Consorzio Stabile GMG S.c.ar.1.

CourtArmed Services Board of Contract Appeals
DecidedMay 1, 2023
Docket62753
StatusPublished

This text of Consorzio Stabile GMG S.c.ar.1. (Consorzio Stabile GMG S.c.ar.1.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consorzio Stabile GMG S.c.ar.1., (asbca 2023).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Consorzio Stabile GMG S.c.ar.l. ) ASBCA No. 62753 ) Under Contract No. N33191-14-D-1050 )

APPEARANCE FOR THE APPELLANT: Marc Lamer, Esq. Kostos and Lamer, P.C. Philadelphia, PA

APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq. Navy Chief Trial Attorney Patricia Walter, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE HERZFELD

The Department of the Navy (Navy) awarded a task order to Consorzio Stabile GMG S.c.ar.l. (Consorzio) to design and construct a vestibule and replace the doors at Building 261, NSA-I in Bahrain. The Navy terminated Consorzio’s task order for default and justifies its termination based on Consorzio’s failure to make progress in performing the task order. Consorzio asserts that the Navy wrongfully terminated the contract for default because the Navy waived the performance date and failed to create a new performance date. Consorzio seeks to have the termination converted into a termination for convenience. The parties filed briefs on the record, waived a hearing, and requested the Board issue a decision under Board Rule 11. The Board has jurisdiction of this appeal under the Contract Disputes Act (CDA) of 1978, 41 U.S.C. § 7105(e)(1)(A). We sustain the appeal and convert Consorzio’s default termination to a termination for convenience.

FINDINGS OF FACT

On September 17, 2014, the Navy, through the Naval Facilities Engineering Command Europe Africa Central, awarded Consorzio an indefinite delivery/indefinite quantity multiple-award construction Contract No. N33191-14-D-1050 (the Contract) to design/build-design/bid/build new construction, renovation, alteration, and repair projects at areas in Bahrain and the United Arab Emirates (R4, tab 36; U.S. Department of Defense, Contract Awards for Sept. 17, 2014). 1

1 https://www.defense.gov/News/Contracts/Contract/Article/606022/ (visited on Apr. 27, 2023). On July 31, 2018, the Navy awarded Consorzio Task Order No. N3319118F4309 (the Task Order), which called for Consorzio to design and construct a vestibule and repair or replace the doors at Building 261, NSA-I in Bahrain for $853,000 (R4, tab 6 at 404, 409). 2 The Task Order required Consorzio to:

(a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 425 calendar days of award. The time stated for completion shall include final cleanup of the premises.

(R4, tab 6 at 407) (emphasis in original). The Task Order specifically identified September 29, 2019, as the completion date (R4, tab 6 at 406). The Task Order included a Liquidated Damages provision, which set a $400 rate for each calendar day of delay (R4, tab 6 at 407 (incorporating Federal Acquisition Regulation (FAR) 52.211-12, LIQUIDATED DAMAGES – CONSTRUCTION (SEP 2000)).

The Task Order required Consorzio to submit its detailed construction phasing plan for the Navy’s approval at the kickoff meeting, which occurred on September 6, 2018 (R4, tab 4 at 267, 11 at 422, 12 at 424). The construction phasing plan would indicate the sequence of work and timeline for the blast-resistant doors, interior doors, and other exterior doors requiring repairs (R4, tab 4 at 267). Consorzio submitted its performance guarantee as required by the Task Order on October 9, 2018, but not its phasing plan (R4 tabs 7 at 411-14, 8 at 415; gov’t br. at 3).

The parties held a progress meeting on December 18, 2018, regarding the Task Order (and other projects). During this meeting, Consorzio committed to providing its phasing plan to Navy personnel no later than December 22, 2018 (R4, tab 10 at 420). The Navy emphasized to Consorzio the project’s high visibility and the need for timely completion (R4, tab 10 at 420). Consorzio responded that, if necessary, it would deploy additional workers from Italy to ensure timely completion of the project (R4, tab 10 at 420).

On January 27, 2019, the Navy issued a letter of concern for lack of progress on the project (R4, tab 12). The Navy’s letter stated that, “40% of the contract time has elapsed,” Consorzio’s “65% design package was 45 days late,” and Consorzio still had yet to submit its detailed phasing plan originally due at the September 6, 2018 kickoff

2 The Navy has numbered the Rule 4 file with a leading prefix of GOV followed by zeroes prior to the page number. For ease of reference, we cite the page numbers without the prefix and leading zeroes. 2 meeting (R4, tab 12 at 424). The Navy’s letter expressed concern that Consorzio could not “complete the required work by the contract’s completion date of September 29, 2019” unless it took immediate action (id.).

Referencing the Contract’s default provision, the Navy also advised Consorzio to provide documentation justifying Consorzio’s position if circumstances outside of its control were preventing timely execution of the contract, reminding Consorzio that the Navy would assess liquidated damages of $400 per day for each calendar day of delay in accordance with the Contract (id.; see also R4, tab 36 at 656 (incorporating by reference FAR 52.249-10 – DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)). Additionally, the Navy directed Consorzio to provide the Navy within 10 days a written plan, an updated schedule, and a detailed phasing plan indicating how it would complete the project by the contract’s completion date (R4, tabs 11 at 422, 12 at 424).

Consorzio submitted its phasing plan on February 9, 2019 (R4, tab 13). The plan indicated that Phase I would require 58 days to complete, beginning on March 18, 2019, and ending on May 14, 2019; Phase II would require 60 days to complete, beginning on May 7, 2019, and ending on July 7, 2019; and Phase III would require 79 days to complete, beginning on July 8, 2019, and ending on September 25, 2019 (id. at 430-42).

By letter dated February 10, 2019, Consorzio responded to the Navy’s January 27, 2019 letter of concern (R4, tab 14). Consorzio indicated that circumstances beyond its control had prevented the timely submission of some design steps and stated that it was “gathering . . . supporting documents” to request a time extension (id.). Consorzio emphasized that it was taking immediate action to make up for lost time and that it believed it could complete the project on time (id.; Mattivi decl. ¶ 10). 3

Consorzio encountered difficulty procuring the doors necessary to complete the project from the Italian supplier it had intended to utilize because of “issues with the technical documentation for the doors” (D’Amico decl. ¶ 4; see also R4, tab 20 at 456). 4 On June 3, 2019, Consorzio proposed to resolve the difficulties with the documentation for the doors by installing anti-blast steel doors instead of aluminum doors (D’Amico decl. ¶ 5; app. ex. A at 1 (Request for Information)). Consorzio stated that aluminum blast-resistant doors meeting the Anti-Terrorism/Force Protection requirements of the Task Order were unavailable and requested permission to install the steel doors at no additional cost to the Navy (app. ex. A at 1; Mattivi dec. ¶ 11).

3 Ms. Jennifer Mattivi was the Navy’s contracting officer (Mattivi decl. ¶ 1). 4 Mr. Matteo D’Amico was a project manager for Consorzio (D’Amico decl. ¶ 1). 3 On June 24, 2019, a Navy contract specialist indicated agreement with Consorzio’s request, proposed that any change should be in accordance with the Contract’s Changes clause, requested a proposal from Consorzio to install blast- resistant steel doors in lieu of blast-resistant aluminum doors, and indicated that Consorzio should justify any request for a time extension (D’Amico decl. ¶ 6; Mattivi decl. ¶ 12; app. ex.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Consorzio Stabile GMG S.c.ar.1., Counsel Stack Legal Research, https://law.counselstack.com/opinion/consorzio-stabile-gmg-scar1-asbca-2023.