Todd Construction, L.P. v. United States

656 F.3d 1306, 2011 U.S. App. LEXIS 17980, 2011 WL 3796259
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 29, 2011
Docket2010-5166
StatusPublished
Cited by112 cases

This text of 656 F.3d 1306 (Todd Construction, L.P. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Todd Construction, L.P. v. United States, 656 F.3d 1306, 2011 U.S. App. LEXIS 17980, 2011 WL 3796259 (Fed. Cir. 2011).

Opinion

DYK, Circuit Judge.

Todd Construction, L.P. (“Todd”) is a government contractor. Todd filed suit in the Court of Federal Claims (“Claims Court”) under the Tucker Act, 28 U.S.C. § 1491, and the Contract Disputes Act (“CDA”), 41 U.S.C. § 601 et seq., alleging that the United States Army Corps of Engineers (the “government”) gave it an unfaii’ and inaccurate performance evaluation. The Claims Court held that the CDA provided it with subject matter jurisdiction over such a claim, but dismissed Todd’s complaint for lack of standing and failure to state a claim. Todd Constr., L.P. v. United States, 85 Fed.Cl. 34 (2008) (“Todd /”); Todd Constr. L.P. v. United States, 88 Fed.Cl. 235 (2009) (“Todd II”); Todd Constr. L.P. v. United States, 94 Fed.Cl. 100 (2010) (“Todd III”). We affirm both the Claims Court’s determination that it had jurisdiction under the CDA and its dismissal of Todd’s complaint on the grounds of lack of standing and failure to state a claim.

BaCkground

In 2003, Todd entered into two task order contracts with the government on two construction projects for roof repairs of government buildings. The parties refer to these projects as “Building 2121” and “Building 3611.” The government agreed to amended completion dates, making the completion dates June 25, 2004, for the Building 2121 project and July 30, 2004, for the Building 3611 project. Due to a series of delays (some of which Todd alleges were caused by its subcontractors, the government, or other circumstances outside of its control), the projects were not completed and accepted by the government until September 30, 2005, and October 14, 2005, respectively.

At the time, the Federal Acquisition Regulations (“FAR”) required that for “each construction contract” for “$550,000 or more,” a “[performance] report shall be prepared ... in accordance with agency procedures” and that “[e]ach performance report shall be reviewed to ensure that it is accurate and fair.” 1 48 C.F.R. § 36.201 (2006). The government issued ER 415-1-17 to implement FAR § 36.201 and establish procedures for contractor performance evaluations. See U.S. Army Corps of Engineers Regulation 415-1-17 (“ER 415-1-17”). That regulation, inter alia, required: (1) “[N]oti[ce] [to] the contractor ... of the performance elements against which his performance will be evaluated;” *1309 (2) a conference with the contractor prior to the issuance of interim unsatisfactory-performance ratings; (3) “re-evaluation of [any] interim unsatisfactory rating every three months;” (4) and issuance of a final evaluation within sixty days of “substantial completion of the work.” Id. 415-1-17(5)(a)-(c). It also permitted contractors to “submit written comments, which should be addressed and included in the report,” and allowed contractors to appeal a final unsatisfactory performance evaluation “to one level above the Contracting Officer.” Id. 415-1-17(5)(c)(2), (3)(f). The regulation explained that the evaluations would typically be prepared by the “resident engineer” and reviewed and approved by the contracting officer. Id. 415 — 1—17(5)(c)(l). This was apparently the case with Todd’s evaluations. The final evaluations are filed in a central database where the information is stored for at least six years. 48 C.F.R. § 36.201(c); ER 415-l-17(5)(c)(l). The information is then used by contracting officers in determining future contract awards. See 48 C.F.R. §§ 42.1501-1503.

Todd received negative interim performance evaluations from the resident engineer for both projects on February 5, 2004. On March 26, 2006, the resident engineer issued his proposed negative final performance evaluations for both projects pursuant to 48 C.F.R. § 36.201 and ER 415-1-17. On April 20, 2006, Todd submitted comments protesting the proposed evaluations. These comments primarily took issue with the purported lack of timeliness of its performance, asserting that its subcontractors and “other problems” that were “beyond Todd’s control” caused the delays. J.A. 41-43. Todd also asserted that it “took extraordinary steps to supervise, manage, coordinate and control its subcontractors,” that it was “responsive to the Government’s concerns,” and that its “quality control system” was adequate. Id. The evaluations were not changed as a result of Todd’s comments.

In the final performance evaluations, the resident engineer assigned Todd an overall performance rating of unsatisfactory. The resident engineer also assigned unsatisfactory ratings for each project in fifteen individual performance categories. Many of these categories (e.g., “adherence to approved schedule,” “correction of deficient work in a timely manner,” and “resolution of delays”) related to the timeliness of Todd’s performance. J.A. 35. Todd was also given unsatisfactory ratings in categories such as “coordination and control of subcontractor^],” “quality of workmanship,” “management of resources/personnel,” and “cooperation and responsiveness.” Id. The resident engineer also included specific comments expanding on the negative ratings. For example, the resident engineer stated that “[the] [f]irst submittal was not received until 22 Dec 03,” that the “[c]ontractor did not start work until the week of 29 March 04,” and that the “[c]ontraetor’s quality control system allowed subcontractors to field paint damaged roof panels without government approval.” Id.

Following internal reviews within the Department of the Army, the final evaluations were issued on July 23, 2006. Todd sought review by the contracting officer. On April 25, 2007, the contracting officer issued a “final decision regarding [Todd’s] performance,” concluding that “the [unsatisfactory performance appraisal [was] justified and all required procedures were followed.” J.A.59.

On May 25, 2007, Todd filed a complaint in the Claims Court, alleging that the government failed to follow the proper procedures and that the unsatisfactory performance evaluations were arbitrary and capricious and seeking, inter alia, a declaratory judgment. In this complaint, Todd did not challenge any particular performance ratings. Instead, it merely pled *1310 that the government issued overall unsatisfactory performance evaluations and that these ratings were arbitrary and capricious. In an initial opinion, the Claims Court held that it had subject matter jurisdiction over the suit under the CDA because the claim that the performance evaluations were inaccurate and improper “relat[ed] to the contract,” as required by the CDA. Todd I, 85 Fed.Cl. at 44-45.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Technical Services, Inc
Armed Services Board of Contract Appeals, 2023
Consorzio Stabile GMG S.c.ar.1.
Armed Services Board of Contract Appeals, 2023
Sana Kappouta v. Valiant Integrated Services
60 F.4th 1213 (Ninth Circuit, 2023)
ServeFed, Inc.
Armed Services Board of Contract Appeals, 2023
22nd Century Technologies, Inc. v. United States
57 F.4th 993 (Federal Circuit, 2023)
Lockheed Martin Aeronautics Company
Armed Services Board of Contract Appeals, 2021
JAAAT Technical Services, LLC
Armed Services Board of Contract Appeals, 2021
Hvf West, LLC v. United States
Federal Claims, 2020
PROTEC GmbH
Armed Services Board of Contract Appeals, 2019

Cite This Page — Counsel Stack

Bluebook (online)
656 F.3d 1306, 2011 U.S. App. LEXIS 17980, 2011 WL 3796259, Counsel Stack Legal Research, https://law.counselstack.com/opinion/todd-construction-lp-v-united-states-cafc-2011.