Day v. United States

48 Ct. Cl. 128, 1913 U.S. Ct. Cl. LEXIS 152, 1912 WL 1178
CourtUnited States Court of Claims
DecidedFebruary 3, 1913
DocketNo. 21182
StatusPublished
Cited by1 cases

This text of 48 Ct. Cl. 128 (Day v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Day v. United States, 48 Ct. Cl. 128, 1913 U.S. Ct. Cl. LEXIS 152, 1912 WL 1178 (cc 1913).

Opinion

Peelle, Ch. J.,

delivered the opinion of the court:

The question for decision is whether under the contract and specifications made part thereof the claimants were thereby obligated to preserve in good condition without expense to the Government all work then in place; and in respect of the work to be done bidders were advised by paragraph 40 of the specifications that it was imperatively necessary for them to “ visit the locality of the proposed work and obtain, from personal investigation, the information necessary to enable them to make intelligent proposals,” of which personal investigation they were to advise the Government in their letter transmitting their proposals. This was done.

Paragraph 2 of the contract provides that “ the party of the second part shall furnish such labor and material in place, and do such work, and discharge such other obligations connected therewith prescribed in the forementioned specifications, as may be necessary to complete the work of ‘Improving canal at the cascades of the Columbia River, Oregon.’ ”

Paragraph 45 of the specifications provides that “the contract to be entered into will include all excavations and dredging, including the removal of the bulkheads, masonry, filling behind walls, grading and protection of slopes, the placing of irons, the construction of the gates and operating machinery, in short, the entire completion of the lock ready for use, as shown by the drawings and set forth in these specifications.”

Paragraph 149 of the specifications provides:

“ 149. Responsibility for property. — The contractor will be held responsible, without expense to the Government, for the preservation and good condition of all the work now in place, and such as-he may from time to time under this contract put in place, until the termination of the contract, or until the whole work is turned over to the Government in a completed condition, as required. This to include all material of every description on which full or partial payments have been made and all property belonging to the United States in the possession or control of the contractor.”

[137]*137Paragraph. 152 of the specifications provides:

“152. The contractor’s prices for the various items shall cover all costs of preparation for work, all costs of the materials and appliances in place, all transportation, preservation until termination of contract, and every expense of whatever nature which the United States would otherwise have to pay that may arise during the progress of the work or continuance of this contract, except contingencies for engineering and superintendence by the agents of the United States.”

Such are the material and controlling provisions of the contract and specifications.

The substantial facts found are that in May and June, 1894, while the work was in progress, a heavy flood arose, the water rising'in the river at the rate of an inch per hour until it finally reached from 4 to 6 feet above the highest known level, by reason of which it became necessary to protect the work then in place, which was done by the claimants, as averred, under the authority of the engineer in charge, by constructing a new and higher bulkhead over a line nearly 2,000 feet long and two temporary dams, at a cost to them, exclusive of any profits or of any compensation to them for services, of $37,465.35. Hence this action.

The work on the project, to complete which the contract herein was let and upon which the Government had expended over $1,850,000, was begun in 1878, and was continued under the direct charge of the Chief of Engineers, United States Army, until the advertisement for proposals in 1892, from which resulted the contract with the claimants herein.

The original project, the work of the engineers of the United States Army, was revised by them in 1884 with reference to the records of floods to that date; and protecting bulkheads had been constructed by the Government to an elevation of 142 feet, that being the elevation provided by the plans for the completed work. The project so revised was unchanged at the time the contract herein was awarded.

The defendants’ contention is that by the terms of the contract and specifications the claimants were bound to protect the work then in place, though the flood should exceed [138]*138the elevation of 142 feet; while the claimants’ contention is that as the project and plans contemplated an elevation of 142 feet at the time their contract was awarded, the work of protecting the bulkheads by increasing the elevation to 148 feet was outside the contract, for which the Government is liable upon an implied contract on quantum meruit.

The defendants base their contention on the paragraphs of the contract and specifications set forth, which obligated the contractor to furnish all the labor and materials necessary “ for the entire completion of the lock ready for use,” in the doing of which the contractor, without expense to the Government, was to “ be held responsible for the preservation and good condition of all the work now in place, and such as he may from time to time under this contract put in place, until the termination of the contract, or until the work is turned over to the Government in a completed condition, as required.”

The act authorizing the continuance of the improvement of the canal of the cascades, as its title indicates, was “ for the construction, repair, and preservation of certain public works on rivers and harbors,” of which the claimants were bound to take notice.

It is apparent from the findings that as the work embraced within the claimants’ contract was for the completion and preservation of the work under the project, they could not have completed the work under their contract without preserving as they did the bulkheads theretofore constructed by the Government for the protection of the work.

The question, therefore, is, Was the work performed within the contemplation of the parties when they entered into the contract? The project, which had long been.matured, coupled with the claimants’ knowledge of the flood levels prior to the date of the contract, would at first seem to exclude the work from the contract. On the other hand, the claimants were bound to take notice of the uncertainty of floods, and if they had desired protection against the same, provision therefor should have been made in the contract; and not having been so made, and the doing of the work necessary “ for the preservation and good condition of all [139]*139the work now in place ” being authorized by the act and embraced within the terms of the contract, the ordinary rules applicable to voluntary undertakings without qualification must be held to apply. That is to say, as was early held in the case of Dermott v. Jones (2 Wall., 1, 7):

“ It is a well-settled rule of law that if a party by his contract charge himself with an obligation possible to be performed, he must make it good, unless its performance is rendered impossible by the act of God, the law, or the other party. Unforeseen difficulties, however great, will not excuse him.”

In the later case of Chicago, Milwaukee & St. Paul Railway Co. v. Hoyt (149 U. S., 1, 14), the rule was stated thus:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mittry v. United States
73 Ct. Cl. 341 (Court of Claims, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
48 Ct. Cl. 128, 1913 U.S. Ct. Cl. LEXIS 152, 1912 WL 1178, Counsel Stack Legal Research, https://law.counselstack.com/opinion/day-v-united-states-cc-1913.