Gulf Extreme Engineering & Construction

CourtArmed Services Board of Contract Appeals
DecidedOctober 30, 2023
Docket62592
StatusPublished

This text of Gulf Extreme Engineering & Construction (Gulf Extreme Engineering & Construction) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gulf Extreme Engineering & Construction, (asbca 2023).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Gulf Extreme Engineering & Construction ) ASBCA No. 62592 ) Under Contract No. W5J9JE-16-C-0003 )

APPEARANCE FOR THE APPELLANT: Mr. Mir Sulaiman Amini Chief Executive Officer

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Rebecca L. Bockmann, Esq. Kathryn G. Morris, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Middle East Winchester, VA

OPINION BY ADMINISTRATIVE JUDGE SMITH

Appellant Gulf Extreme Engineering & Construction (GEEC or appellant) challenges Respondent U.S. Army Corps of Engineers’ (the government’s) default termination of GEEC’s construction contract for failure to diligently prosecute the work. GEEC contends that the government’s suspension of one of the contract’s line items (CLINs) during the project, along with COVID and other government actions, impeded GEEC’s performance and excused its considerable project delay. But GEEC’s arguments are unsupported or unavailing and they fail to rebut the government’s demonstrated justification for termination. The appeal is denied.

FINDINGS OF FACT

GEEC was awarded a $7,985,000 design-build contract on April 6, 2016 (R4, tab 6 at 2). The contract was grouped into eight CLINs for design and construction of electric power transmission infrastructure in Baghlan province, Afghanistan (R4, tab 6 at 3-6). CLINs 3, 4, and 5 were geographically discrete work elements that could be performed independently (R4, tab 6 at 3-6, 52-53, tab 14). The government issued notice to proceed on June 10, 2016, establishing a completion date 707-days later on May 19, 2018 (R4, tab 13). During performance, a total of five modifications were issued, two of which bilaterally expanded the period of performance to 1,386 days with a revised project completion date of March 28, 2020 (R4, tabs 7-11). Although the solicitation and contract included a preliminary conceptual route for the electric transmission lines, the actual route was to be determined by GEEC during the design phase and based upon then-existing conditions, coordination with Afghan utilities, available rights of way, and the contractor’s own design, cost, and construction decisions (R4, tab 6 at 57, 110-11, 355, tab 7 at 2). The contract expressly required GEEC to “. . . investigate other routes for optimization and cost savings . . . .” (compare R4, tab 12 at 3, with R4, tab 6 at 53-54, 57). On July 2, 2016, GEEC’s RFI 1 proposed a route that differed from the conceptual route, calling it a “change request” without cost or schedule impact (R4, tab 139). Even though it was not a change to GEEC’s obligation to propose a route, the government accepted GEEC’s proposal and reiterated the contract requirement that GEEC was responsible for rights-of-way and coordination with the Afghan government, which needed to be finalized in the 35% design submittal (R4, tab 16, tabs 139-140 at 1).

GEEC’s design submittals were all late (R4, tab 14 at 3 (activity ID Srvy-15)- 4 (activity IDs Dsgn-11, Dsgn-15, Dsgn-19, & Dsgn-23); tab 20 at 2-3, tab 33 at 1, tab 156 at 1). For example, GEEC’s 99% design was 333 days later than its original schedule, and 200 days later than its May 2017 schedule update (R4, tab 156 at 1). It was also based upon the preliminary route in the contract, not the approved route chosen by GEEC and discussed above (compare R4, tab 153 at 5, with R4, tab 6 at 355).

By May 22, 2017, GEEC was 345-days into the 707-day period of performance yet had earned just 25% of the contract value (R4, tab 115 at 1). Nine months after that, in February 2018—626 days into the now-modified 776-day performance period—GEEC had completed just 51% of the work (R4, tab 124 at 1). This left five months to complete the other half of the project and GEEC had achieved, at most, 3.5% progress per month (id.). So, by the end of February 2018, GEEC’s rate of progress suggested at a minimum 14 more months of work. Timely performance was essentially impossible.

On April 23, 2018, the government requested a realistic recovery schedule to complete on time (R4, tab 43). The government said that “[i]f you claim uncontrollable delays please provide the reasons and backup documents” (id.). GEEC did not respond with a realistic recovery plan or justification for delays. In fact, GEEC did not respond at all. On June 2, 2018, the government asked again (R4, tab 45). GEEC responded with a June 5, 2018, RFI 9 that largely repeated RFI 1, which had been approved by the government over two years earlier (R4, tab 147). Unlike RFI 1, however, RFI 9 now sought a schedule extension and undefined additional compensation (id.).

GEEC attributed its slow progress to a “stop work order by Baghlan municipality” that would be “resolved as soon as possible” (R4, tab 46 at 2), but again

2 did not provide a recovery schedule. Instead, GEEC’s June 30, 2018, schedule update projected late completion by over 14 months and sought a price increase to CLIN 3 from $3.2 million to over $7 million (R4, tab 6 at 4, tab 149 at 5). But the record reflects that some of GEEC’s delay was caused by its failure to coordinate its proposed route with the Afghan authorities, which was a clear contract requirement (R4, tab 137 at 1498 (under “Quality Assurance Narrative(s)”), tab 6 at 78 (¶ 3.1.6)).

Despite its earlier delays, GEEC made progress in the latter half of 2018, including on CLINs 4 (70.3%) and 5 (88%), although much of the increased percentages were due to invoicing high-cost materials as opposed to performance of actual construction work (R4, tab 132 at 2).

When the Army vacated Camp Kelaghai in early 2019, the government suspended work on CLINs 3 and 5 (72% of the remaining work) and sought a credit proposal for deleting them from the contract (R4, tabs 55-56, 152-153 at 2). Rather than a credit for CLINs 3 and 5, GEEC sought an overall increase of $1.7 million and a 609-day time extension, citing “major factors that ha[ve] affected the project progress and caused delays in project works” (R4, tab 62 at 1, tab 63 at 140). Despite its off-task proposal, the government granted GEEC’s entire time-extension request, setting a new completion date of March 28, 2020 (R4, tab 159 at 4, 6). The government directed GEEC to continue work on CLIN 4, including the procurement of long lead items, while the disposition of CLINs 3 and 5 was determined (R4, tab 73).

The government lifted the suspension of CLIN 5 on September 2, 2019, and the parties formalized the extension of the completion date to March 28, 2020, with bilateral Modification No. P00001 (R4, tab 11). Modification No. P00001 did not change the price of the contract (id.). As GEEC later acknowledged, Modification No. P00001 “compensate[d GEEC for] unforeseen delays beyond GEEC’s control” including “expenses due to work stoppage” (R4, tab 92 at 3). GEEC’s subsequent schedule updates reflected completion of CLINs 4 and 5 within the newly revised March 28, 2020, performance period (R4, tab 70 at 85-87).

Despite these agreed-upon changes, GEEC did not promptly resume work on CLINs 4 and 5 which drew letters of concern from the government on October 24, November 6, December 17, and December 24, 2019 (R4, tabs 73, 76, 82-83). It was not until December 29, 2019, that GEEC revealed that it had intended all along to “complet[e] all contract CLINs simultaneously and concurrently for successful execution and completion of the project” (R4, tab 84 at 2).

Meanwhile, the government split CLIN 3 into two parts (which for ease of reference we call CLIN 3.1 and CLIN 3.2) with CLIN 3.1 remaining suspended (R4, tabs 78-79). GEEC was directed to resume work on CLIN 3.2 (id.). On January 7, 2020, GEEC submitted a schedule that showed it resuming work on CLIN 3.2 and

3 completing it by August 22, 2020 (R4, tab 161 at 168 (“Schedule Narrative”)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Gulf Extreme Engineering & Construction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gulf-extreme-engineering-construction-asbca-2023.