McGowan v. United States

35 Ct. Cl. 606, 1900 U.S. Ct. Cl. LEXIS 17, 1900 WL 1488
CourtUnited States Court of Claims
DecidedOctober 22, 1900
DocketNo. 19806
StatusPublished
Cited by3 cases

This text of 35 Ct. Cl. 606 (McGowan v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McGowan v. United States, 35 Ct. Cl. 606, 1900 U.S. Ct. Cl. LEXIS 17, 1900 WL 1488 (cc 1900).

Opinion

Peedle, J.,

delivered the opinion of the court:

The contract, made part of the petition herein, provides for the construction of the stone masonry of the walls of the superstructure of the court-house and post-office building in the city of Pittsburg.

The work thereon was divided into three divisions, designated as the first, second, and third divisions; the first division [616]*616embraced the masonry of the superstructure of the building, from the water table to the top of the second-floor line; the second division was from the seeond-floor line to the top of the third-story cornice; and the third division being all the masonry work above the last-named point to complete the building.

From an examination of the statutes making appropriations from time to time to continue the prosecution of the work, it is evident that the work was divided as indicated, in order that such appropriations mig’ht not be exceeded in the prosecution of the work. (Act August 7, 1882 (22 Stat. L., 302, 305); act March 3, 1883 (22 Stat. L., 603, 601); act August 4, 1886 (24 Stat. L., 222, 223); act March 3, 1887 (24 Stat. L., 509, 511), and numerous other acts.)

Under the terms of the contract the claimant’s decedent obligated himself to furnish all the labor and materials required to complete the first division for $64,041 and to complete the same within ten months from the time the possession of the building was given to him; and he further obligated himself, if ordered by the defendants so to do, to complete the second division for the sum of $130,414 within seven months from the date of the order for the commencement of work on said second division; and to complete the work on said third division, if ordered by the defendants so to do, within seven months therefrom for the sum of $180,517.

Pursuant to the contract thus entered into, the contractor, in September, 1886, was given possession and began work on the first division of the building, but he did not complete the same until about September 26, 1887, or a little more than twelve months from the time he commenced work. For the work so performed he was paid the sum of $45,742.60, leaving a difference Between his bid and the amount paid of $18,298.40.

About one month after he had commenced work on the first division of the building, as set forth in the findings, he was notified by the Supervising Architect that he would be required to proceed with the work on the second division.

That part of the contract material to the case is as follows:

“It is further covenanted and agreed bjr and between the parties hereto, that if the said party of the second part shall [617]*617fail to prosecute the work herein contracted for with such diligence as in the judgment of the party of the first part will insure the completion of the said work within the time here-inbefore provided, or shall fail to comply with any of the terms of this contract, and thereby, in the judgment of the party of the first part, hazard the satisfactory completion of the work as hereinbefore stipulated, the said party of the first part is authorized and empowered, after eight days’ due notice thereof in writing, served personally upon or left at the shop, office, or usual place of abode of the said party of the second part, or with his agent, and the said party of the second part having failed to take such action within said eight days as will, in the judgment of the party of the first part, remedy the default for which said notice was given, to take possession of the said work in whole or in part, and of whatever machinery, tools, or materials belonging to the said party of the second part and employed thereon, and to complete the said work, and to supply the labor, materials, and tools of whatever character necessary to be purchased dr supplied by reason of the default of the said party of the second part, and the actual cost thereof shall bo deducted from any moneys due or owing to the said party of the second part on account of this contract, and if that amount be not due, then the actual cost thereof shall be repaid to the party of the first part on demand. ”

In the judgment of the Supervising Architect the claimant’s decedent failed to prosecute the work with that degree of diligence which insured the completion thereof within the time provided in the contract; and availing themselves of that provision of the contract relating thereto, the defendants, through their agent, the Supervising Architect, under date of September 16, 1887, notified the contractor in writing, as set forth in the findings, that unless he took such action within eight days therefrom as would remedy his default they would take possession of the work in whole, including his machinery, tools, and materials used in connection therewith, and complete the building, and that whatever labor, material, and tools of whatever character became necessaiy therefor would be purchased or supplied and the actual cost thereof deducted from any monej^s due him on account of said contract, “and if that amount be not due, then the actual cost thereof shall be repaid to the party of the first part on demand.”

Thereafter, and about the time of the completion of the [618]*618ñrst division of the building, the claimant’s decedent, as set forth in the findings, notified the Supervising Architect:

“That by reason of serious complications I am unable to complete the remainder of my contract, and hereby relinquish all my rights to you under said contract as the official representative in behalf of the United States.

“And I hereby surrender to you full possession of such material, machinery, and tools which belong to me and used in connection with said work, in full compliance with the tonus of my said contract. I further surrender all my right, title, and interest in the lease of the George Candage stone quarries at East Blue Hills, Hancock County, in the State of Maine, hereby giving you full possession of said premises for the prosecution and completion of my said contract.”

On the same day the Supervising Architect informed the claimant’s decedent, that in consequence of the relinquishment of his rights under the contract, and of his surrendering and giving full possession of the material, machinery, and tools which belonged to him and which were used in connection with the work, including the quarries, aforesaid, that the defendants had taken possession of the work in whole and would complete the same.

In compliance with the terms of the contract so relinquished, the Government completed the work on the second and third divisions of the building, using therefor the machinery, tools, and materials surrendered therefor by the claimant’s decedent, and purchasing such other machinery, tools, and materials as became necessary therefor, at the cost of $4:69,055.99, which, added to the sum of $45,742.60, paid to the claimant’s decedent for the work done by him on the first division of said building, makes the total cost of $514,798.59, or $139,826.59 in excess of the bids of the claimant’s decedent therefor.

After the completion of the building the defendants sold the materials, tools, and appliances of the claimant’s decedent, as aforesaid, for the sum of $1,019.14 and paid the money into Treasury of the United States in reduction of the amount of the loss so sustained by the Government.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arctic Contractors, Inc. v. State
564 P.2d 30 (Alaska Supreme Court, 1977)
Mittry v. United States
73 Ct. Cl. 341 (Court of Claims, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
35 Ct. Cl. 606, 1900 U.S. Ct. Cl. LEXIS 17, 1900 WL 1488, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcgowan-v-united-states-cc-1900.