Branch Banking & Trust Co. v. United States

98 F. Supp. 757, 120 Ct. Cl. 72
CourtUnited States Court of Claims
DecidedJuly 9, 1951
Docket47210, 47211
StatusPublished
Cited by53 cases

This text of 98 F. Supp. 757 (Branch Banking & Trust Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Branch Banking & Trust Co. v. United States, 98 F. Supp. 757, 120 Ct. Cl. 72 (cc 1951).

Opinion

HOWELL, Judge.

Plaintiffs 1 sue to recover $292,170.85 withheld by defendant from payments which plaintiffs allege were due them under two contracts with defendant.

In December 1940, defendant entered into a cost-plus-a-fixed-fee contract (No. W-6826qm-2) with J. J. McDevitt Company, a corporation, E. W. Grannis, an individual, F. N. Thompson, an individual, and V. B. Higgins, an individual, trading as V. B. Higgins Company. Pursuant to the terms of the contract, the corporation and the three individuals were bound both jointly and severally as contractor.

Under the terms of the above contract, the contractor was to construct an antiaircraft firing center, including the necessary buildings, temporary structures, utilities and appurtenances, later known as Camp Davis, near Wilmington, North Carolina. •

The contract provided (article I, 1, (c)) that in addition to reimbursement of certain costs and rentals of the contractor’s equipment, the contractor should receive a fixed fee which would constitute complete compensation for the contractor’s services, including profit and all general overhead expenses.

The contract contained the usual undertakings by the contractor regarding the keeping of accurate records and accounts, the taking of cash and trade discounts and rebates, and the use of the contractor’s best efforts to protect and subserve the interests of the Government. The contract provided that all work would be performed in the shortest possible time in accordance with the drawings and specifications and “subject in every detail” to the supervision, direction and instructions of the contracting officer, 2 and further that the contractor would be reimbursed for actual expenditures in the performance of the work as approved by the contracting officer, including all subcontracts made in accordance with the provisions of the contract. Article V — 1 (d) and (e) provided:

1. The Contractor hereby agrees that he will:

« * * =i
“(d) Enter into no subcontract for any portion of the work, except in the form *764 prescribed by the Secretary of War, nor without the written approval of the Contracting Officer. Subcontracts are defined as contracts entered into by the Contractor with others which involve the performance, wholly or in part at the site of the work, of some part of the work described in Article I hereof.
“(e) At all times during the progress of the work keep at the site thereof a duly appointed and qualified representative who shall receive and execute on the part of the Contractor such notices, directions, and instructions as the Contracting Officer may give.”

During contract negotiations in Washington, the members of the joint venture were informed that a Colonel Montgomery was to be the representative of the contracting officer in charge of the work and that if Colonel Montgomery required any advice concerning his work, he was to contact Mr. Harry A. Fish, Supervising Constructing Quartermaster in Washington who would secure the proper answers for him. The parties agreed that Mr. Clarence P. Street would serve as project manager for the contractor, as required by Article V-l(e), quoted above.

Early in the progress of work under the contract, it was discovered that the camp site was largely swampy and large quantities of sand and sand clay would be required as a stabilizer. Only a small quantity of such material was available on the site and it became apparent that most of it would have to be procured outside the site. As a result of discussions between the project manager and Colonel Montgomery, it was decided that the cheapest, quickest, and most efficient method of securing the material was to place purchase orders for its delivery to the site. Consideration was given to permitting the contractor to buy or rent trucks for the procurement of the necessary sand, but the contractor was informed by the defendant that the purchase of trucks had been forbidden by the War Department and that the rental of sufficient trucks was not feasible because of the unattractive recapture provisions required by the Government in rental agreements.

The project manager was accordingly directed to secure bids from persons who could supply the material, and to place purchase orders with the lowest bidder.

Bids for the sand and sand clay were solicited in December 1940, and the low bid received was from Edward W. Grannis who was one of the contracting parties. The project manager for the contractor questioned the propriety of the contractor entering into a subcontract with one of the contracting parties, and he asked Colonel Montgomery, the contracting officer, to secure a ruling on the matter from the appropriate source in Washington. Pursuant to his instructions, mentioned above, Colonel Montgomery telephoned to Mr. Fish in Washington and asked him to secure a ruling as to whether a subcontract for the purchase of sand and sand clay could properly be awarded to one of the four contracting parties. Mr. Fish contacted the Legal Department of the Construction Division of the War Department and was advised that there was no objection to securing the sand by purchase order from Mr. Grannis. Mr. Fish informed Colonel Montgomery of the ruling, who in turn advised the project manager to place the purchase order with Mr. Grannis.

On December 21, 1940, Purchase Order No. 197 was issued by the purchasing agent for the contractor to Mr. Grannis for 200.000 cubic yards of sand clay to be delivered on the site by truck from a local pit, involving a truck haul of approximately 7% miles, at $1 per cubic yard. This purchase order was approved in writing by Colonel Montgomery as representative of the Constructing Quartermaster and contracting officer. On March 25, 1941, the order was increased to 350,000 cubic yards at the same price, and the “Change of Purchase Order 197” was approved in writing by Captain K. M. Pattee, as the representative of the Constructing Quartermaster. On April 24, 1941, Purchase Order No. 903 was issued by the contractor’s purchasing agent to Mr. Grannis for 100.000 yards of sand clay at 75 cents per cubic yard. This purchase order was approved in writing by Lieutenant Alden E. Spees, for the Constructing Quartermaster. *765 Subsequently, further purchase orders for sand were placed with Mr. Grannis and with Mr. F. N. Thompson, another member of the joint venture, all with the approval of the Constructing Quartermaster. Only the first purchase order was placed as a result of competitive bidding. On being asked at the trial why further bids were not solicited before placing further purchase orders, the representative of the contracting officer testified that it was believed sufficient to merely review the original bids, and that was done. It was the opinion of the representatives of the Government charged with the duty of approving these purchases, that the prices paid were reasonable.

After payment by the contractor to Gran-nis and Thompson for the materials delivered under the purchase orders, vouchers for reimbursement for the money so paid were submitted to and paid by the Government to the contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cebe Farms, Inc. v. United States
116 Fed. Cl. 179 (Federal Claims, 2014)
Lublin Corp. v. United States
98 Fed. Cl. 53 (Federal Claims, 2011)
S & M Management Inc. v. United States
82 Fed. Cl. 240 (Federal Claims, 2008)
Brunner v. United States
70 Fed. Cl. 623 (Federal Claims, 2006)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
In Re NextWave Personal Communications Inc.
244 B.R. 253 (S.D. New York, 2000)
Harbert/Lummus v. United States
41 Cont. Cas. Fed. 77,020 (Federal Claims, 1996)
Thomas Creek Lumber & Log Co. v. United States
41 Cont. Cas. Fed. 76,971 (Federal Claims, 1996)
Dan Rice Construction Co. v. United States
36 Fed. Cl. 1 (Federal Claims, 1996)
Garza v. United States
34 Fed. Cl. 1 (Federal Claims, 1995)
Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)
Howard v. United States
37 Cont. Cas. Fed. 76,130 (Court of Claims, 1991)
H. Landau & Co. v. United States
36 Cont. Cas. Fed. 75,863 (Court of Claims, 1990)
H. Landau & Company v. The United States
886 F.2d 322 (Federal Circuit, 1989)
Colorado State Bank of Walsh v. United States
18 Cl. Ct. 611 (Court of Claims, 1989)
H. Landau & Co. v. United States
885 F.2d 322 (Federal Circuit, 1989)
Lichtefeld-Massaro, Inc. v. United States
35 Cont. Cas. Fed. 75,664 (Court of Claims, 1989)
Llamera v. United States
15 Cl. Ct. 593 (Court of Claims, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
98 F. Supp. 757, 120 Ct. Cl. 72, Counsel Stack Legal Research, https://law.counselstack.com/opinion/branch-banking-trust-co-v-united-states-cc-1951.