Williams Building Company, Inc. v. Secretary of State

Court of Appeals for the Federal Circuit·Decided July 23, 2025·No. 23-2337·Unpublished

Opinion

NOTE: This disposition is nonprecedential.

United States Court of Appeals for the Federal Circuit

WILLIAMS BUILDING COMPANY, INC., Appellant

v.

SECRETARY OF STATE, Appellee

2023-2337

Appeal from the Civilian Board of Contract Appeals in Nos. 6650, 7147, Administrative Judge Harold D. Lester, Jr, Administrative Judge Joseph A. Vergilio, Administrative Judge Kathleen J. O’Rourke.

Decided: July 23, 2025

KEVIN MICHAEL COX, Camardo Law Firm, P.C., Auburn , NY, argued for appellant.

GEOFFREY M. LONG, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington , DC, argued for appellee. Also represented by BRIAN M. BOYNTON, PATRICIA M. MCCARTHY, CORINNE ANNE NIOSI; RANDAL WAX, Office of Legal Adviser for Buildings 2 WILLIAMS BUILDING COMPANY, INC. v. SECRETARY OF STATE

and Acquisitions, United States Department of State, Washington, DC.

Before LOURIE, DYK, and CHEN, Circuit Judges.

LOURIE, Circuit Judge.

Williams Building Company, Inc. (“Williams”) appeals from the decision of the Civilian Board of Contract Appeals (“the Board”) that granted summary judgment in favor of the Department of State’s Bureau of Overseas Building Operations (“OBO”) on all three counts of its appeal to the Board. Williams Bldg. Co. v. Dep’t of State, CBCA 23-1 B.C.A. ¶ 38328, 2023 WL 3144494 (Apr. 26, 2023) (“Decision ”), J.A. 1–33. For Count I and most of Count II, the Board determined that prior bilateral contract modifications and releases barred recovery. For the remainder of Count II and Count III, the Board determined that Williams could not prove damages. For the following reasons, we affirm.

BACKGROUND As the Board noted, this case has “had a somewhat torturous history.” Decision, at J.A. 2. With that in mind, only the details most salient to the issues on appeal are summarized below. See id. at J.A. 2–14 (providing a more detailed history).

On June 15, 2016, Williams entered into a firm-fixedprice contract with the OBO for renovations of an office space in Wuhan, China. J.A. 1657–60. Following delays and disputes over the original “issued for construction” documents , the parties agreed to contract modifications P00007 (“modification-7”), J.A. 1793–99, and P00008 (“modification-8”), J.A. 1800–06, on March 16 and June 15, 2018, respectively. The modifications replaced the original “issued for construction” documents with new documents, provided for an extension of time, and each included an

WILLIAMS BUILDING COMPANY, INC. v. SECRETARY OF STATE 3

agreement by Williams to release the government from further liability “attributable to such facts or circumstances giving rise to the proposals for adjustment.” J.A. 1799; J.A. 1806 (same).

Beginning in November 2018, Williams submitted a series of requests seeking additional money under the contract . See Decision, at J.A. 5. Among those requests were proposed change order (“PCO”) 075 requesting an extension of time and a request for equitable adjustment (“REA”) for alleged breaches of contract for a cardinal change due to the deficient original “issued for construction” documents and interference with Williams’ subcontractor, Huashi. Id. at J.A. 5–6. Those requests eventually evolved into two certified claims submitted to OBO on May 9, 2019: (1) seeking a time extension—beyond what was granted in modification-8—for alleged government-caused delays after January 31, 2018, and (2) seeking compensation for a cardinal change claim and a breach of contract claim for alleged interference with Huashi. Id. at J.A. 7–8. On August 13, 2019, the OBO contracting officer issued a final decision denying both claims. Id. at J.A. 8; J.A. 2676–701.

Subsequently, on September 28, 2019, OBO and Williams settled the first claim seeking a time extension and a separate claim for customs storage fees with contract modification P00020 (“modification-20”). See J.A. 1839–50. Modification-20 provides that “[t]he contractor has three open certified legal claims related to customs storage fees, time delays, and cardinal changes to the contract. This [request for contract action (“RFCA”)] represents a partial settlement of the first two of these claims . . . . Additional funding to settle the Breach of Contract claims [e.g., the cardinal change claim] will be requested when additional funds are available.” J.A. 1847–48. The modification’s description of the scope of work provides additional details including PCO 067 for “Additional Storage Costs,” the aforementioned PCO 075 for “Time Extension,” and another contractor release for claims “attributable to the facts 4 WILLIAMS BUILDING COMPANY, INC. v. SECRETARY OF STATE

or circumstances set forth in [Williams’] above-referenced PCOs.” J.A. 1850.

Then, on November 8, 2019, Williams appealed to the Board the contracting officer’s August 13, 2019 decision with respect to the second May 9, 2019 claim for breach. Williams’ complaint to the Board included three counts alleging breach of contract: (I) for a cardinal change to the contract, (II) for breach of the implied duty of good faith and fair dealing due to OBO’s untimely responses to Williams ’ requests for information (“RFIs”) and submittals, and (III) for breach of the implied duty of good faith and fair dealing due to OBO’s alleged interferences with Williams ’ relationship with its subcontractor, Huashi. J.A. 93–114. The complaint did not request a specific quantity of damages, but rather damages “in an amount to be determined at a hearing before the Board.” J.A. 115. OBO moved for a more definite statement on damages, which the Board granted. J.A. 40–44. The Board subsequently issued a scheduling order that required Williams to provide a detailed schedule of all costs it was seeking, along with identification of documentary support for said costs no later than October 16, 2020, and ordered that no other documentary support would be admitted at the hearing of the appeal. J.A. 47–48.

Following conclusion of discovery on June 30, 2021, the parties moved for summary judgment, and the Board granted judgment in favor of OBO on all three counts. For Count I, the Board determined that the broad releases in modification-7 and -8 barred the cardinal change claim and that modification-20 did not waive those releases. Decision , at J.A. 16–21. For Count II, the Board determined that the majority of the identified responses were associated with the circumstances of modification-7 and -8 and were thus barred by the releases contained therein and that Williams failed to identify any damages associated with the remainder. Id. at J.A. 21–24. For Count III, the Board determined that a genuine issue of fact existed

WILLIAMS BUILDING COMPANY, INC. v. SECRETARY OF STATE 5

precluding summary judgment as to the breach, but that Williams failed to properly identify any costs associated with the alleged interference with Huashi because the evidence was first submitted by Williams in response to OBO’s summary judgment motion. Id. at J.A. 24–29.

Williams timely appealed, and we have jurisdiction under 28 U.S.C. § 1295(a)(10).

DISCUSSION We review the Board’s determinations on questions of law, including contract interpretation, de novo. Rockies Express Pipeline LLC v. Salazar, 730 F.3d 1330, 1335–36 (Fed. Cir. 2013). The Board’s factual determinations may not be set aside unless they are “(A) fraudulent, arbitrary, or capricious; (B) so grossly erroneous as to necessarily imply bad faith; or (C) not supported by substantial evidence.” 41 U.S.C. § 7107(b); see also Rockies Express Pipeline, 730 F.3d at 1335. The Board’s decisions regarding procedure relating to discovery and evidentiary issues shall not be overturned unless an abuse of discretion is clear and is harmful. Johnson Mgmt. Grp. CFC, Inc. v. Martinez, 308 F.3d 1245, 1252 (Fed. Cir. 2002).

Free access — add to your briefcase to read the full text and ask questions with AI

Williams Building Company, Inc. v. Secretary of State, (Fed. Cir. 2025).

Williams Building Company, Inc. v. Secretary of State (Williams Building Company, Inc. v. Secretary of State) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related