done in attempting to construct and erect the building. Whether the subcontractors or material men and laborers under the contractors are in any better situation, is the question to be determined;

Sec. 3314, R. S., provides that: “Every person who as principal contractor, . . . performs any wrork or labor, furnishes any material, . . . in or about the erection, construction, ... of any dwelling house, building, . . . shall haw a lien thereon, and upon the interest of the owner of sueh dwelling house, building, ... in and to the land upon which the same is situated, . . . not exceeding in extent,” etc. And see. 3315 extends the right to “ every person who, as subcontractor of a principal contractor, or employee of any contractor or subcontractor, performs any work or labor for, or furnishes any materials' to a principal contractor or subcontractor in any of the cases mentioned in the preceding section,” if within sixty days thereafter he gives the specified notice in writing to the owner, or his agent, of the property to be affected by such lien, “ with a statement of the labor performed or materials furnished, and the amounts due from such principal contractor or subcontractor, and that he claims the lien given ” by oh. 143, R. S.

The lien provided by the statute is in the nature of a charge on land given by statute to the persons named therein to secure a priority or preference of payment for the performance of labor or supply of materials to buildings or other improvements, to be enforced against the particular property in which they have become incorporated, in the manner and under the limitations therein expressly provided.” Phil. Mech. Liens, § 9. In Van Stone v. Stillwell & B. Mfg. Co. 142 U. S. 128, 136, it was said, in substance, that the lien is given to secure priority of payment of the price and value of work performed and the maté-.rials furnished; that “ it is the use of the materials fur-[293]*293nishecl and labor expended by the contractor, whereby the building becomes a part of the freehold, that gives the material man or laborer his lien under the statute.” The object is not only to encourage building, but to afford the contractor, material man, or laborer security upon and against the property of the owner materially increased in value by the materials and labor wrought into it, and so rests upon the strongest equitable basis, for the building becomes a part of the realty, and it is the principal matter, to which the lien on the realty seems to be an incident, and without which the lien on the building would be fruitless or of little value. In Mallory v. La Crosse Abattoir Co. 80 Wis. 170, 175, in which the remedy given by this statute to subcontractors, laborers, and material men was considered, it was said: “ The theory of the law giving to laborers and material men specific liens upon the property upon which their labor was performed or their materials used seems to be that, because the value of such property has been enhanced thereby, it is just that the property should be specifically charged with the sums expended thereon for those purposes. The reason of the law extends to expenditures on the property by subcontractors as well as by those who contract directly with the owner.” And the cases, of Munger v. Lenroot, 32 Wis. 544, and Winslow v. Urquhart, 39 Wis. 260, really rest upon this ground.

In this case the defendant Baerlocher, the owner of the lots, has received no benefit whatever from the material and labor in question, and the principal contractors were clearly not entitled to any compensation for them, nor to any lien on the lots, on that account. This case is not, we think, within the statute relied on, for the statute does not extend to the case where no building is erected or constructed and no benefit has passed to or been accepted by the lot owner. To apply the statute so as to extend its provisions to such a case as the present would, we think, [294]*294be giving it not merely a liberal, but a most latitudinarián and unreasonable, construction, and to mistake the incident as the subject of the lien for the principal thing which gives increased value to the ground upon which it has been erected, and would require the lot owner to answer through his property for the materials and labor that had entered into the building destroyed, from which he has not and could not derive any benefit, and would leave him without any remedy whatever against the principal contractor; making him practically an insurer of property over which he had not acquired control, and which remained at the risk of the contractors. If the second building shall be destroyed before its completion, it might thus transpire that the lot owner, according to the respondents’ contention, might be wholly deprived of his lots without any fault of ■his own, and without having received any benefit or compensation therefor whatever.

Under a statute in Pennsylvania not materially different from the one in question, it has been held that the lien on the building is the principal thing, and the lien upon the land on which it is situated is an incident of the completion of the building, and that when the building is destroyed, by fire or otherwise, before completion, there can be no lien against the land on which it was attempted to erect it; that the lien shares the fate of the building; and that the reason for binding the land ceases with the destruction of the. building. Presbyterian Church v. Stettler, 26 Pa. St. 246; Wigton and Brook's Appeal, 28 Pa. St. 161; Linden Steel Co. v. Rough Run Mfg. Co. 158 Pa. St. 238, 246. This view is sustained by Coddington v. Dry-Dock Co. 31 N. J. Law, 477, 480, where it is said: “ The act did not intend to give a lien on labor not performed on the land upon which it is to be a lien, nor on lumber before it was made land. . . . As soon as the lumber is converted into land, then, the land is seized by the lien by reason of the building, and [295]*295the building because it is a part of the land; and from thence it follows that if the land and the building, by any chance, become separated, the lien is lost on both,— the land, because it has lost the building and the increased value thereby given to it; and the building, because separated from the land.” Houck, Liens, §§ 203-205; Schukraft v. Ruck, 6 Daly, 1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Wright
196 B.R. 97 (W.D. Wisconsin, 1995)
Boston Old Colony Insurance v. International Rectifier Corp.
284 N.W.2d 93 (Wisconsin Supreme Court, 1979)
Gleich v. Earnest
173 N.E. 212 (Ohio Court of Appeals, 1930)
Bailey Lumber Co. v. General Construction Co.
133 S.E. 135 (West Virginia Supreme Court, 1926)
In re Jaeger
284 F. 130 (W.D. Wisconsin, 1921)
Taylor v. Dall Lead & Zinc Co.
111 N.W. 490 (Wisconsin Supreme Court, 1907)
Halsey v. Waukesha Springs Sanitarium Co.
104 N.W. 94 (Wisconsin Supreme Court, 1905)
Humboldt Lumber Mill Co. v. Crisp
81 P. 30 (California Supreme Court, 1905)
Lang v. Menasha Paper Co.
96 N.W. 393 (Wisconsin Supreme Court, 1903)
Vogt v. Hecker
95 N.W. 90 (Wisconsin Supreme Court, 1903)
State ex rel. Kaltenbach v. Shiel
90 N.W. 112 (Wisconsin Supreme Court, 1902)
Seeman v. Biemann
84 N.W. 490 (Wisconsin Supreme Court, 1900)
Watkins v. Bugge
77 N.W. 83 (Nebraska Supreme Court, 1898)
Bailey v. Costello
68 N.W. 663 (Wisconsin Supreme Court, 1896)
Bratton v. Ralph
42 N.E. 644 (Indiana Court of Appeals, 1896)
Thorn v. Mayer
33 N.Y.S. 664 (Superior Court of New York, 1895)
Thorn v. Mayer
67 N.Y. St. Rep. 389 (Superior Court of Buffalo, 1895)

Cite This Page — Counsel Stack

Bluebook (online)
60 N.W. 415, 88 Wis. 287, 1894 Wisc. LEXIS 52, Counsel Stack Legal Research, https://law.counselstack.com/opinion/goodman-v-baerlocher-wis-1894.