Mittry v. United States

73 Ct. Cl. 341, 1931 U.S. Ct. Cl. LEXIS 230, 1931 WL 2425
CourtUnited States Court of Claims
DecidedDecember 7, 1931
DocketNo. J-604
StatusPublished
Cited by7 cases

This text of 73 Ct. Cl. 341 (Mittry v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mittry v. United States, 73 Ct. Cl. 341, 1931 U.S. Ct. Cl. LEXIS 230, 1931 WL 2425 (cc 1931).

Opinion

Williams, Judge,

delivered the opinion:

The plaintiffs in this suit seek to recover the sum of $32,545.16. Their claims are: (1) $30,887.14, the cost of reconstructing one of the group of buildings being constructed by plaintiffs under a contract with the Veterans’ Bureau, which, when practically completed, but prior to acceptance by the Government, was partially destroyed by a gas ex[356]*356plosion; (2) $1,658.02 liquidated damages deducted by the defendant on final settlement with plaintiffs for the work done under the contract.

The plaintiffs on December 31, 1924, entered into a contract with the Veterans’ Bureau to furnish all necessary labor and material required to construct and finish complete all work of “ general construction ” of a group of buildings at the U. S. Veterans’ Hospital at San Fernando, California, in accordance with specifications covering the same, at a total cost to the defendant of $755,900. The entire work was to be completed within 350 calendar days from the receipt of official notice to begin work. The contract provided for the deduction of liquidated damages at the rate of $250 for each day of delay in completing the work beyond the 350 days stipulated in the contract.

The contract provided:

“Aeticle III. * * * All work when finished shall be delivered in a complete and perfect state. * * *
“Article XIII. * * * The contractor shall * * * be responsible for the proper care and protection of all materials delivered and work performed by him until the completion and final acceptance of same.”

One of the buildings covered in the contract, building No. 6, was designated as the Women’s General Medical Building. Three separate contracts were entered into by the United States with as many independent contractors for the plumbing, heating, and electrical work, which, Avith the plaintiffs’ work, was required to complete building No. 6. No one of the four contractors having work to do on building No. 6 was under the supervision of any one of the other contractors, and all were required to coordinate their respective portions of the work. The United States also entered into a contract with the Southern California Gas Company for the delivery of gas to the mains of the hospital during the period from November 1, 1925, to June 30, 1926.

After the award of the contract and as a basis of determining the amount of the progress payments, the plaintiffs prepared and the Veterans’ Bureau approved a schedule of costs, under the specifications of the contract, by which the [357]*357sum of $55,108.00 was allocated as the cost of constructing building No. 6.

The plaintiffs were notified on January 19, 1925, to begin work, which notice automatically fixed January 4, 1926, as the elate for the completion of the work. The plaintiffs duly proceeded with their work, made the required monthly progress reports, and received monthly payments of approximately 90% of the value of the work in place until October, 1925. The United States retained 10% of the monthly payments until final acceptance of the work embraced by the contract.

Shortly before eleven o’clock on the morning of December 14, 1925, building No. 6 was severely damaged as the result of an explosion caused by an accumulation of gas beneath the building. At the time of the explosion the plaintiffs had substantially completed the building, except for some sweeping, window washing, lock adjusting, painting, etc. There had been no final inspection or acceptance of the building by the United States.

On January 4, 1926, the date for the completion of the work, the United States accepted all the buildings covered by the plaintiffs’ contract except building No. 6. There was then due to the plaintiffs under their contract, including the percentage of progress payments retained, $102,655.72, which sum the United States refused to pay until building No. 6 was completed.

Immediately following the explosion the superintendent of construction requested the Veterans’ Bureau to make an investigation and determine the cause of the explosion and the responsibility for it. A board of inquiry was appointed and made an exhaustive investigation. Its conclusions, which we have found are fully sustained by the record herein, are set out in Finding IX and need not be restated in detail here. They show that the explosion which wrecked building No. 6 was caused by the negligence of two independent contractors, the plumbing contractor, and the Southern California Gas Company.

In view of the fact the explosion was not caused by any ■fault or negligence on the part of either the plaintiffs or the [358]*358defendant, and the obligations imposed upon plaintiffs by the contract to construct and deliver to the Government a building “ in a complete and perfect state,” plaintiffs can not recover the cost incurred by them in reconstructing building No. 6. The building at the time of the explosion had not been inspected and accepted by the Government. It is true work upon the building was substantially finished and was ready for inspection, but until its final inspection and acceptance by the Government, the plaintiffs, under Article XIII of the contract, were responsible for its proper care and protection. The Government was entitled to receive a completed building.

The rule is well settled that where a contractor undertakes to erect a building, and during the process of construction the building is injured or destroyed without fault of either party to the contract, the contractor is still bound by his undertaking to complete the building, and is liable in damages if he fails to do so. Day v. United States, 48 C. Cls. 128, 245 U. S. 159; United States v. U. S. Fidelity & Guaranty Co., 236 U. S. 512; Atlantic, Gulf, etc., Co. v. Philippine Islands, 219 U. S. 17; Simpson v. United States, 172 U. S. 372; Dermott v. Jones, 2 Wall. 1.

In Dermott v. Jones, supra, the court held that performance of a contract to build a house for another on the soil of such person, and that the work should be executed, finished, and ready for use and occupation, and to be delivered over so finished and ready to the owner of the soil, at a day named, is not excused by the fact that there was a latent defect in the soil, in consequence of which the walls sank and cracked, and the house, having become uninhabitable and dangerous, had to be taken down and rebuilt. The court said:

“ It is a well-settled rule of law that if a party by his contract charge himself with an obligation possible to be performed, he must make it good, unless its performance is rendered impossible by the act of God, the law, or the other party. * * * If a tenant agree to repair, and the tenement be burned down, he is bound to rebuild. A company agreed to build a bridge in a substantial manner, and to keep it in repair for a certain time. A flood carried it away. It [359]*359was held that the company was bound to rebuild.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

No. 75-1765
551 F.2d 717 (Sixth Circuit, 1977)
Arctic Contractors, Inc. v. State
564 P.2d 30 (Alaska Supreme Court, 1977)
Hines, Inc. v. United States
551 F.2d 717 (Sixth Circuit, 1977)
John C. Kohler Co. v. United States
498 F.2d 1360 (Court of Claims, 1974)
John McShain, Inc. v. United States
375 F.2d 829 (Court of Claims, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
73 Ct. Cl. 341, 1931 U.S. Ct. Cl. LEXIS 230, 1931 WL 2425, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mittry-v-united-states-cc-1931.