General Injectables & Vaccines, Inc. v. Gates

527 F.3d 1375, 2008 U.S. App. LEXIS 11762, 2008 WL 2261597
Court of Appeals for the Federal Circuit·Decided June 3, 2008·No. 2007-1119·Published·Cited by 16 cases

Opinion

ON PETITION FOR REHEARING

BRYSON, Circuit Judge.

General Injectables & Vaccines, Inc. (“GIV”) has filed a petition for rehearing in which it contends that the panel’s interpretation of the “excusable delays” provision at issue in this case, FAR 52.212-4(0, conflicts with several Court of Claims decisions, Poloron Products v. United States, 126 Ct.Cl. 816, 116 F.Supp. 588 (1953), Climatic Rainwear Co. v. United States, 115 Ct.Cl. 520, 88 F.Supp. 415 (1950), and *1376 H.B. Nelson Construction Co. v. United States, 87 Ct.Cl. 375 (1938). We think it appropriate to supplement our earlier opinion to address that contention.

FAR 52.212-4(f) reads as follows:

The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers.

The panel opinion interpreted that provision consistently with the general rule that an unexcused default by a subcontractor does not excuse nonperformance by the prime contractor. See Johnson Mgmt. Group CFC, Inc. v. Martinez, 308 F.3d 1245, 1252 (Fed.Cir.2002) (“A contractor is responsible for the unexcused performance failures of its subcontractors.”) (citing cases); Hutton Contracting Co. v. City of Coffeyville, 487 F.3d 772, 779 (10th Cir.2007) (“The most reasonable interpretation of ‘fault of [Hutton]’ in the force-majeure clause is ‘fault of Hutton and those to whom it delegates its responsibilities under the contract.’ ”); In re Mary Rogers Manley d/b/a Mary Rogers Real Estate, HUDBCA No. 76-27, 78-2 B.C.A. (CCH) ¶ 13,519, at 66248, 1978 WL 2465 (Oct. 25, 1978) (“The principle is well established that the prime contractor is responsible for unexcused failures of performance by its subcontractors.”); In re Pelton Water Wheel Co., IBCA 16, 1955 WL 29 (Oct. 12, 1955) (“Delays of a subcontractor do not excuse the prime contractor from performing on time unless the subcontractor’s difficulty itself results from an excusable cause under the contract.”). 1

GIV argues that Poloron Products, Climatic Rainwear, and H.B. Nelson stand for the proposition that if the contractual delay provision does not separately state that the contractor is liable for the unexcused actions of its subcontractor, then subcontractor delays are excusable as long as the contractor acted reasonably in selecting the subcontractor. In fact, those cases do not state that rule expressly, nor can the cases fairly be read as adopting such a rule implicitly.

The delay provisions in all three of the cited cases specified that the contractor would not be liable for delays due to “unforeseeable causes” beyond its control. The court in each of those cases focused on the foreseeability of the problem that resulted in the delay, not on whether the problem was foreseeable to the contractor as opposed to the subcontractor. In fact, in Climatic Rainwear, the court observed that the problem was “clearly unforeseeable on the part of everyone associated with the contract,” including the subcontractor. 88 F.Supp. at 426. In Poloron Products, the court found the delay caused by the subcontractor to be foreseeable to *1377 the contractor and therefore not excused. 116 F.Supp. at 595. And in H.B. Nelson the court regarded the failure of common carriers to deliver undamaged goods to be unforeseeable, without addressing the question whether the common carriers should be regarded as subcontractors for purposes of determining whether the plaintiff had established a valid excuse to performance. 87 Ct.Cl. at 375.

In a subsequent decision, the Armed Services Board of Contract Appeals noted that the H.B. Nelson case focused on the issue of foreseeability and did not establish any broad principle limiting the normal rule that a contractor is liable for the unexcused defaults of its subcontractors. See In re Hogan Mech., Inc., ASBCA No. 21612, 78-1 B.C.A. (CCH) ¶ 13,164, at 64,334, 1978 WL 2347 (Mar. 30, 1978) (“The Nelson case ignored the subcontractor issue and premised its decision completely upon the foreseeability issue”). We agree with that characterization, and we think the characterization applies equally to the other two cases on which GIV relies. We thus do not regard those cases as implicitly rejecting the longstanding rule discussed in the panel opinion and applied in this case. In fact, both the Court of Claims and this court, in cases post-dating the three cases on which GIV relies, have endorsed the principle that prime contractors are ordinarily responsible for the unexcused performance failures of their subcontractors. See Johnson Mgmt. Group, 308 F.3d at 1252; Olson Plumbing & Heating Co. v. United States, 221 Ct.Cl. 197, 602 F.2d 950, 957 (1979).

The H.B. Nelson case is distinguishable on another ground as well: it dealt with a failure of proper and timely delivery by a common carrier. A common carrier stands in a very different position from a supplier of the goods that the contractor has agreed to provide to the government. The Veterans Administration Board of Contract Appeals in In re Malan Construction Corp., VABCA No. 262, 1960 WL 148, 151 (June 17, 1960), distinguished H.B. Nelson on that ground: “The court obviously considered the case as involving an accident, the circumstances of which were not known, occurring when the equipment was in the custody of common carriers and beyond the control of the subcontractor who fabricated it and the contractor who ordered it.” Id. at 4. The importance of the distinction between a supplier and a common carrier is underscored by the fact that the H.B. Nelson case would not be decided differently under the FAR provision that was applied in this case. That provision, FAR 52.212-4(f), includes “delays of common carriers” among the conditions that constitute valid excuses for nonperformance because they are considered “beyond the reasonable control of the Contractor.” Thus, nothing in the H.B. Nelson case is contrary to our ruling that under FAR 52.212—4(f) the failure of a contractor’s supplier does not provide a valid excuse for contractor nonperformance unless the supplier’s failure is shown to be excusable.

Free access — add to your briefcase to read the full text and ask questions with AI

General Injectables & Vaccines, Inc. v. Gates, 527 F.3d 1375, 2008 U.S. App. LEXIS 11762, 2008 WL 2261597 (Fed. Cir. 2008).

527 F.3d 1375 (General Injectables & Vaccines, Inc. v. Gates) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Vision Distributors LLC
Armed Services Board of Contract Appeals, 2026
FlightSafety International, Inc.
Armed Services Board of Contract Appeals, 2022
SupplyCore, Inc.
Armed Services Board of Contract Appeals, 2022
John's Tile and Carpet Service
Armed Services Board of Contract Appeals, 2020
Grow Life General Trading, LLC
Armed Services Board of Contract Appeals, 2019
Stobil Enterprise
Armed Services Board of Contract Appeals, 2019
Rashed Elham Trading Company
Armed Services Board of Contract Appeals, 2017
United Healthcare Partners, Inc.
Armed Services Board of Contract Appeals, 2016
Securiforce International America, LLC v. United States
125 Fed. Cl. 749 (Federal Claims, 2016)
Terraseis Trading Limited
Armed Services Board of Contract Appeals, 2015
Stein v. Paradigm Mirasol, LLC
586 F.3d 849 (Eleventh Circuit, 2009)