Stobil Enterprise

CourtArmed Services Board of Contract Appeals
DecidedJanuary 18, 2019
DocketASBCA No. 61688, 61689
StatusPublished

This text of Stobil Enterprise (Stobil Enterprise) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stobil Enterprise, (asbca 2019).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) Stobil Enterprise ) ASBCA Nos. 61688, 61689 ) Under Contract No. FA3016-18-P-0074 )

APPEARANCE FOR THE APPELLANT: Mr. Billie 0. Stone CEO

APPEARANCES FOR THE GOVERNMENT: Jeffrey P. Hildebrant, Esq. Air Force Deputy Chief Trial Attorney Heather M. Mandelkehr, Esq. Lt Col Scott A. Van Schoyck, USAF Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE SHACKLEFORD

ASBCA No. 61688 is an appeal from a contracting officer's final decision (COFD) denying a contractor claim for $126,000. ASBCA No. 61689 is an appeal from a COFD terminating the subject appeal for default. Both entitlement and quantum are before us in ASBCA No. 61688; only the propriety of the termination for default is before us ASBCA No. 61689. Appellant has elected to proceed under Board Rule 12.2 for small business concerns. A decision under Rule 12.2 shall have no value as precedent, and in the absence of fraud, shall be final and conclusive and may not be appealed or set aside.

Further, the parties have chosen to submit the appeals for decision on the record pursuant to Board Rule 11, without a hearing. Each party has submitted initial and reply briefs and have submitted documents to be considered in deciding these appeals.

SUMMARY FINDINGS OF FACT

1. In January 2018, the 502d Contracting Squadron (government) issued a Request for Quotation (RFQ) on one contract line item number (CLIN) described as follows:

Remove Steel Overhead Door and replace with new 25' x 21' heavy duty rolling overhead door w/electrical operators. Bldg 84, JBSA Randolph See attached SOW dated 9 January 2018[.]

(R4, tab 2 at 1)

2. Paragraph 5 of the RFQ, Delivery/Assembly, states:

Delivery shall be FOB Destination and included in CLIN prices noted above, unless otherwise and clearly noted by offeror in submitted offer. The items must be fully assembled and ready for use upon delivery.

(R4, tab 2 at 2)

3. The SOW which was referenced in the RFQ was dated January 9, 2018, and provided, in relevant part, the provisions set forth below:

PROJECT SCOPE: The contractor shall furnish all supervision, labor, transportation, materials, tools, incidentals, equipment, and Quality Assurance to remove existing Overhead Door and install new Overhead Door, hardware, and electric motors at building 84, JBSA Randolph Air Force Base (AFB), TX.

PROJECT DESCRIPTION: The requirements of this project are but not limited to the following: Remove one (1) each steel overhead door and replace with new 25' by 21' heavy duty rolling overhead door with electric operators.

OVERHEAD DOOR DEMOLITION:

Remove and dispose of existing overhead doors and hardware.

OVERHEAD DOOR INSTALL:

Install 1 each 25' x 21' Heavy duty Rolling Overhead Door 20 Gauge Galvanized Steel flat slat with baked finish Heavy duty malleable galv. Steel end locks are to be provided

2 Steel angle guides Bottom weather seal Electric Operator with photo eyes[.]

(R4, tab I at 1)

4. The record reflects that appellant submitted a quote for $11,200 on January 19, 2018 (see R4, tab 3 at 5; gov't br. at 2).

5. On January 26, 2018, TS gt Heather Consola, the contract specialist for the government, emailed appellant with regard to its quote, stating:

I have been conducting the reviews of all quotes submitted for this requirement and I just wanted to clarify a few things with you based on just the pricing you sent us.

So there was a statement of work that was attached to the solicitation and we just want to make sure that the price you gave us includes all that was stated needed to be done? Does it also include the removal and haul away of the old door? I only ask because other contractors either did or didn't realize all that needed to be done.

(R4, tab 3 at 4-5)

6. Stobil replied on the same day that its "quote [did] not include the removal and haul away of the old door as well" (R4, tab 1 at 4 ).

7. On January 29, 2018, TSgt Consola responded by email to appellant as follows:

Thank you for clarifying. Would you please provide me a quote with the removal and disposal of the old door as well since that is stated as needed in the SOW. I am also attaching the Statement of Work so that you can ensure the new quote you will be providing is encompassing all that is requested for this requirement.

(R4, tab 3 at 3)

8. Appellant responded:

The quote would be $26,800.00 ... correction/new drum-plate

3 needed for new models and removal/disposal of old components.

(R4, tab 3 at 1)

9. On February 23, 2018, Contract No. FA3016-18-P-0074 was awarded to appellant in the firm-fixed-price amount of $26,800.00. The one CLIN in that contract required appellant to:

Remove Steel overhead door and replace with new 25' x 21' heavy duty rolling overhead door w/electrical operators IA W SOW dated 9 January 2018.

(R4, tab 4 at 3)

10. FAR 52.212-4, CONTRACT TERMS AND CONDITIONS-COMMERCIAL ITEMS (JAN 2017), was incorporated into the contract and provided in subsections (d) and (m) as follows:

(d) Disputes. This contract is subject to 41 U.S.C. Chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at FAR 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.

(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly I 4 terminated this contract for default, such termination shall be deemed a termination for convenience.

(R4, tab 4 at 4)

11. Addendum FAR 52.212-4(C), Changes, was also included in the contract and provided that "( c]hanges in the terms and conditions of this contract may be made only by written agreement of the parties" (R4, tab 4 at 4 ).

12. On April 25, 2018, appellant sent an email to TSgt Consola regarding the contract, as follows:

During our teams [sic] inspection of the drum ... an unforeseeable concern arose, as well as, a safety issue for our team ... the customer .... and the governments' [sic] requirement in general. CE [government] personnel was notified and a site visit occurred on today 25 April 2018. The existing drum was ruled possibly damaged by the lead technician and was unable to be unloaded. Evidence discovered [reveals] that the door has been damaged for about 2 yrs; that the motor possibly reversed the enter load; no movement of the load could be accomplished prior to downloading the system; and therefore a decision to continue with the use of the old drum is sought from the government at this point. In the interim, Stobil will obtain a manufacturer[' ls cost for a new drum w/plates and have a quote ready pending the government's decision.

(R4, tab 7 at 1)

13. On April 27, 2018, TSgt Consola replied to appellant, stating:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

General Injectables & Vaccines, Inc. v. Gates
519 F.3d 1360 (Federal Circuit, 2008)
General Injectables & Vaccines, Inc. v. Gates
527 F.3d 1375 (Federal Circuit, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
Stobil Enterprise, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stobil-enterprise-asbca-2019.