Engineered Maintenance Services, Inc. v. United States

55 Fed. Cl. 637, 2003 U.S. Claims LEXIS 73, 2003 WL 1683852
CourtUnited States Court of Federal Claims
DecidedMarch 20, 2003
DocketNo. 96-625C
StatusPublished
Cited by5 cases

This text of 55 Fed. Cl. 637 (Engineered Maintenance Services, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Engineered Maintenance Services, Inc. v. United States, 55 Fed. Cl. 637, 2003 U.S. Claims LEXIS 73, 2003 WL 1683852 (uscfc 2003).

Opinion

OPINION

DAMICH, Chief Judge.

I. Introduction

This case is before the Court on Defendant’s Motion for Summary Judgment pursuant to Rule 56 of the Rules of the Court of Federal Claims (RCFC). Defendant contends that it was justified in terminating for default its contract with the Plaintiff, Engineered Maintenance Services, Inc. (“EMS”). According to Defendant, Plaintiff failed to give proper notice of its claim for differing site conditions and, moreover, cannot successfully assert excusable delay under the differing site condition clause. For the reasons set forth herein, Defendant’s motion is hereby GRANTED.

II. Background

On August 3, 1994, the United States Army Missile Command awarded Contract DAAH03-94-C-0087 to EMS for $895,995.00. This firm fixed-price contract contemplated the replacement of steam and condensate lines in the 3300 Area at Red-stone Arsenal, Alabama, to be completed within 315 days after receipt of a notice to proceed.

As a general rule, the Government instructed EMS to install pipe at a minimum depth of three feet. The contractor could use its discretion in choosing to install new pipe over existing pipe, so long as the new pipe met the three foot groundcover requirements. However, in response to written pre-bid questions by bidding contractors, the Government stated that in two different instances it would be appropriate to run the new system and condensate lines over the top of storm culverts with less than the required groundcover.

Although the Government did not provide any documents indicating the depth of all existing pipe, its specifications provided that the contractor could determine that depth by the depth at which the existing pipe penetrated the steam pit walls. When EMS inspected the site, it determined that the existing pipe was installed at a sufficient depth so that it believed very little of the existing pipe would need to be removed. Indeed, the Government’s internal estimator estimated that only 520 linear feet of existing pipe would have to be removed. Moreover, although the contract documents indicated that all of the existing pipe contained asbestos, EMS only allocated $16,000 for asbestos removal because it believed it could install most of the pipe over existing lines. The contract drawings did not show the depth of any underground utilities, and some utilities were not shown at all.

The specifications provided that the contractor was to perform all excavation and trenching necessary to accomplish pipe removals and new pipe installation and that no steam outages would be permitted during the months of October through March. The specifications also required that the steam pits connecting the pipe be sealed and that sump pumps capable of continuously pumping water be placed in the pits to remove water.

The Government issued a notice to proceed on December 1, 1994 and ordered the contract to be completed by October 11, 1995. EMS submitted a required progress chart to the Government on January 18, 1995 which indicated that EMS would begin on-site work by February 1, 1995. On February 13, 1995, the Government notified EMS that it was concerned with its lack of progress and failure to commence work. EMS did not actually begin work on the construction site until February 23, 1995.

EMS submitted a statement of progress on March 21, 1995, indicating that it had only completed 35% of construction on the new steam pit, which was to have been completed by March 3, 1995. In addition, the progress report indicated that no work had com[640]*640menced on the removal and replacement of the steam and condensate pipes. EMS was still several weeks behind its scheduled performance milestones in the middle of April, 1995. The Government requested that EMS take necessary steps to improve its progress on May 15, 1995 and instructed EMS to provide the Government with a supplemental progress report to demonstrate how EMS planned to regain progress. At that point, EMS did not offer any explanations for its lack of progress.

Because EMS encountered piping that was not indicated in the Government’s drawings, the Government requested that EMS provide it with a proposed cost increase on May 26, 1995. EMS informed the Government that it would not require any additional days to be added to the contract completion date, but it continued to fail to make adequate progress under the contract throughout June and July, 1995. On August 4, 1995, the Government notified EMS that it was at least five weeks behind schedule and that it must take immediate steps to improve progress by September 15, 1995. EMS responded that it had experienced several delays due to rainfall but offered no further excuse for delays.

Unsatisfied with EMS’s excuse and delays, the Government held a meeting with EMS’s representatives on September 11, 1995 to discuss why little work had been performed and to express concern over EMS’s use of too few workers on the project. The Government claims the EMS representatives did not raise any issues justifying its failure to make progress and that EMS representatives did not ask for any equitable adjustments to the contract price, or for any extensions of the contract completion date. The Contracting Officer (CO) contacted EMS’s president on September 12, 1995 since he was not present at the earlier meeting. The Government notified EMS that it could expect a cure notice if the project was not on schedule by the milestone date of September 15, 1995. By this point, the Government had granted EMS permission to work several weekends in an effort to make up some of its work.

The Government issued a cure notice on September 19, 1995, informing EMS that its failure to improve progress and meet the approved contract milestones by September 15, 1995 was a condition endangering performance of the contract. The Government conducted a further review of EMS’s progress on October 5, 1995. In so doing, the Government found that EMS had not yet installed 2,125 linear feet of the required 5,205 linear feet of pipe between the pits, nor had it installed 100 linear feet of the required 210 linear feet of pipe within the pits. The Government calculated that EMS was at least 115 days from completing the contract.

The Government terminated its contract with EMS for default on October 10, 1995. The Government claims that at the time of termination, EMS had completed only approximately 60% of the required pipe installation, 50% of required electrical work, 30% of pit work, and none of the required work for insulation, landscaping and patch work. The Government further argues that a review of EMS’s payroll records revealed that EMS had not made sufficient attempts to accelerate progress to meet the contract requirements. After the termination, EMS responded with an explanatory letter on October 16, 1995, outlining the delays caused by differing site conditions and a further request for an extension of time. The Government rejected these documents.

III. Discussion

A. Law

Summary judgment is appropriate when there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law. RCFC 56(c); Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986); Jay v. Secretary, DHHS, 998 F.2d 979

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ECC International LLC
Armed Services Board of Contract Appeals, 2021
Harry Pepper and Associates, Inc.
Armed Services Board of Contract Appeals, 2020
Edge Construction Co. v. United States
95 Fed. Cl. 407 (Federal Claims, 2010)
Renda Marine, Inc. v. United States
66 Fed. Cl. 639 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
55 Fed. Cl. 637, 2003 U.S. Claims LEXIS 73, 2003 WL 1683852, Counsel Stack Legal Research, https://law.counselstack.com/opinion/engineered-maintenance-services-inc-v-united-states-uscfc-2003.