State of Florida, Department of Insurance, as Receiver for Southeastern Casualty & Indemnity Insurance Company v. United States

81 F.3d 1093, 40 Cont. Cas. Fed. 76,916, 1996 U.S. App. LEXIS 6993, 1996 WL 167160
CourtCourt of Appeals for the Federal Circuit
DecidedApril 10, 1996
Docket95-5106
StatusPublished
Cited by21 cases

This text of 81 F.3d 1093 (State of Florida, Department of Insurance, as Receiver for Southeastern Casualty & Indemnity Insurance Company v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State of Florida, Department of Insurance, as Receiver for Southeastern Casualty & Indemnity Insurance Company v. United States, 81 F.3d 1093, 40 Cont. Cas. Fed. 76,916, 1996 U.S. App. LEXIS 6993, 1996 WL 167160 (Fed. Cir. 1996).

Opinion

BRYSON, Circuit Judge.

The construction contract at issue in this case resulted in a default termination of both the contractor and the contractor’s surety. The surety’s receiver sued the United States for damages based on losses suffered by the surety in connection with the project. The Court of Federal Claims denied relief, Florida Dep’t of Ins. v. United States, 33 Fed. Cl. 188 (1995), and we affirm.

I

In October 1987, the Padula Construction Company (Padula) contracted with the Postal Service to build a post office facility in Jupiter, Florida. Padula failed to perform according to the contract requirements, and on October 18, 1988, shortly before the completion date set forth in the contract, the Postal Service terminated the contract for default. The Postal Service provided notice of the default to Padula’s surety, the Southeastern Casualty and Indemnity Insurance Company (Southeastern). Pursuant to its performance bond agreement, Southeastern undertook to finish the building, promising to use its best efforts to complete the work in accordance with the terms of the original contract. At the time it took over the project, Southeastern promised that within two weeks it would provide a written strategy for finishing the work.

Southeastern did not meet that deadline: In fact, for several months Southeastern did little or no work on the project. In early November 1988, the Postal Service complained to Southeastern about its failure to prepare a project schedule and emphasized that “in order to meet the needs of the Postal Service for the facility and to minimize the expense for Southeastern Casualty Company due to contractual penalties for late delivery of the building, it is essential that everything possible be done in order to expedite the completion of the facility.” In early December, the Postal Service warned Southeastern of continuing damage to the structure resulting from exposure to the elements because the roof of the building had not yet been completed. The Postal Service reiterated its concern about the project schedule and again advised Southeastern that it planned to pursue liquidated damages under the contract for the delay in completing the building. At the same meeting, the Postal Service questioned Southeastern’s desire to go to bid on the project and again demanded a project schedule.' On December 20, 1988, the Postal Service wrote Southeastern to state that it was “increasingly concerned about the lack of response” from Southeastern regarding the plans for completing the facility. The Postal Service requested a full written report on the status of the matter within 10 days, and it restated its concern “that any further delay will accelerate the deterioration of the existing construction work.” By the end of December, Southeastern had neither provided thé Postal Service with a project schedule nor advanced the project’s completion.

In February 1989, Southeastern informed the Postal Service that it had chosen Frank Maio General Contractors, Inc. (Maio) to complete the project. Maio provided a proposed work schedule that estimated the project would be completed by August 1989. *1096 The parties did not fix a firm date for completion of the building, but the Postal Service again advised Southeastern that liquidated damages continued to accrue and would be deducted from any monthly payment requests. To ensure that the project would move forward within a reasonable time, the Postal Service again requested updated schedules and documentation regarding the identity of the proposed participants and their roles in completing the project. Southeastern did not comply with that request.

A March 1989 site inspection showed that no work was in progress inside the budding and that the roof was still incomplete. On March 30, the Postal Service told Southeastern that it was critical that arrangements be made immediately to complete the roof.

In early April, the Postal Service learned that the Treasury Department would likely revoke Southeastern’s authority to act as a federal bond surety because Southeastern had failed to meet the Department’s minimum financial requirements to retain that status. The Postal Service asked to meet with Southeastern on April 18 to discuss a possible termination for default because of Southeastern’s failure to make progress on the project. During the April 18 meeting, a Postal Service representative asked for a specific commitment from Southeastern that it was ready, willing, and able to complete the project without delay. In response, Southeastern stated that it had no obligation to keep the Postal Service advised of its progress. After the Postal Service again warned Southeastern that termination was imminent, Southeastern stated it should not be required to “isolate, analyze and submit corrective proposals at [its] expense” for defective work performed by Padula. Southeastern also suggested that, because of the necessary corrective work, the building might not be completed in August as Maio had promised.

On May 12,1989, the Postal Service terminated Southeastern for default because of its failure to make progress. The Treasury Department revoked Southeastern’s certificate of authority to act as a federal surety on the same day. In August 1989, a Florida court deemed Southeastern insolvent and appointed a receiver.

In December 1990, the Florida Department of Insurance, as receiver for Southeastern, submitted a claim to the contracting officer for $465,973.65. Of that amount, $200,000 was attributable to the Postal Service’s allegedly improper progress payments to Padula prior to Padula’s default, and the remainder was attributable to funds expended by Southeastern after it took over the project. After the contracting officer denied the claim, Southeastern’s receiver filed suit in the Court of Federal Claims, for the amount set forth in the claim. The court granted partial summary judgment to the United States with respect to the payments to Padula; after trial, the court ruled in favor of the United States on the remaining portions of the claim.

II

A

The appellant first argues that the Postal Service waived its right to terminate Southeastern, because it failed to set a deadline for completion after the original October 1988 deadline had passed and because it allowed Southeastern to continue to perform until May 1989. By those actions, the appellant maintains, the Postal Service led Southeastern to believe that time was no longer of the essence and induced Southeastern to undertake substantial efforts to complete the contract.

A waiver of the government’s right to terminate a contract for default may be found when the government allows “a delinquent contractor to continue [substantial] performance past a due date,” under circumstances that justify a conclusion that the default has been excused. DeVito v. United States, 413 F.2d at 1147, 1153-54 (Ct.Cl.1969). The purpose of the waiver doctrine is to protect contractors who are led to believe that time is no longer of the essence and undertake substantial efforts after the performance date specified in the contract has passed. Olson Plumbing & Heating Co. v. United States, 221 Ct.Cl. 197, 602 F.2d 950, 955 (1979). When the non-breaching party *1097

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Racer Machinery International
Armed Services Board of Contract Appeals, 2026
Mindseeker, Inc.
Armed Services Board of Contract Appeals, 2024
Consorzio Stabile GMG S.c.ar.1.
Armed Services Board of Contract Appeals, 2023
Kellogg Brown & Root Services, Inc.
Armed Services Board of Contract Appeals, 2021
GSC Construction, Inc.
Armed Services Board of Contract Appeals, 2020
Watts Constructors, LLC
Armed Services Board of Contract Appeals, 2019
ECC CENTCOM Constructors, LLC
Armed Services Board of Contract Appeals, 2018
People v. Madison
2018 COA 62 (Colorado Court of Appeals, 2018)
United Partition Systems, Inc. v. United States
90 Fed. Cl. 74 (Federal Claims, 2009)
Bearingpoint, Inc. v. United States
82 Fed. Cl. 181 (Federal Claims, 2008)
Engineered Maintenance Services, Inc. v. United States
55 Fed. Cl. 637 (Federal Claims, 2003)
SIPCO Services & Marine Inc. v. United States
42 Cont. Cas. Fed. 77,277 (Federal Claims, 1998)
Interstate General Government Contractors, Inc. v. United States
42 Cont. Cas. Fed. 77,314 (Federal Claims, 1998)
Carter Chevrolet Agency, Inc. v. United States Postal Service
19 F. Supp. 2d 1246 (W.D. Oklahoma, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
81 F.3d 1093, 40 Cont. Cas. Fed. 76,916, 1996 U.S. App. LEXIS 6993, 1996 WL 167160, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-of-florida-department-of-insurance-as-receiver-for-southeastern-cafc-1996.