Whitlock Corporation v. United States

159 F. Supp. 602, 141 Ct. Cl. 758, 1958 U.S. Ct. Cl. LEXIS 105
CourtUnited States Court of Claims
DecidedMarch 5, 1958
Docket32-54
StatusPublished
Cited by17 cases

This text of 159 F. Supp. 602 (Whitlock Corporation v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Whitlock Corporation v. United States, 159 F. Supp. 602, 141 Ct. Cl. 758, 1958 U.S. Ct. Cl. LEXIS 105 (cc 1958).

Opinion

LITTLETON, Judge.

Plaintiff sues to recover amounts withheld by defendant under contracts which were admittedly performed. The defendant counterclaims for a larger amount representing excess costs allegedly sustained when an earlier supply contract between the parties was terminated for default and the goods repurchased elsewhere at greater cost. The controversy, therefore, centers on the counterclaim.

On March 7, 1952, the plaintiff, a wholesale hardware jobber, contracted to supply the Philadelphia Quartermaster Depot with 1,175,400 brass buckles at unit and total prices of $0.064 and $75,-225.60, respectively, pursuant to an invitation of the preceding December and plaintiff’s low bid thereon of January 9, 1952. 1 Since plaintiff was not a manufacturer it planned to subcontract the entire order, basing its bid on a commitment which it had obtained from The Hatheway Manufacturing Company, a small Connecticut manufacturer. Plaintiff had never dealt with Hatheway previously, but secured its name from a trade register which reported Hatheway to have been in business for over 50 years and to have what plaintiff considered to be an adequate credit rating. Hatheway offered to manufacture and deliver the buckles at a unit price of $0.05785. Neither plaintiff nor Hatheway had previously supplied or manufactured such an article and neither was familiar with the costs involved.

Plaintiff had specified clearly in its bid that the entire contract was to be performed by Hatheway under subcontract. Paragraph 27 of the General Provisions, Supply Contract, which accompanied plaintiff’s bid and became part of the subsequent contract, provided in part:

“27. Names and Location of Factories
“The names and locations of the factories where manufacture of the items bid upon will be performed are set forth herein. The performing of any of the work contracted for in any place other than that named herein is prohibited, unless the same is specifically approved in advance by the Contracting Officer. * * *”

The time for acceptance of plaintiff’s bid was extended to March 20 by mutual consent to afford defendant an opportunity to make a preaward survey of Hatheway’s facilities, pursuant to authority in the Armed Service Procurement Regulations. Although the record does not establish that such a preaward survey was made, the contract was awarded to plaintiff on March 7, 1952, and plaintiff immediately ordered Hatheway to proceed with the subcontract. The contract delivery dates were postponed one month so as to require fixed monthly quantities from May 30 through October 31, 1952. Plaintiff’s subcontract with Hatheway did not specify delivery dates, but plaintiff informed Hatheway later in March of the requirements.

Hatheway experienced difficulties in preparing its special jigs and dies, and plaintiff unsuccessfully requested defendant for a change in brass specifications. On July 9, 1952, with no buckles then or *605 thereafter produced, plaintiff learned Hatheway’s insolvency and inability to perform the subcontract. Plaintiff forthwith solicited bids from other manufacturers to complete the contract, obtaining its most favorable offer from Shields Fifth Avenue at a unit price of $0.08. Plaintiff requested defendant without success to be excused from performance, and then asked for an increase in the contract price to $0.08 per unit so that it could subcontract to Shields, without profit to itself. This, too, was refused by the contracting officer. of

Meanwhile, on July 18, 1952, the contracting officer terminated plaintiff’s contract for default, finding specifically that plaintiff’s failure to perform did not arise out of causes beyond its control and without its fault or negligence, and advising plaintiff that the buckles would be procured in the open market and plaintiff would be liable for any excess costs. Plaintiff filed a timely appeal with the Secretary of the Army who, through the Armed Services Board of Contract Appeals, affirmed the contracting officer on August 27, 1953, after a hearing. The contracting officer, after issuing an invitation to numerous suppliers and securing 14 bids, awarded a repurchase contract to Dorset Products, Inc., on October 1, 1952, at unit and total prices of $.08399 and $98,721.86. Dorset Products, Inc., was the lowest responsible bidder on the repurchase invitation, the lowest bidder having been properly rejected for just cause. Under this contract defendant paid Dorset $98,366.86 for the buckles, representing an excess of $23,893.52 over the price of $74,473.34 in plaintiff’s defaulted contract. The contract with Dorset provided for no discount on early payment.

The contracting officer’s termination of plaintiff’s contract was made pursuant to the following clause 11 of the General Provisions:

“11. Default
“(a) The Government may, subject to the provisions of paragraph (b) below, by written Notice of Default to the Contractor terminate the whole or any part of this contract in any one of the following circumstances :
“(i) if the Contractor fails to make delivery of the supplies or to perform the services within the time specified herein or any extension thereof; or
“(ii) if the Contractor fails to perform any of the other provisions of this contract, or so fails to make progress as to endanger performance of this contract in accordance with its terms, and in either of these two circumstances does not cure such failure within a period of 10 days (or such longer period as the Contracting Officer may authorize in writing) after receipt of notice from the Contracting Officer specifying such failure.
“(b) The Contractor shall not be liable for any excess costs if any failure to perform the contract arises out of causes beyond the control and without the fault or negligence of the Contractor. Such causes include, but are not restricted to, acts of God or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, unusually severe weather, and defaults of subcontractors due to any of such causes unless the Contracting Officer shall determine that the supplies or services to be furnished by the subcontractor were obtainable from other sources in sufficient time to permit the Contractor to meet the required delivery schedule.
“ (c) In the event the Government terminates this contract in whole or in part as provided in paragraph (a) of this clause, the Government may procure, upon such terms and in such manner as the Contracting Officer may deem appropriate, supplies or services similar to those so terminated, and the Contractor shall be liable to the Government for any excess costs for such similar supplies or services, Provided, That the Con *606 tractor shall continue the performance of this contract to the extent not terminated under the provisions of this clause.
* -x- * * * *
“12. Disputes

Free access — add to your briefcase to read the full text and ask questions with AI

Related

General Injectables & Vaccines, Inc. v. Gates
519 F.3d 1360 (Federal Circuit, 2008)
Elmore Moving and Storage, Inc. v. The United States
845 F.2d 1001 (Federal Circuit, 1988)
Udis v. United States
32 Cont. Cas. Fed. 73,268 (Court of Claims, 1985)
Midwest Industrial Painting of Florida, Inc. v. United States
31 Cont. Cas. Fed. 71,962 (Court of Claims, 1983)
Prestex, Inc. v. United States
31 Cont. Cas. Fed. 71,508 (Court of Claims, 1983)
Fairfield Scientific Corp. v. United States
611 F.2d 854 (Court of Claims, 1979)
Jennie-O Foods, Inc. v. United States
580 F.2d 400 (Court of Claims, 1978)
Eastern Air Lines, Inc. v. Gulf Oil Corp.
415 F. Supp. 429 (S.D. Florida, 1975)
United States v. Morrison
370 F. Supp. 193 (E.D. Virginia, 1974)
Schweigert, Inc. v. The United States
388 F.2d 697 (Court of Claims, 1967)
H & H Manufacturing Co. v. United States
168 Ct. Cl. 873 (Court of Claims, 1964)
Union Painting Co. v. United States
194 F. Supp. 803 (D. Alaska, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
159 F. Supp. 602, 141 Ct. Cl. 758, 1958 U.S. Ct. Cl. LEXIS 105, Counsel Stack Legal Research, https://law.counselstack.com/opinion/whitlock-corporation-v-united-states-cc-1958.