Tompkins v. . Dudley

25 N.Y. 272
CourtNew York Court of Appeals
DecidedSeptember 5, 1862
StatusPublished
Cited by71 cases

This text of 25 N.Y. 272 (Tompkins v. . Dudley) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tompkins v. . Dudley, 25 N.Y. 272 (N.Y. 1862).

Opinion

On the 31st of August, 1857, Cornelius Chambers, by a written contract, agreed to make, erect, build and furnish for the plaintiffs a school-house, according to certain plans and specifications, and to furnish the materials for the sum of $678.50. The school-house was to be completed on the 1st day of October, 1857. The defendants guaranteed the performance of the contract on the part of the builder. The building was not completed on the 1st day of October, and it was burned down on the night of the 5th of October. The judge who tried the cause found, as matter of fact, that the contract was substantially performed by Chambers, but that the building was not entirely completed according to the specifications, there remaining to be done a small amount of painting and the hanging of the window blinds, and that the same had not been formally accepted nor the key delivered on the *Page 273 5th of October. This action is brought to recover the money paid on account to Chambers as the building progressed, and for the damages which the plaintiffs have sustained by reason of the non-completion of the contract, the fulfillment of which was guaranteed by the defendants. It is undeniable that the school house was not completed, nor delivered and accepted by the plaintiffs at the time of its destruction. They had a right to insist upon the completion of the contract according to its terms, and the builder did not allege or pretend that he had completed it. A substantial compliance with the terms of the contract will not answer when the contractor, as in this case, admits and concedes that the work was incomplete; he was still in possession, engaged in its completion. According to the testimony, about $60 was yet to be expended on the building. Had the builder completed the building and complied with his contract at the time of the destruction of the school house? I am constrained to say he had not. He was not only to complete it in accordance with its terms, but was to deliver it over to the plaintiffs thus finished, or offer to deliver it, before his whole duty was performed. Now it is undeniable that the builder did not do this. A portion of the work was yet to be done; the builder was still in possession, and actually engaged in the work of completion at the time of its destruction. This court has declared the law in this State to be, that a contract for the building of a vessel, or other thing in esse, does not vest any property in the party for whom it is to be constructed during the progress of the work, nor until it is finished and delivered, or at least ready for delivery, and approved by such party. It is said all the authorities agree in this. (Andrews v. Durant, 1 Kern., 35, and the authorities there cited.) And it was also held that the law is the same, though it be agreed that payment shall be made to the builder during the progress of the work, and such payments are made accordingly. In Mucklow v. Mangles (1 Taunt., 218), which arose out of a contract for building a barge, the whole price was paid in advance, the vessel was built and the name of the person who contracted for it was painted on the stern, *Page 274 yet it was held that the title remained in the builder. LAWRENCE, J., said, "No property vests till the thing is finished and delivered." In Merritt v. Johnson (7 John., 473), where a sloop was agreed to be built and one-third of the price was to be paid when one-third of the work was done; two-thirds when two-thirds were done; and the balance when it was completed, and before it was finished it was sold on execution against the builder, after more than one-third had been done, and more than that proportion of the price had been paid, the court held that the vessel was the property of the builder and not of the person who engaged it to be constructed. The court says, in its opinion, "The sloop did not become his property (the person for whom it was built) until finished and delivered." The Supreme Court of Massachusetts, in Adams v. Nichols (19 Pick., 275), a case quite like the present, say: "It is not very material to consider whose property the house was before its destruction. The principal defendant had contracted to build and finish a house on the plaintiff's land. After the conflagration, he might have proceeded, under the contract, and if he had completed a house according to the terms of his agreement the plaintiff would have been bound to perform his part of the stipulations. So if in any stage of its progress he had seen fit to remove any part of the materials, and substitute others, the plaintiff could not complain. They must, therefore, be deemed to be at his risk. And if he had not intended to incur this risk, he should otherwise have stipulated in his agreement. Had the article to be made been a chattel, or a coach, or a vessel, it is extremely clear that the materials in the first place, and the article itself, in every stage of its manufacture, from its inception to its completion, would have been at the risk of the builder. Now it is not easy to preceive how it can make any difference in the construction or operation of the contract, that the thing manufactured, was to be attached to the freehold."

The builder, in the present case, by his own contract, created a liability and incurred a duty, which the defendants guaranteed *Page 275 he should perform, and which he has not performed. In justification of such non-performance, he alleges the destruction of the building by fire and inevitable accident, without any fault on his part. The law is well settled, that this is no legal justification for the non-performance of the contract. This subject was most carefully considered and elaborately discussed in the case of Harmony v. Bingham (2 Kern., 99), and it was then held by this court, that when a party is prevented by the act of God from discharging a duty created by the law, he is excused; but when he engages unconditionally, by express contract, to do an act, performance is not excused by inevitable accident or other unforeseen contingency not within his control. EDWARDS, J., says: "This rule has been uniformly followed, and that, too, even in cases in which its application has been considered by the court as attended with great hardships." RUGGLES, J., said: "It is a well-settled rule of law, that when a party, by his own contract, absolutely engages to do an act, it is deemed to be his own fault and folly that he did not thereby expressly provide against contingencies, and exempt himself from responsibility in certain events; and in such a case, therefore, that is, in the instance of an absolute and general contract, the performance is not excused by an inevitable accident or other contingency, although not foreseen by or within the control of the party." These principles have been applied by the Supreme Courts of Massachusetts, Connecticut and New Jersey, in cases almost entirely analogous to the one now under consideration. InAdams v. Nichols (supra), the action was upon a bond executed by Nichols, one of the defendants, as principal, and by Selkirk, the other defendant, as surety, conditioned that Nichols should fully perform an agreement in writing, by which he contracted to erect a dwelling house for the plaintiff, on the plaintiff's land. It was agreed that, at the time of the execution of the bond and agreement, the plaintiff advanced to Nichols the sum of $400, in pursuance of such agreement; that subsequently Nichols commenced building the house and continued to work on it until 23d of August, 1836 (the agreement *Page 276

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Halmar Construction Corp. v. New York State Environmental Facilities Corp.
76 A.D.2d 957 (Appellate Division of the Supreme Court of New York, 1980)
Warren Bros. Div. v. State
59 A.D.2d 1039 (Appellate Division of the Supreme Court of New York, 1977)
New Era Homes Corp. v. Forster
86 N.E.2d 757 (New York Court of Appeals, 1949)
Mohrmann v. Kob
182 Misc. 571 (New York Supreme Court, 1944)
Beechwood Gun Club, Inc. v. City of Beacon
153 Misc. 358 (New York Supreme Court, 1933)
Salinger v. General Exchange Ins. Corp.
250 N.W. 13 (Supreme Court of Iowa, 1933)
Mittry v. United States
73 Ct. Cl. 341 (Court of Claims, 1931)
F. M. Gabler, Inc. v. Evans Laboratories, Inc.
129 Misc. 911 (New York Supreme Court, 1927)
Heinse v. Howard
138 A. 255 (Court of Appeals of Maryland, 1927)
Dearstine v. Dunckel
130 Misc. 281 (New York Supreme Court, 1926)
Greenberg v. Mager
115 Misc. 503 (Appellate Terms of the Supreme Court of New York, 1921)
Ahlgren v. Walsh
158 P. 748 (California Supreme Court, 1916)
Richards & Co. v. Wreschner
174 A.D. 484 (Appellate Division of the Supreme Court of New York, 1916)
Maryland Casualty Co. v. Town of Wellston
1915 OK 121 (Supreme Court of Oklahoma, 1915)
H. Wales Lines Co. v. Hartford City Gas Light Co.
93 A. 129 (Supreme Court of Connecticut, 1915)
Cameron-Hawn Realty Co. v. . City of Albany
101 N.E. 162 (New York Court of Appeals, 1913)
American Towing & Lightering Co. v. Baker-Whiteley Coal Co.
84 A. 182 (Court of Appeals of Maryland, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
25 N.Y. 272, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tompkins-v-dudley-ny-1862.