Johnson Management Group Cfc, Inc. v. Mel. R. Martinez, Secretary of Housing and Urban Development

308 F.3d 1245, 2002 U.S. App. LEXIS 21657, 2002 WL 31319701
CourtCourt of Appeals for the Federal Circuit
DecidedOctober 17, 2002
Docket01-1145
StatusPublished
Cited by32 cases

This text of 308 F.3d 1245 (Johnson Management Group Cfc, Inc. v. Mel. R. Martinez, Secretary of Housing and Urban Development) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson Management Group Cfc, Inc. v. Mel. R. Martinez, Secretary of Housing and Urban Development, 308 F.3d 1245, 2002 U.S. App. LEXIS 21657, 2002 WL 31319701 (Fed. Cir. 2002).

Opinions

Opinion for the Court filed by Circuit Judge SCHALL. Opinion eoncurring-in-part and dissenting-in-part filed by Circuit Judge PAULINE NEWMAN.

SCHALL, Circuit Judge.

This case involves a dispute between Johnson Management Group CFC, Inc. (“JMG”) and the Department of Housing and Urban Development (“HUD”). The dispute arises out of a Real Estate Asset Management (“REAM”) contract under which JMG agreed to provide management and related services for single family, HUD-owned properties in DeKalb County, Georgia.1 After HUD terminated the contract for default, JMG appealed to the HUD Board of Contract Appeals (“Board”) under the Contract Disputes Act of 1978, as amended, 41 U.S.C. §§ 601-613 (“CDA”). In addition to challenging the default termination, JMG claimed that it was entitled to additional compensation under the contract. Following an eviden-tiary hearing, the Board sustained the default termination. Johnson Mgmt. Group CFC, Inc., HUDBCA Nos. 96-C-132-C15, 97-C-109-C2, 99-2 BCA ¶ 30,520, at 150, 699, 150,706, 1999 WL 651557 (Aug. 4, 1999) (“Johnson I”). At the same time, the Board ruled that JMG was entitled to some recovery on its monetary claims, but that the amounts due JMG were to be offset against the unliquidated balance of advance payments that JMG owed to the government. See id. at 150,712. The Board also ruled that the government held a Men on equipment purchased by JMG for performance of the contract, as security for JMG’s obligation to repay advance payments, and that the government was entitled to enforce its lien rights. See id. at 150,707 JMG moved for reconsideration of the Board’s decision, asserting various factual, evidentiary, and legal errors. Johnson Mgmt. Group CFC, Inc., HUDBCA [1248]*1248Nos. 96-C-132-C15, 97-C-109-C2, 00-2 BCA ¶ 31,116, at 153,677, 2000 WL 1528761 (Sept. 20, 2000) (“Johnson II”). The Board denied JMG’s motion for reconsideration, Johnson II, 00-2 BCA at 153,-684, and JMG now appeals. Because the decision of the Board is free of legal error and is supported by substantial evidence, we affirm.

BACKGROUND

Under the REAM contract, JMG was required to perform various property management services at specified HUD-owned properties. These services included property inspections, leasing and sales activities, rent collection, making improvements and repairs, keeping tax assessment records, and lawn maintenance. The contract was a firm fixed-price services contract, with the lawn maintenance services being treated as a cost-reimbursable item. Johnson I, 99-2 BCA at 150,701. The contract was for a period of one year, with up to four option years. Id.

The effective date of the contract was November 1, 1994. Id. Upon expiration of the base year on November 1, 1995, HUD exercised its option to extend the contract for a second one-year term. However, during the option year, it came to HUD’s attention that JMG was failing to comply with contract requirements relating to the submission of subcontractor invoices for lawn maintenance services. Id. at 150,702. As a result, the contracting officer issued a cure notice to JMG. The cure notice called for JMG to submit accurate subcontractor invoices relating to lawn maintenance services by February 28, 1996. JMG responded to the notice in three separate communications, but failed to allay the contracting officer’s concerns relating to the invoices. See id. at 150,702-03. In addition, several property inspections by HUD revealed that, contrary to what was suggested by submitted invoices, lawn maintenance at a number of properties had not been performed properly. Id. On July 8, 1996, the contracting officer issued a final decision terminating the REAM contract for default on account of JMG’s failure to comply with the contract’s subcontractor invoice requirements. See id. at 150,703.

Following the default termination, JMG presented monetary claims for previously submitted but unpaid invoices totaling $119,758.53. On February 6, 1997, the contracting officer issued a final decision asserting that the government held a lien on equipment purchased by JMG with advance payments under the contract and that, pursuant to that lien, HUD was entitled to demand return of the equipment under the provisions of the Federal Acquisition Regulations (“FAR”) relating to advance payments. The contracting officer declared that HUD would withhold payment of JMG’s monetary claims until JMG agreed to return the equipment. See id. at 150,704. JMG did not agree to return the equipment, and on May 21, 1997, the contracting officer issued a third final decision. In the decision, the contracting officer again refused payment of any of JMG’s monetary claims until JMG returned contract equipment to HUD. See id.

JMG appealed to the Board, challenging the termination for default and seeking payment for contract work it allegedly had performed prior to the default termination. JMG also sought payment for the cost of liability insurance that it had purchased at HUD’s request. Following a hearing, the Board sustained the default termination. As to JMG’s monetary claims, the Board ruled that JMG was entitled to payment on invoices for services provided by JMG prior to termination of the contract. In its determination as to the amount owed JMG, however, the Board found that in the [1249]*1249case of a number of invoices, JMG was entitled to either no reimbursement or only partial reimbursement. In addition, the Board ruled that JMG was not entitled to reimbursement for the cost of liability insurance it had purchased at HUD’s request. Id. at 150,708. At the end of the day, the Board upheld JMG’s monetary claims to the extent of $34,641.38 for lawn maintenance work that HUD inspectors had found to be fully performed and to the extent of $43,859.65 for unpaid management services fees under the contract. Id. at 150,712.

The Board held, however, that the government was entitled to offset against amounts owed to JMG “the unliquidated balance of the advance payments owed to the Government by Appellant.” Id. The Board also held that, as security for the repayment of advance payments extended to JMG under the contract, the government held a lien on equipment that JMG had purchased with advance payments. Id. at 150,707. Finally, the Board held that the government was entitled to “exercise any of the options available under the Advance Payments clause to recover an amount reflecting the unliquidated balance of the advance payments owed by JMG.” Id. at 150,712. That meant that HUD was entitled to seek immediate repayment of the unliquidated balance of advance payments, to take possession of and sell the equipment on which it had a hen, and to apply the proceeds of that sale against the unliquidated balance of advance payments. Following the Board’s denial of its motion for reconsideration, Johnson II, 00-2 BCA at 153,684, JMG timely appealed to this court. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(10).

DISCUSSION

We review the Board’s decision under the standard set forth in the CDA.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J.A.M. Construction Services, Inc.
Armed Services Board of Contract Appeals, 2026
Futures, Inc.
Armed Services Board of Contract Appeals, 2026
Colony Construction
Armed Services Board of Contract Appeals, 2023
Gulf Extreme Engineering & Construction
Armed Services Board of Contract Appeals, 2023
IMC Construction Group
Armed Services Board of Contract Appeals, 2023
Cascade Designs, Inc.
Armed Services Board of Contract Appeals, 2022
Emiabata v. United States
Federal Circuit, 2019
Bowles v. United States
Federal Claims, 2019
Canpro Investments, Ltd v. United States
130 Fed. Cl. 320 (Federal Claims, 2017)
Baistar Mechanical, Inc. v. United States
128 Fed. Cl. 504 (Federal Claims, 2016)
Zoeller v. McHugh
626 F. App'x 983 (Federal Circuit, 2015)
P & K Contracting, Inc. v. United States
108 Fed. Cl. 380 (Federal Claims, 2012)
Todd Construction, L.P. v. United States
656 F.3d 1306 (Federal Circuit, 2011)
NCLN20, Inc. v. United States
99 Fed. Cl. 734 (Federal Claims, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
308 F.3d 1245, 2002 U.S. App. LEXIS 21657, 2002 WL 31319701, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-management-group-cfc-inc-v-mel-r-martinez-secretary-of-cafc-2002.