Satterlee v. United States

30 Ct. Cl. 31, 1895 U.S. Ct. Cl. LEXIS 127, 1895 WL 704
CourtUnited States Court of Claims
DecidedJanuary 14, 1895
DocketDepartmental 49
StatusPublished
Cited by7 cases

This text of 30 Ct. Cl. 31 (Satterlee v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Satterlee v. United States, 30 Ct. Cl. 31, 1895 U.S. Ct. Cl. LEXIS 127, 1895 WL 704 (cc 1895).

Opinion

Weldon, J.,

delivered the opinion of the court.

The subject-matter of this claim was referred by the Honorable Secretary of the Treasury, in the following communication:

“Treasury Department,
“Office op the Secretary,
“ Washington, D. 0., Febrwwry 9, 1894.
The Honorable the Chief Justice
and Judges of the Court of Claims :
“As recommended by the Second Comptroller of the Treasury in his letter of the Gth instant, which is herewith transmitted, I have the honor to refer to your honorable court, pursuant to the provisions of the act of March 3, 1883 (22 Stat. L., 485), the claim of the administrators of the estate of John [48]*48Satterlee, deceased, for work performed on the Harlem River improvement, New York, under contracts dated August 12, 1889, and March 9,1891, or either of them, or under ‘a certain decision of the Acting Secretary of War, made on or about July 11, 1893,’ and for percentages retained from payments made under said contracts, the Second Comptroller having certified that said claim involves controverted questions of fact and law, and that the decision of the court will furnish a precedent for the future action of the accounting officers.
“All the papers, documents, and proofs pertaining to the claim are herewith transmitted, and the questions of fact and law submitted by the Second Comptroller for your decision are stated as follows:
“First. Whether the sums due and the percentages retained under either or both of the contracts of August 12,1889, and March 9,1891, have at any time become forfeited to the United States; and if so, whether as liquidated damages or as unliqui-dated damages, and in what amount..
“Second. Whether the claimants are indebted to the United States on account of additional expenses incurred by it tor engineering and inspection during the period covered by the several extensions of the contracts of August 12, 1889, and March 9, 1891; and if so, in what amount.
“ Third. Whether the claimants are entitled to recover damages on account of the breaking of either or both of the two dams inclosing the working pit and the consequent filling of the cofferdam with water and submerging the plant used on the work on or about April 21,1893, or any other account; and if so, in what amount.
“ Fourth. Whether under either or both of the contracts of August 12, 1889, and March 9, 1891, the United States is entitled to retain or to recover any amount or amounts as damages on account of the noncompletion of said contract or contracts on or before June 1, 1893; and if so, in what amount.
“ Fifth. Whether the claimants are entitled to recover anything under or by virtue of the indorsement of the Acting Secretary of War dated July 11,1893; and if so, in what amount.
“ Respectfully, yours,
“ W. E. Curtis,
Acting Secretary.”

As stated in the letter of transmittal, this claim comes within the jurisdiction of the court under the second section of the act entitled “ An act to afford assistance and relief to Congress and the Executive Departments in the investigation of claims and demands against the Government,” March 3,1883 (22 Stat. L., p. 485):

“ Sec. 2. That when a claim or matter is pending in any of the Executive Departments which may involve controverted [49]*49questions of fact or law, tbe bead of sucb Department may transmit the same, with the vouchers, papers, proofs, and documents pertaining thereto, to said court, and the same shall be there proceeded in under such rules as the court may adopt.
“ When the facts and conclusions of law shall have been found, the court shall not enter judgment thereon, but shall report its findings and opinions to the Department by which it was transmitted for its guidance and action.”

The first and fourth questions propounded in the communication embrace substantially the same inquiry, and will be answered together.

As to the second question, the court finds that in consequence of the extension of the time within which the work was completed, made at the instance of the contractor, the increased cost to the United States by the additional expense of engineering and inspection is the sum of $3,383.83, for which the claimants are liable, and is a proper claim for recoupment from money otherwise due the claimants under said agreements.

In answer to the third inquiry, the court determines that the claimants are not entitled to recover damages because of the insufficiency of the dams to withstand the storm of the 21st of April. Neither party can complain as against the other, for the reason that in the adoption of the plans, specifications, and execution of the work they both exercised reasonable care, caution, and judgment, and the result was not due to the fault of either.

The amount of retained percentage is $11,098, which, being diminished by the sum for which claimants are responsible because of the additional costs of engineering and inspection, leaves a balance of $7,714.17. The completion of the work was not physically nor practically impossible, as it was finally completed under another agreement, but at an expense wholly disproportionate to the compensation agreed to be paid the decedent.

The first, fourth, and fifth questions embrace the issue of the controversy as shown by the facts.

The substance of the first inquiry is whether the retained per cent has become forfeited to the United States as liquidated damages. This court has held, in Kennedy's Case (24 C. Cls. R., 123), that “the 10 per cent reserved until completion of work, [50]*50though declared forfeited by the agreement in the case of an annulment, must be treated as a penalty and not as liquidated damages.” In that case will be found a collection and discussion of the authorities upon the distinction between penalty and .liquidated damages. The 10 per cent being a penalty and not liquidated damages, a failure to perform the contract does not necessarily involve the forfeiture of the retained per cent; but it might be retained by way of recoupment to pay the actual damages to which the party had been subjected because of the failure to perform the agreement.

By the fourth question we are called upon to decide whether the storm of April 21,1893, discharged the claimants from a full and complete performance of the contract, so as to entitle them to recover for the work already performed as represented by the retained per cent; in other words, are the United States entitled to retain the 10 per cent and to recover whatever they may have been damaged beyond that amount because of the failure of the claimants to perform fully their agreements. The facts do not show that the completion of the agreements became physically impossible; but upon the contrary show that the United States did complete the work at a very much increased expense.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Penn-Ohio Steel Corporation v. The United States
354 F.2d 254 (Court of Claims, 1965)
MacO Warehouse Company California v. United States
169 F. Supp. 494 (Court of Claims, 1959)
Branch Banking & Trust Co. v. United States
98 F. Supp. 757 (Court of Claims, 1951)
Carnegie Steel Co. v. United States
49 Ct. Cl. 403 (Court of Claims, 1914)
Day v. United States
48 Ct. Cl. 128 (Court of Claims, 1913)
New Jersey Foundry & Machine Co. v. United States
44 Ct. Cl. 570 (Supreme Court, 1909)
Gleason v. United States
33 Ct. Cl. 65 (Court of Claims, 1897)

Cite This Page — Counsel Stack

Bluebook (online)
30 Ct. Cl. 31, 1895 U.S. Ct. Cl. LEXIS 127, 1895 WL 704, Counsel Stack Legal Research, https://law.counselstack.com/opinion/satterlee-v-united-states-cc-1895.