VAN DUSEN, Senior Circuit Judge.
I. INTRODUCTION
This appeal is from a December 2, 1977, district court judgment after a non-jury trial, awarding plaintiff, Shea-S&M Ball (Shea), $14,000.00 in damages. Shea commenced this action sounding in contract and tort against Massman-Kiewit-Early (MKE) and the Washington Metropolitan Area Transit Authority (WMATA) as a result of recurrent overflows of water from MKE’s construction site onto Shea’s.
The trial court found that MKE was obligated under §§ 3.4 and 3.6.9
of its
contract with WMATA to control groundwater within its area and to prevent the sewer from overflowing. Shea was found to be a third-party beneficiary of that contract. Although MKE was found to have breached its contract, the trial court limited Shea’s recovery because it found that the first flood was caused by an act of God, the later floods were foreseeable, and Shea did not properly mitigate its damages.
The court never reached the question of whether MKE was negligent as it concluded that Shea could not recover on its negligence claim because it was “contributorily negligent in failing to take the obvious steps to avoid the injury” (8a).
Finally, the trial court found that WMATA had no duty to supervise or enforce its solution to the flooding problem.
Because we have concluded that there was insufficient evidence in the record to support the district court’s conclusion that the first flood was an act of God, and that district court applied an incorrect rule of law in concluding that Shea did not properly mitigate damages, and erred in concluding that WMATA had no duty to resolve disputes between adjoining contractors, we reverse the December 2, 1977, judgment and remand the case to the district court for further proceedings consistent with this opinion.
II. ACT OF GOD
The first flood, which occurred on June 21,1973, could only be an act of God if the rains were “an unprecedented and extraordinary occurrence of unusual proportions and could not have reasonably been foreseen by the parties.”
Barnard-Curtiss Company v. United States,
257 F.2d 565, 568 (10th Cir. 1958).
Accord, Gleeson v. Virginia Midland R’D Co.,
140 U.S. 435, 11 S.Ct. 859, 35 L.Ed. 458 (1891);
UniRoyal, Inc. v. Hood,
588 F.2d 455 (5th Cir. 1979);
Marriott Corporation v. Norfolk and Western Ry. Co.,
319 F.Supp. 646 (E.D.Mo.1970);
Garner v. Ritzenberg,
167 A.2d 353 (D.C. Mun.App.1961); 1 C.J.S. Act of God 1423 (1936). There is no evidence in the district court record upon which the court could conclude that the rains that caused Shea’s damages were extraordinary or unusual. The record is completely devoid of any evidence of the normal range of rainfall in Washington, D. C., and the amount of rain that actually fell during the time periods when the floods occurred.
Heavy rainfalls, unless they are unusual and extraordinary, are not considered acts of God.
Marriott Corporation
v.
Norfolk and Western Ry. Co., supra; McCarthy v. District of Columbia,
168 A.2d 910 (D.C. Mun.App.1961);
Garner v. Ritzenberg, supra.
The
Garner
court stated:
“We take judicial notice that rains of heavy intensity and average duration are occurrences of common experience. This event was described as a flash flood. People often use that expression in describing accumulations of rain water running off along natural or artificial contours of the ground; but that imports no particular legal significance. Such events, though infrequent, are to be expected. They do not create the widespread devastation commonly associated with earthquakes, tornadoes, hurricanes or extraordinary floods. The occasional filling of low-level or basement areas by rain water is a probable and foreseeable result of a heavy rain. To classify it as an act of God is an unwarranted extension of that doctrine not supported by the authorities.”
Garner v. Ritzenberg, supra
at pages 354-55.
The trial judge concluded that the first flood was an act of God in the absence of evidence that the rainfall was extraordinary or unusual. Because the defendants did not introduce sufficient evidence for a trier of fact to conclude that the first rainfall was an act of God, this defense must fail. Since we agree with the trial court that the plaintiff is the third-party beneficiary of a contract between the defendants and that MKE breached that contract by allowing rain water to flow onto Shea’s construction site, upon remand the trial
court
will have to make a determination of the damages Shea incurred as a result of the first flood.
III. MITIGATION OF DAMAGES
The trial court granted Shea only a small portion of its damages, despite the fact that it found that MKE had breached its duties under the contract. The district court concluded that Shea had not properly mitigated its damages by failing to build a dike at or near the interface.
See
footnote 3.
Although the law does not permit an injured party to stand idly by, accumulating damages, when certain obvious, reasonable steps, if taken, would have greatly reduced the damages, the law does not penalize the nonbreaching party in the type of situation that is before this court.
“Where both the plaintiff and the defendant have had equal opportunity to reduce the damages by the same act and it is equally reasonable to expect the defendant to minimize damages, the defendant is in no position to contend that the plaintiff failed to mitigate. Nor will the award be reduced on account of damages the defendant could have avoided as easily as the plaintiff.
See
Dobbs, Handbook on the Law of Remedies § 3.7 at 186 (1973). The duty to mitigate damages is not applicable where the party whose duty it is primarily to perform a contract has equal opportunity for performance and equal knowledge of the consequences of nonperformance.
See Parker v. Harris Pine Mills,
206 Or. 187, 291 P.2d 709 (1955).”
S. J. Groves & Sons Co. v. Warner Co.,
576 F.2d 524, 530 (3d Cir. 1978).
Accord, McCarty v. United States,
185 F.2d 520
Free access — add to your briefcase to read the full text and ask questions with AI
VAN DUSEN, Senior Circuit Judge.
I. INTRODUCTION
This appeal is from a December 2, 1977, district court judgment after a non-jury trial, awarding plaintiff, Shea-S&M Ball (Shea), $14,000.00 in damages. Shea commenced this action sounding in contract and tort against Massman-Kiewit-Early (MKE) and the Washington Metropolitan Area Transit Authority (WMATA) as a result of recurrent overflows of water from MKE’s construction site onto Shea’s.
The trial court found that MKE was obligated under §§ 3.4 and 3.6.9
of its
contract with WMATA to control groundwater within its area and to prevent the sewer from overflowing. Shea was found to be a third-party beneficiary of that contract. Although MKE was found to have breached its contract, the trial court limited Shea’s recovery because it found that the first flood was caused by an act of God, the later floods were foreseeable, and Shea did not properly mitigate its damages.
The court never reached the question of whether MKE was negligent as it concluded that Shea could not recover on its negligence claim because it was “contributorily negligent in failing to take the obvious steps to avoid the injury” (8a).
Finally, the trial court found that WMATA had no duty to supervise or enforce its solution to the flooding problem.
Because we have concluded that there was insufficient evidence in the record to support the district court’s conclusion that the first flood was an act of God, and that district court applied an incorrect rule of law in concluding that Shea did not properly mitigate damages, and erred in concluding that WMATA had no duty to resolve disputes between adjoining contractors, we reverse the December 2, 1977, judgment and remand the case to the district court for further proceedings consistent with this opinion.
II. ACT OF GOD
The first flood, which occurred on June 21,1973, could only be an act of God if the rains were “an unprecedented and extraordinary occurrence of unusual proportions and could not have reasonably been foreseen by the parties.”
Barnard-Curtiss Company v. United States,
257 F.2d 565, 568 (10th Cir. 1958).
Accord, Gleeson v. Virginia Midland R’D Co.,
140 U.S. 435, 11 S.Ct. 859, 35 L.Ed. 458 (1891);
UniRoyal, Inc. v. Hood,
588 F.2d 455 (5th Cir. 1979);
Marriott Corporation v. Norfolk and Western Ry. Co.,
319 F.Supp. 646 (E.D.Mo.1970);
Garner v. Ritzenberg,
167 A.2d 353 (D.C. Mun.App.1961); 1 C.J.S. Act of God 1423 (1936). There is no evidence in the district court record upon which the court could conclude that the rains that caused Shea’s damages were extraordinary or unusual. The record is completely devoid of any evidence of the normal range of rainfall in Washington, D. C., and the amount of rain that actually fell during the time periods when the floods occurred.
Heavy rainfalls, unless they are unusual and extraordinary, are not considered acts of God.
Marriott Corporation
v.
Norfolk and Western Ry. Co., supra; McCarthy v. District of Columbia,
168 A.2d 910 (D.C. Mun.App.1961);
Garner v. Ritzenberg, supra.
The
Garner
court stated:
“We take judicial notice that rains of heavy intensity and average duration are occurrences of common experience. This event was described as a flash flood. People often use that expression in describing accumulations of rain water running off along natural or artificial contours of the ground; but that imports no particular legal significance. Such events, though infrequent, are to be expected. They do not create the widespread devastation commonly associated with earthquakes, tornadoes, hurricanes or extraordinary floods. The occasional filling of low-level or basement areas by rain water is a probable and foreseeable result of a heavy rain. To classify it as an act of God is an unwarranted extension of that doctrine not supported by the authorities.”
Garner v. Ritzenberg, supra
at pages 354-55.
The trial judge concluded that the first flood was an act of God in the absence of evidence that the rainfall was extraordinary or unusual. Because the defendants did not introduce sufficient evidence for a trier of fact to conclude that the first rainfall was an act of God, this defense must fail. Since we agree with the trial court that the plaintiff is the third-party beneficiary of a contract between the defendants and that MKE breached that contract by allowing rain water to flow onto Shea’s construction site, upon remand the trial
court
will have to make a determination of the damages Shea incurred as a result of the first flood.
III. MITIGATION OF DAMAGES
The trial court granted Shea only a small portion of its damages, despite the fact that it found that MKE had breached its duties under the contract. The district court concluded that Shea had not properly mitigated its damages by failing to build a dike at or near the interface.
See
footnote 3.
Although the law does not permit an injured party to stand idly by, accumulating damages, when certain obvious, reasonable steps, if taken, would have greatly reduced the damages, the law does not penalize the nonbreaching party in the type of situation that is before this court.
“Where both the plaintiff and the defendant have had equal opportunity to reduce the damages by the same act and it is equally reasonable to expect the defendant to minimize damages, the defendant is in no position to contend that the plaintiff failed to mitigate. Nor will the award be reduced on account of damages the defendant could have avoided as easily as the plaintiff.
See
Dobbs, Handbook on the Law of Remedies § 3.7 at 186 (1973). The duty to mitigate damages is not applicable where the party whose duty it is primarily to perform a contract has equal opportunity for performance and equal knowledge of the consequences of nonperformance.
See Parker v. Harris Pine Mills,
206 Or. 187, 291 P.2d 709 (1955).”
S. J. Groves & Sons Co. v. Warner Co.,
576 F.2d 524, 530 (3d Cir. 1978).
Accord, McCarty v. United States,
185 F.2d 520 (5th
Cir. 1950);
Unverzagt v. Young Builders, Inc.,
252 La. 1091, 215 So.2d 823 (1968);
Parker v. Harris Pine Mills,
206 Or. 187, 291 P.2d 709 (1955); 22 Am.Jur.2d Damages § 37 (1965); 25 C.J.S. Damages § 34 (1966). MKE breached its contract by allowing surface water to run off its jobsite onto Shea’s jobsite. Pursuant to its contract with WMATA, MKE had the primary responsibility for controlling its water runoff and had the same opportunity as Shea to build a dike that would have prevented the damages. MKE also had knowledge of the consequences of nonperformance. Therefore, the doctrine of mitigation of damages is not applicable. On remand, the district court will have the opportunity to recalculate Shea’s damages in accordance with this opinion, if Shea presents sufficient evidence to form a basis for such recalculation.
IY. CLAIM AGAINST WMATA
With respect to plaintiff’s claims against WMATA, the district court held that:
“WMATA through its engineers and consultants undertook to advise and consult with its contractors and supervised their performance against specifications. It convened the February 1974 meeting in an attempt to arrive at a reasonable solution. Beyond this it had no duty, contractual or otherwise, to enforce its resolution of a dispute between two adamant contractors who had contractual obligations to cooperate and remedy a problem wholly within their control.” (8a)
We disagree with this conclusion of the district court. Section 1.14 of the contracts in question are as follows:
“The Authority may undertake or award other contracts for additional work, and the Contractor shall fully cooperate with such other contractors and Authority employees and carefully fit his own work to such additional work as may be directed by the Contracting Officer. The Contractor shall not commit or permit any act which will interfere with the performance of work by any other contractor or by Authority employees.”
In
Hoffman
v.
United States,
340 F.2d 645, 166 Ct.Cl. 39 (1964), which involved similar provisions in contracts
between the United States and contractors who were constructing parallel bridges 500 feet apart on the same river, the court held that the United States had an obligation under the contract to secure the cooperation of the upstream contractor for the benefit of the downstream contractor. The court went on to state:
“These rights inured through the right of the Government to require cooperation from this subcontractor through the Government contract with the prime contractor, the State of Oregon. There is no evidence that defendant ever attempted to secure this cooperation, other than arranging for one unsuccessful conference with Young & Smith who refused to make any changes ‘because nobody offered to pay for it.’
“ . . . For the Board to say, under circumstances where the contracting officer himself found the acts of the contractor upstream to be the cause of plaintiff’s delay, that ‘the contracting officer is not designated by the contract as the arbiter and quite properly refused to take sides in the matter,’ is a complete and unwarranted disavowal of all responsibility on the part of the Government to direct or require cooperation from anyone (except
plaintiff). Such a conclusion by the Board is erroneous as a matter of law and not supported by the substantial evidence in the administrative record.”
Id.
at pages 650-51.
The contracting authority has the duty to invoke its contractual rights to compel cooperation among contractors. Abutting contractors enter into contracts such as are present here with entities such as WMATA with the expectation that supervisory authority will be exercised to insure cooperation.
Cf. Paccon, Inc. v. United States,
399 F.2d 162, 185 Ct.Cl. 24 (1968); L.
L. Hall Construction Co. v. United States,
379 F.2d 559, 177 Ct.Cl. 870 (1966).
In this case, as in
Hoffman,
the contracting authority limited the exercise of its supervisory authority to the arranging of an unsuccessful conference, when it had a duty to compel cooperation. Shea had a right to expect cooperation from MKE and to expect WMATA to enforce § 1.14 for Shea's benefit. WMATA's failure to exercise its supervisory function and compel cooperation has resulted in their breach of a contractual duty owed to Shea. Therefore, the district court erred in concluding that Shea’s cause of action against WMATA lacked merit.
V. CONCLUSION
The case will be remanded to the district court for further proceedings in accordance with this opinion.