General Injectables & Vaccines, Inc. v. Gates

519 F.3d 1360, 2008 U.S. App. LEXIS 5750, 2008 WL 724245
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 19, 2008
Docket2007-1119
StatusPublished
Cited by15 cases

This text of 519 F.3d 1360 (General Injectables & Vaccines, Inc. v. Gates) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Injectables & Vaccines, Inc. v. Gates, 519 F.3d 1360, 2008 U.S. App. LEXIS 5750, 2008 WL 724245 (Fed. Cir. 2008).

Opinion

BRYSON, Circuit Judge.

General Inyectables & Vaccines, Inc. (“GIV”) appeals a decision of the Armed Services Board of Contract Appeals affirming the termination of a government contract for default. We affirm.

I

On January 14, 2004, the Defense Supply Center Philadelphia (“DSCP”), an agency within the Department of Defense, issued a solicitation requesting bids for influenza vaccine for the 2004-2005 flu season. GIV, a wholesale distributor of pharmaceuticals and supplies, submitted its initial bid on February 13, 2004. In that bid, GIV noted that it might “have to alter delivery schedule outlined in bid due to releases of vaccine.”

The DSCP awarded the contract to GIV on April 21, 2004. The final contract amended the “Delivery” subsection to specify that delivery was “[dependent on FDA release of vaccine.” Twenty-five percent of the total awarded quantity was to be delivered “no later than” September 30, 2004, another 25 percent by October 31, 2004, and the final 50 percent by November 30, 2005. The contract acknowledged that Chiron Vaccines, located in Liverpool, United Kingdom, would be responsible for the vaccine manufacturing and packaging. The contract also incorporated by reference FAR 52.212 — 4(f), which provides for “Excusable delays”:

The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers.

In late August 2004, Chiron discovered that certain lots of its vaccine were contaminated by bacteria. Chiron notified the FDA and indicated that it would not release any additional lots of vaccine without the approval of U.S. and U.K. authorities. British authorities inspected Chiron’s facilities in September and, on October 5, 2004, suspended its license to operate for three months.

In response to numerous inquiries by the DSCP, GIV sent the DSCP a letter on October 12, 2004, indicating that because of Chiron’s manufacturing problems, GIV would most likely not be able to deliver any vaccine:

This letter is to advise you that we have been informed by Chiron, our supplier of Fluvirin Influenza Vaccine, that it will not be able to supply any flu vaccine for the 2004-2005 flu season. As you have probably heard, [British authorities have] temporarily suspended Chiron’s license to manufacture Fluvir[i]n vaccine preventing the company from releasing any product for the 2004-2005 influenza season. As a consequence, we will be unable to fill any orders for Fluvir[i]n vaccine for the current flu season.
We deeply regret the unfortunate developments and we are doing everything *1363 possible to identify potential alternative sources of flu vaccine. However, because of the late timing of this unexpected development, we are not optimistic that we will be able to identify alternative sources of supply that could meet all or any option of your order.

On October 15, the FDA banned further imports of Fluvirin and ordered all existing U.S. stocks not to be distributed for use.

Subsequently, the DSCP contracting officer terminated GIV’s contract for default. The final decision, issued on November 15, 2004, indicated that GIV “failed to make timely delivery ... and ... such failure was not due to excusable causes.”

GIV appealed to the Armed Services Board of Contract Appeals, alleging that its performance had not become due because the condition precedent of “FDA release” had not occurred given the FDA’s embargo and freeze of domestic lots of Fluvirin. GIV also contended that any nonperformance was excused under FAR 52.212 — 4(f) because of “acts of the government” that were beyond the reasonable control of GIV.

The Board affirmed the termination for default. On cross-motions for summary judgment, the Board concluded that the condition precedent did not apply because GIV and Chiron were responsible for the failure to manufacture an acceptable product, which was the cause of the FDA’s refusal to release Fluvirin. The Board likewise concluded that “acts of the government” did not excuse nonperformance because the relevant act, the FDA approval process, was contingent on GIV’s delivery of conforming Fluvirin. In reaching those conclusions, the Board found that GIV was responsible for the actions of Chiron because GIV was a distributor that contracted with the government to sell Fluvirin, -and that it did not simply act as a common carrier for the vaccine.

II

The principles governing the failure to deliver contract goods are well established. A contractor’s failure to make timely delivery of agreed-upon goods establishes a prima facie case of default. See Nuclear Research Corp. v. United States, 814 F.2d 647, 650 (Fed.Cir.1987). The burden then shifts to the contractor to show that the failure to deliver the contract goods was excusable. See DCX, Inc. v. Perry, 79 F.3d 132, 134 (Fed.Cir.1996). An excusable failure of timely delivery occurs when the failure is “caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence.” FAR 52.212-4(f); DCX 79 F.3d at 134. The Board in this case concluded that GIV had failed to satisfy its obligation to produce vaccine that satisfied the requirements of the contract, and that it had failed to show that the default was excusable.

On appeal, GIV asserts that its failure to deliver any vaccine did not constitute a default because the condition precedent of FDA release of the vaccine had not occurred. Alternatively, GIV argues that if there was a default, it was excused under FAR 52.212 — 4(f).

A

GIV argues that FDA release of the vaccine was a condition precedent to GIV’s delivery obligation. Accordingly, GIV contends that once it showed that the condition precedent did not occur, the burden shifted to the government to show that *1364 some misconduct by GIV prevented the condition precedent from being satisfied. Thus, GIV contends that the government should have been required to prove that GIV was responsible for Chiron’s failure to produce uncontaminated vaccine, and that because the government did not prove GIV’s fault, it cannot be found in default. We disagree with GIV’s analysis.

The parties plainly understood that the essence of contract performance was production of vaccine that complied with the governing standards applied by the FDA. Moreover, GIV does not suggest that the actions of either the British authorities or the FDA in preventing distribution of the Chiron vaccine were improper. Thus, GIV’s failure to supply the vaccine constituted a simple failure of performance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SupplyCore, Inc.
Armed Services Board of Contract Appeals, 2022
John's Tile and Carpet Service
Armed Services Board of Contract Appeals, 2020
Grow Life General Trading, LLC
Armed Services Board of Contract Appeals, 2019
Stobil Enterprise
Armed Services Board of Contract Appeals, 2019
Rashed Elham Trading Company
Armed Services Board of Contract Appeals, 2017
United Healthcare Partners, Inc.
Armed Services Board of Contract Appeals, 2016
Quality Trust Inc.
Armed Services Board of Contract Appeals, 2016
Securiforce International America, LLC v. United States
125 Fed. Cl. 749 (Federal Claims, 2016)
Terraseis Trading Limited
Armed Services Board of Contract Appeals, 2015

Cite This Page — Counsel Stack

Bluebook (online)
519 F.3d 1360, 2008 U.S. App. LEXIS 5750, 2008 WL 724245, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-injectables-vaccines-inc-v-gates-cafc-2008.