Nuclear Research Corporation v. The United States

814 F.2d 647, 33 Cont. Cas. Fed. 75,209, 1987 U.S. App. LEXIS 193
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 19, 1987
DocketAppeal 86-1434
StatusPublished
Cited by24 cases

This text of 814 F.2d 647 (Nuclear Research Corporation v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nuclear Research Corporation v. The United States, 814 F.2d 647, 33 Cont. Cas. Fed. 75,209, 1987 U.S. App. LEXIS 193 (Fed. Cir. 1987).

Opinion

EDWARD S. SMITH, Circuit Judge.

This is an appeal from the Armed Services Board of Contract Appeals’ (board) final decisions in ASBCA No. 28641 and in ASBCA No. 28979. 1 The board affirmed the contracting officer’s (CO) final decisions terminating the contract for default (ASBCA No. 28641) and demanding return of unliquidated progress payments (ASBCA No. 28979). The board’s final decisions are affirmed.

ISSUES
The issues presented on appeal are:
1. Whether the board had jurisdiction over the appeals from the CO’s final decisions;
2. Whether the board erred in finding •that the CO had exercised discretion in deciding to terminate the contract for default; and
3. Whether the board erred in sustaining the CO’s decision to terminate the contract for default.

BACKGROUND

On September 21, 1981, the Navy awarded Nuclear Research Corporation (NRC) a fixed-price contract for 24,930 thermoluminescent dosimeters (TLD). The TLD’s are radiation monitoring devices designed to be worn by Naval personnel in areas where they might be subject to greater than normal radiation.

A TLD is a small cylinder containing two small chips of manganese activated calcium fluoride to measure radiation exposure. The Navy required the TLD’s to be reusable, by “baking out” the stored radiation, at least 600 times.

*649 Under the original contract, NRC was to begin delivering TLD’s in 120 days, or by January 25, 1982, at the rate of 2,500 TLD’s per month until complete. NRC was unable to deliver acceptable TLD’s because of difficulty in obtaining satisfactory calcium fluoride chips. The contract was modified twice to allow deliveries to begin on February 23, 1983, at the rate of 2,000 TLD’s per month.

On or about February 23, 1983, NRC delivered the first lot of 2,000 TLD’s, but the lot was rejected for failure to pass the testing set out in the contract. On March 14, 1983, the Navy formally warned NRC that default termination was being considered. On April 22, 1983, NRC shipped a “partial lot” of 400 TLD’s, but the Navy refused to test the shipment, stating that it was too small to test economically.

On May 4, 1983, the CO issued a final decision terminating the contract for default for failure to deliver acceptable supplies within the time specified in the contract. On August 3, 1983, the CO issued another final decision demanding return of $332,752 in unliquidated progress payments.

NRC appealed both decisions to the board. After hearings, the board affirmed both decisions in a single opinion with detailed findings of fact and conclusions of law.

ANALYSIS

A. Jurisdiction of the Board.

The Government urges that the board had no jurisdiction over the appeal from the CO’s decision on default termination because the decision did not involve a claim for money. The Government further argues that the decision on return of unliquidated progress payments was completely independent of, and separately reviewable from, the decision on default termination.

In this instance, the board properly exercised jurisdiction over the combined appeals from both decisions. The decision on return of unliquidated progress payments involved the Government’s claim for money. The net amount of money owed by NRC is dependent on the propriety of the CO’s decision to terminate the contract for default. If default termination were improper, NRC may have been entitled to a settlement whereby its costs would have been subtracted from the payments received.

We hold that, in this case, the board had jurisdiction over the appeal from the final decision on default termination as well as the appeal from the final decision on the amount of unliquidated progress payments to be returned. 2

B. Contracting Officer’s Discretion to Terminate for Default.

In deciding whether to terminate a contract for default, the CO is required to exercise his discretion, to make sure that termination is in the best interests of the Government. 3 Here, NRC argues that the CO was simply following instructions to terminate the contract by the using agency, Naval Electronics Systems Command (NA-VELEX), and that he failed to exercise any discretion.

However, it is not the function of this court to make factual findings. The board heard the testimony, observed the witnesses, and considered all the evidence, and the board found that the CO had exercised his own discretion in deciding to terminate the contract. We must affirm the board’s decision unless it is legally in error, fraudulent, arbitrary, capricious, so grossly erroneous as to necessarily imply bad faith, or unsupported by substantial evidence. 4 It is under this standard that we must review the record before us.

NRC’s argument relies on evidence that, on April 28, 1983, the CO prepared an *650 internal memorandum concluding that, although the Government had the legal authority to terminate for default, it was not in the best interests of the Government to do so. NAVELEX, however, did not agree with the CO’s initial recommendation to continue the contract. After consulting with NAVELEX, the CO issued a final decision terminating the contract for default on May 4, 1983.

However, there is no implied prohibition against the CO consulting with the agency which would actually use the TLD’s. 5 Indeed, it is difficult to imagine how the CO could make an informed decision about the best interests of the Government without consulting with the agency most affected by the contract. The fact that the CO changed his mind after discussing the contract with NAVELEX, without more, is insufficient to show an abdication of discretion. 6

Moreover, there is substantial evidence to support the board’s decision. The CO testified that, although he considered the desires of the using agency, the final decision to terminate was his own. He further testified that his decision was based on his view that termination for default was in the best interests of the Government.

NRC had the opportunity to cross-examine the CO on the independence of his decision, 7 but NRC failed to show that the CO had been directed to terminate for default 8 or otherwise improperly influenced in his decision. 9

Therefore, the board’s finding, that the CO exercised discretion in deciding to terminate the contract for default, is affirmed.

C. Reasons for Default Termination.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pyrotechnic Specialties, Inc.
Armed Services Board of Contract Appeals, 2017
Securiforce International America, LLC v. United States
125 Fed. Cl. 749 (Federal Claims, 2016)
DayDanyon Corporation
Armed Services Board of Contract Appeals, 2014
Pinero v. United States
844 F. Supp. 2d 232 (D. Puerto Rico, 2012)
Universal Shelters of America, Inc. v. United States
87 Fed. Cl. 127 (Federal Claims, 2009)
General Injectables & Vaccines, Inc. v. Gates
519 F.3d 1360 (Federal Circuit, 2008)
Specialty Transportation, Inc. v. United States
57 Fed. Cl. 1 (Federal Claims, 2003)
Engineered Maintenance Services, Inc. v. United States
55 Fed. Cl. 637 (Federal Claims, 2003)
Davies Precision Machining, Inc. v. United States
35 Fed. Cl. 651 (Federal Claims, 1996)
Fairchild Industries, Incorporated v. United States
71 F.3d 868 (Federal Circuit, 1996)
Hannon Electric Co. v. United States
39 Cont. Cas. Fed. 76,664 (Federal Claims, 1994)
The Sharman Company, Inc. v. United States
2 F.3d 1564 (Federal Circuit, 1993)
Boeing Co. v. United States
37 Cont. Cas. Fed. 76,276 (Court of Claims, 1992)
Crippen & Graen Corp. v. United States
35 Cont. Cas. Fed. 75,726 (Court of Claims, 1989)
Mega Construction Co. v. United States
34 Cont. Cas. Fed. 75,445 (Court of Claims, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
814 F.2d 647, 33 Cont. Cas. Fed. 75,209, 1987 U.S. App. LEXIS 193, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nuclear-research-corporation-v-the-united-states-cafc-1987.