Midwest Industrial Painting of Florida, Inc. v. United States

31 Cont. Cas. Fed. 71,962, 4 Cl. Ct. 124, 1983 U.S. Claims LEXIS 1549
CourtUnited States Court of Claims
DecidedDecember 9, 1983
DocketNo. 456-81C
StatusPublished
Cited by13 cases

This text of 31 Cont. Cas. Fed. 71,962 (Midwest Industrial Painting of Florida, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Midwest Industrial Painting of Florida, Inc. v. United States, 31 Cont. Cas. Fed. 71,962, 4 Cl. Ct. 124, 1983 U.S. Claims LEXIS 1549 (cc 1983).

Opinion

OPINION

LYDON, Judge:

Plaintiff brings the present action, pursuant to the Contract Disputes Act, 41 U.S.C. §§ 601-613 (Supp. V 1981), to recover $82,-326.04 plus interest which the government withheld from the final payment on plaintiff’s painting contract with the Department of the Air Force (Air Force).

Plaintiff was the prime contractor on a project at MacDill Air Force Base (MacDill) involving the sandblasting and painting of certain buildings and equipment at said base. Plaintiff subcontracted to another painting contractor, Capitol Maintenance, Inc. (Capitol), the work under the contract which involved the sandblasting and priming of 60 jet fuel pumps and the buildings housing the pumps. Capitol failed to take adequate precautions to protect the seal assemblies in the pumps and as a result damaged the seals. The Air Force, subsequently, withheld $89,200 from its final payment on the contract to cover the estimated cost of repairing the seals.

Plaintiff concedes that Capitol damaged the pump seals by negligently sandblasting the fuel pumps. Plaintiff contends, however, that the government is entitled to withhold only $6,873.96 for the damaged seals and advances two arguments to support its contention. Plaintiff first argues that the government failed to mitigate its damages by halting the sandblasting operation of Capitol after the government learned that Capitol’s sandblasting method caused pump seal leaks. Plaintiff asserts [126]*126that the government is not entitled to recover for the repair of those pump seals damaged after the government learned of the damage being caused by the sandblasting since this damage was an avoidable consequence of Capitol’s improper sandblasting.

Plaintiff’s second argument is that the government is not entitled to recover the cost of replacing 14 of the seals which were damaged prior to the government’s learning of the seal leaks caused by the sandblasting. Plaintiff maintains that 14 of the 20 seals damaged prior to the time that the government learned of the seal leaks were old seals which had exceeded their normal life expectancy and which, in any event, were scheduled at the time of the sandblasting to be replaced within a period of 6 months to 2 years. Since the government replaced these old 14 seals with 14 new seals, plaintiff argues that the government is prohibited from recovering the replacement cost of these 14 old seals by the “new for old” rule of damages.

For its part, the government disputes plaintiff’s attempt to limit its recovery. It maintains that plaintiff’s mitigation of damages theory is inapplicable because it had no obligation to terminate plaintiff’s contract or Capitol’s contract performance. Further, the government maintains that it is entitled to recover the cost of replacing the 14 old seals since it merely replaced 14 nonleaking seals with another 14 nonleaking seals. The government concedes, however, that the total cost of repairing all 60 damaged seals was only $84,209.80, and that plaintiff is consequently entitled to recover $5,010.20. Plaintiff concedes liability for $6,873.96, the expense of repairing 6 new seals damaged prior to the government’s learning of the seal leaks. Accordingly, the sum in dispute is actually $77,315.84.

Following trial on the merits and upon consideration of the briefs of the parties, it is concluded that plaintiff is entitled to recover $36,519.44, plus interest as provided by law. This sum represents the amount conceded by the government plus the cost of replacing the 14 old seals with 14 new seals.

I.

After trial on the merits, the court makes the following findings of fact:

Plaintiff is a company which was incorporated in the State of Florida. On September 27, 1980, plaintiff entered into a contract with the Air Force (number FO 8602-80-C0073). This contract required plaintiff to waterblast and paint certain jet fuel pumps and the buildings housing these pumps at MacDill. In addition, the contract required plaintiff to paint other buildings at MacDill which are not at issue in this case.

Under this contract, there were 4 pumping stations to be worked on, stations 72, 75, 76, and 77. These pumping stations housed a total of 60 high pressure jet fuel pumps which were allocated as follows: stations 72 and 77 contained 10 pumps each, and stations 75 and 76 contained 20 pumps each. These pumps were deep-well turbine pumps which pumped fuel from underground tanks directly into airplanes. They were used to refuel aircraft which were on a quick turnaround since a plane could be refueled by these pumps without having to shut off its engines. These pumps fulfilled a critical need at MacDill because they were the only pumps at the base capable of transferring fuel from underground tanks to the fuel line where the planes refueled. Without the pumps at stations 72, 75, 76, and 77, normal refueling operations at the base could not take place.

After entering into the contract with the Air Force, plaintiff began the process of waterblasting these fuel pumps. Shortly after plaintiff had begun the waterblasting process, the Air Force determined that the waterblasting technique of removing the old paint would not provide the necessary base for a longlife protective coating. The Air Force, therefore, issued a stop-order in October 1980, and began to negotiate with plaintiff concerning a modification to the contract. As a result of these negotiations, the government drafted contract modifica[127]*127tion number P0001 which plaintiff signed on November 5, 1980.

This modification changed the surface preparation process from waterblasting to sandblasting for pump stations 72, 75, 76, and 77, and all pumps and piping within the buildings, as well as the buildings themselves. The modification stated that plaintiff “will provide all equipment, labor, supervision, and material required to sandblast, prime, and paint facilities 72, 75, 76, and 77 in accordance with the attached specifications.” In addition, the modification increased the contract price by $10,720 and extended the completion date by 45 calendar days.

The specifications contained in the modification stated that all “nonferrous metal surfaces, glass and gauges shall be protected against sandblasting damage and over-spray.” The original contract also contained a provision which made plaintiff “responsible for all damage to persons or property that occur [sic] as a result of its fault or negligence.”

Plaintiff subcontracted the sandblasting and painting of pump stations 72, 75, 76, and 77 to Capitol. This subcontract covered all pumps and piping at these 4 stations as well as the buildings which housed the pumps. Capitol did all the sandblasting and painting at stations 72, 75, 76, and 77. Under the original contract, both plaintiff and Capitol were responsible for ensuring the protection of the pump seal assemblies from sandblasting damage.

Capitol’s insurer on the project was Aetna Insurance Company (Aetna). Both Capitol and its insurer Aetna were noticed into this case by plaintiff as third-party defendants. Both Capitol and Aetna, however, elected, at trial, to withdraw from further proceedings in this action. By order dated April 26, 1982, Capitol and Aetna were dismissed as third-party defendants in this case.

On November 8, 1980, Capitol began work on its subcontract by sandblasting station 77.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sterling Savings Ass'n v. United States
80 Fed. Cl. 497 (Federal Claims, 2008)
RCS Enterprises v. United States
57 Fed. Cl. 590 (Federal Claims, 2003)
Koby v. United States
53 Fed. Cl. 493 (Federal Claims, 2002)
Citizens Federal Bank v. United States
52 Fed. Cl. 561 (Federal Claims, 2002)
Brazos Electric Power Cooperative, Inc. v. United States
52 Fed. Cl. 121 (Federal Claims, 2002)
BP Exploration & Oil, Inc. v. Moran Mid-Atlantic Corp.
147 F. Supp. 2d 333 (D. New Jersey, 2001)
Energy Capital Corp. v. United States
47 Fed. Cl. 382 (Federal Claims, 2000)
Quiman, S.A. de C.V. v. United States
42 Cont. Cas. Fed. 77,227 (Federal Claims, 1997)
Spandome Corp. v. United States
40 Cont. Cas. Fed. 76,738 (Federal Claims, 1995)
Northeastern Pennsylvania Shippers Cooperative ass'n v. United States
39 Cont. Cas. Fed. 76,713 (Federal Claims, 1994)
Cates v. Morgan Portable Building Corp.
780 F.2d 683 (Seventh Circuit, 1985)
Forest Environmental Services Co. v. United States
32 Cont. Cas. Fed. 72,683 (Court of Claims, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
31 Cont. Cas. Fed. 71,962, 4 Cl. Ct. 124, 1983 U.S. Claims LEXIS 1549, Counsel Stack Legal Research, https://law.counselstack.com/opinion/midwest-industrial-painting-of-florida-inc-v-united-states-cc-1983.