Ford Motor Company v. Dallas Power & Light Company

499 F.2d 400, 1974 U.S. App. LEXIS 7135
CourtCourt of Appeals for the Fifth Circuit
DecidedAugust 21, 1974
Docket73-1076
StatusPublished
Cited by41 cases

This text of 499 F.2d 400 (Ford Motor Company v. Dallas Power & Light Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ford Motor Company v. Dallas Power & Light Company, 499 F.2d 400, 1974 U.S. App. LEXIS 7135 (5th Cir. 1974).

Opinion

*403 JOHN R. BROWN, Chief Judge:

This case presents the issue of whether the District Court properly entered judgment for Dallas Power & Light Company (DP&L) based on jury answers to 13 questions submitted pursuant to F.R.Civ.P. 49(a). 1 The jury fixed Ford Motor Company’s (Ford) *404 damage at $473,649.00 for flood damages to approximately 650 Ford, Mercury and Lincoln-Continental used automobiles stored on property located below the DP&L Mountain Creek dam. 2 The jury concluded in answers to questions 4 and 8 that the existence of DP&L’s dam caused the water to rise more rapidly than if there had been no dam and that the failure of DP&L officials to give adequate warning information of the heavy discharge of flood waters were both proximate causes of the damages suffered by Ford’s automobiles. The District Court denied Ford’s motion for a judgment on the verdict and entered a take nothing judgment based on the jury’s affirmative answers to contributory negligence issues 9, 10, 11 and 12 which the Court concluded barred Ford from any relief on the theory of imputed contributory negligence. We do not think that Ford was entitled to a judgment based on the jury’s answers to the special issues but not for the reasons given by the District Court. The findings of the jury, on the special issues submitted, are insufficient to justify a verdict for Ford. We conclude, however, that the District Court failed to submit the case to the jury on the proper theory of liability and we therefore reverse and remand for a new trial.

*405 Before discussing either theory of liability, strict liability or negligence, a review is in order of the significant testimony given concerning the location at which the Ford automobiles were being stored, the structure of DP&L’s Mountain Creek dam, the manner of its operation and the flood which caused so much damage.

Big D

At the time of the flood the Ford vehicles were being stored on the premises of the Big D Auto Auction Company (Big D) 3 for reconditioning in preparation for resale. Big D generally dealt directly with auto manufacturers, contracting minor reconditioning work of one year old cars and then auctioning the cars to dealers at wholesale prices. Approximately 12,000 vehicles a year were taken through the Big D facilities and sold at auction. At the time of the flood, there were about 1900 automobiles stored on the Big D lot including automobiles belonging to General Motors, American Motors and Chrysler Corporations. 4

The Big D property near the suburban city of Grand Prairie was located approximately two miles downstream on Mountain Creek from DP&L’s Mountain Creek dam. The terrain of the land was described by experts at trial as flood plain. Big D was back from the Creek about one mile on a large more or' less level open area. There was inside storage on the lot for 300 cars and an additional 14 acres of surfaced parking enclosed by industrial fence.

The Mountain Creek Dam

The Mountain Creek dam was constructed in the mid-1930’s to serve as a cooling pond for DP&L’s Grand Prairie generating station. It was never intended to be used for flood control purposes. The dam, which is a rolled earth filled structure 5,000 feet long, crosses Mountain Creek, a natural tributary of the Trinity River. Behind the dam a reservoir known as Mountain Creek Lake was formed with a capacity of 22,840 acre feet with a water level of 457 feet above sea level. The sill elevation or lowest elevation of the dam is 431 feet above sea level. The top elevation of the earthen sections of the dam are 467 feét — making the maximum height of the dam 36 feet.

Along the 5,000 foot earthen wall are six metal tainter gates, each 34 feet wide. The gates themselves are only 27 feet high so the six gates make a 204 foot length measured across the front of the dam in which the maximum height is only 458 feet above sea level. 5 To allow the release of water from the lake, each gate opens from the bottom. The gates may each be raised a maximum of six feet creating a total gate opening of 36 feet if all six gates are open to maximum at the same time. 6

Experts for both Ford and DP&L testified that the tainter gates úsed in the Mountain Creek Lake dam were not designed for water to go over the top. Any release of water must go under the gates when they are raised.

Came The Flood

During the late afternoon and evening hours of May 6 and the early morning *406 hours of May 7, the Dallas region received an extremely heavy rainfall. 7 Since the 300 square mile watershed of the Mountain Creek Reservoir is within this region, there was an extraordinary increase in the amount of water discharging into the lake. Experts for DP &L estimated that over 77,000 acre feet of water came through the lake during May 6 through May 8. With a total normal lake capacity of only 22,840 acre feet, large amounts of water were necessarily passed through the dam and down Mountain Creek to the Trinity River.

Crane, the manager of Big D, testified that in spite of the heavy rains during the night of May 6, there were no floodwaters on the Big D property when he arrived at work about 8 a. m. on the morning of May 7. In fact the rains had subsided by that time. Not until around 8:30 a. m. did Big D begin to take some water, thus arousing the concerns of the Big D management. DP& L had been allowing the heavy rain waters to flow through the dam during the evening of May 6 and early hours of May 7. According to DP&L’s Assistant Supervisor at Mountain Creek Reservoir, the tainter gates were open to 22 feet at 8 a. m. on May 7. At 9 a. m. the gate opening was 25 feet and by 11 a. m. the opening’ had been increased to 30 feet. The gates remained open at 30 feet all through the afternoon of the 7th and not until 7 p. m. were they lowered to 28 feet. The downstream flood waters did not crest until between 5 and 6 p. m. on May 7. 8

Acting on his concern over the rising waters of Mountain Creek, Big D manager Crane called the DP&L generating station on Mountain Creek Reservoir around 8:30 on the morning of May 7. He identified himself and asked for information regarding DP&L’s plans as to how long the flood gates would be open and how wide the opening would be. The response of the DP&L employee was that he could not give out any information. 9 Crane testified that he was given a downtown number which he called but again received no information. Finally, Crane contacted Bobby J. Adams, a sergeant in the Grand Prairie Police Department, who was off-duty and asked him to contact DP&L and try to get some information. Adams testified that he called the dam about 9:30 a. m.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lorita Savoie v. Huntington Ingalls, Inc.
817 F.3d 457 (Fifth Circuit, 2016)
Randy Austin v. Kroger Texas, L.P.
731 F.3d 418 (Fifth Circuit, 2013)
City of Keller v. Wilson
86 S.W.3d 693 (Court of Appeals of Texas, 2002)
Gaudreau v. Clinton Irrigation District
2001 MT 164 (Montana Supreme Court, 2001)
San Benito Bank & Trust v. Landair Travels
31 S.W.3d 312 (Court of Appeals of Texas, 2000)
Doddy v. Oxy USA, Inc.
101 F.3d 448 (Fifth Circuit, 1996)
Jones v. Texaco, Inc.
945 F. Supp. 1037 (S.D. Texas, 1996)
Eugene Carvin Donna Carvin, on Behalf of Themselves and All Others Similarly Situated James H. Breashears Sharlene G. Breashears Clifton E. Buck Frances M. Buck Dennis Carvin Sara E. Bentley Milton Couch Janet M. Couch Edwin C. Coulson Anna Jeanette Coulson Howard Cranford Janice Cranford Hazel Goodman Jimmy W. Harris Sandra D. Harris Guy M. Hauser James D. Honold Willie Mae Honold M.L. Hooper Unknown Spouse of M.L. Hooper Michael L. Hulsey Unknown Spouse of Michael L. Hulsey Effie Jenkins Donna M. Johnson Charles B. Joplin Clarice M. Joplin Fred B. Kruse R. MacLambert Patricia Lambert T.M. McGregor Aileen McGregor Michael E. Mitchell Brownie K. Mitchell Russell A. New Joe N. Nowell Patsy M. Nowell A.W. O'Keefe Wayne Parsons Roxanne M. Parsons James W. Raney Norma J. Raney Evelyn W. Ray John W. Rayfield Lucille M. Rayfield Terry J. Rickard Patsy Rickard Clark B. Robertson Ruby Robertson B.E. Rust Kenneth M. Schnoeblen Jean Schnoeblen Leon E. Scott Unknown Spouse of Leon E. Scott Billy J. Smallwood Mary S. Smallwood Hoyt W. Smart Virginia A. Smart William F. Smith William H. Stovall Patricia Lee Stovall A.W. Taylor Lois Irene Taylor Donna J. Whistle Jerry S. Yahoda Jane L. Yahoda Chester I. Ziemienski Anna Q. Ziemienski v. Arkansas Power and Light Company, an Arkansas Corporation, Federal Signal Corporation, an Illinois Corporation, Entergy Services, a Delaware Corporation, Martin D. Danford Faye A. Danford Anthony Dematteo Nancy Dematteo Stanley P. Dodd Sally P. Dodd Harry D. Peterson Elaine R. Peterson v. Arkansas Power and Light Company, an Arkansas Corporation Entergy Services, Inc., a Delaware Corporation
14 F.3d 399 (Eighth Circuit, 1994)
Carvin v. Arkansas Power & Light Co.
14 F.3d 399 (Eighth Circuit, 1993)
Dalon v. City of DeSoto
852 S.W.2d 530 (Court of Appeals of Texas, 1992)
Bank One, Texas, N.A. v. Taylor
970 F.2d 16 (Fifth Circuit, 1992)
Barras v. Monsanto Co.
831 S.W.2d 859 (Court of Appeals of Texas, 1992)
Gutierrez v. Scripps-Howard
823 S.W.2d 696 (Court of Appeals of Texas, 1992)
Cook Consultants, Inc. v. Larson
700 S.W.2d 231 (Court of Appeals of Texas, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
499 F.2d 400, 1974 U.S. App. LEXIS 7135, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ford-motor-company-v-dallas-power-light-company-ca5-1974.