Lee Hoffman v. The United States

340 F.2d 645, 166 Ct. Cl. 39, 1964 U.S. Ct. Cl. LEXIS 96
CourtUnited States Court of Claims
DecidedMay 15, 1964
Docket259-59
StatusPublished
Cited by21 cases

This text of 340 F.2d 645 (Lee Hoffman v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lee Hoffman v. The United States, 340 F.2d 645, 166 Ct. Cl. 39, 1964 U.S. Ct. Cl. LEXIS 96 (cc 1964).

Opinion

DURFEE, Judge *

Plaintiff claims additional compensation for increased costs under the “changed conditions” provision of a contract with defendant for construction of a railroad bridge in Oregon. This construction was part of a Federal dam project which required the relocation of highway and railroad facilities in the State of Oregon. The entire project also included construction, at about the same time, of a highway bridge parallel to and immediately upstream from plaintiff’s railroad bridge project on the Deschutes River. The highway bridge was constructed by another company, Young & Smith, under an earlier contract with the State of Oregon, which had the prime contract with defendant for construction of this highway bridge.

Prior to plaintiff’s bid on the railroad bridge, Young & Smith had been awarded the sub-contract for the highway bridge by the State of Oregon. It had planned a cofferdam across part of the river above the highway bridge to facilitate and protect its construction, and had quarried the rock therefor. Upon learning that plaintiff was the low bidder for the railroad bridge immediately below, 1 Young & Smith proposed sharing the cost of its cofferdam with plaintiff, together with other cooperative proposals such as sharing equipment. Plaintiff replied that he could make no commitment until he knew that he was to be awarded his contract. During the next two weeks, the parties were unable to arrange a meeting, and Young & Smith proceeded to build its cofferdam.

Prior to construction of the Young & Smith cofferdam above the highway bridge upstream, the normal width of the river at this location was 200 to 250 feet. The distance between the two railroad bridge abutments on the east and west river banks was about 500 feet, and the main channel, before construction of the Young & Smith cofferdam upstream would have run approximately under the middle area of the proposed railroad bridge. 2

Plaintiff’s railroad bridge project downstream and Young & Smith’s highway bridge project upstream were to be constructed parallel in an east-west direction, and less than 68 feet apart. Plaintiff’s plans for the railroad bridge *647 called for bridge support by a masonry abutment (Number 2) on the east bank of the river, another abutment (Number 1) on the west bank of the river, and intermediate piers in the river channel numbered 1 to 5 from west to east.

The plans for Young & Smith’s highway bridge called for supports called “bents,” numbered 1 to 9 from west to east. Bents 1 and 9 had the same purpose as Abutments 1 and 2 of the railroad bridge, and Bents 2 to 8 the same purpose as Piers 1 to 5 of the railroad bridge. The highway bridge upstream was to extend longitudinally farther both west and east than the railroad bridge, with its Bent 1 lying slightly west of Abutment 1 of the railroad bridge, and Bent 9 lying slightly east of Abutment 2. The relative location of the proposed highway and railroad bridges is depicted in the following diagram:

Relative Location of Relocated Highway and Railroad Bridges

YOUNG & SMITH’S CONSTRUCTION OF A COFFERDAM

According to the contract drawings of the Corps of Engineers, it could be reasonably estimated that during the period of construction under plaintiff’s contract, about 1% feet of water would be touching Abutment 2 of the railroad bridge on the east side of the river, and about 2% feet of water would be around the furthermost pier (Number 5) on the east side. This would not create a major water problem. From his investigation of the site and defendant’s water-flow charts before and after bidding on the railroad bridge contract, plaintiff was justified in concluding that the amount of water around Abutment 2 and Pier 5 at the east side of the river would not be substantial during the construction *648 period, and that elaborate cofferdamming would not be necessary.

Plaintiff received notice from defendant to proceed with his contract for the railroad bridge on July 6, 1954. By this time Young & Smith had completed construction of its cofferdam above the highway bridge upstream. This cofferdam was a solid and continuous rock and sand-fill barrier extending from Bent 1 of the highway bridge on the east bank of the river west across two-thirds of the channel to Bent 7. The two bridge sites are located at the bottom of swift rapids and the Young & Smith cofferdam diverted the entire flow of the river from the wide central main channel to a new narrow channel on the east side. As a result, the entire river then passed over the “normally high and dry” location of plaintiff’s east Abutment 2 and Pier 5 for the railroad bridge with considerable added depth, speed and force. A better method of dewatering by Young & Smith under accepted engineering practice would have been construction of a series of individual cofferdams at each of the nine highway bridge “bents” or piers connected by temporary bridging for access. This established method would not have diverted the central main channel to the east one-third of the river bed, and this was the method that plaintiff planned to use when he had also bid on the highway bridge.

Because of this unexpected river diversion confronting plaintiff on the day he was authorized to start construction, he delayed his operations on the east side of the river, and proceeded with construction only on the west side at Abutment 1, Piers 1 and 2, which was now relatively dry. At various times shortly after receiving notice to proceed, plaintiff asserted orally and in writing to defendant’s representatives that these changed conditions at the site had resulted from the Young & Smith cofferdam a short distance upstream. Plaintiff asserted that Abutment 2 could only be constructed after he first built a cofferdam there at great increase in cost. He stated that the combination of this cofferdam with that of Young & Smith’s immediately upstream would result in virtually damming the entire river, thus causing extreme danger to the cofferdam upstream, to life and to property.

Plaintiff accordingly requested the contracting officer orally and in writing to issue a stop order on construction of Abutment 2, the site of which was now under what plaintiff described as “a great howling mass of water.” He also requested an extension of the completion date thereon until Young & Smith had completed its work upstream to the stage where it could pull its cofferdam back west more to the former center of the channel, and thus eliminate the flooded condition on the east side of the river at Abutment 2 and Pier 5. He asserted that these circumstances were changed conditions under the contract throughout a series of conferences and correspondence extending from early in August through the middle of September, 1954.

To these allegations of changed conditions by plaintiff and to his request for a stop order on Abutment 2, the contracting officer replied that there was no evidence of changed conditions within the meaning of the contract or as a basis for issuance of a stop order or time extension for completion of the abutments, and refused to issue the stop order on Abutment 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Extreme Coatings, Inc. v. United States
109 Fed. Cl. 450 (Federal Claims, 2013)
Olympus Corporation v. United States
98 F.3d 1314 (Federal Circuit, 1996)
Turnkey Enterprises, Inc. v. United States
597 F.2d 750 (Court of Claims, 1979)
Dobson v. Rutgers, State University
384 A.2d 1121 (New Jersey Superior Court App Division, 1978)
Roscoe-Ajax Construction Co. v. United States
458 F.2d 55 (Court of Claims, 1972)
Hoel-Steffen Construction Co. v. United States
456 F.2d 760 (Court of Claims, 1972)
Paccon, Inc. v. The United States
399 F.2d 162 (Court of Claims, 1968)
Perini Corporation v. United States
381 F.2d 403 (Court of Claims, 1967)
Perini Corp. v. United States
381 F.2d 403 (Court of Claims, 1967)
Banks Construction Company, Inc. v. The United States
364 F.2d 357 (Court of Claims, 1966)
Hoffman
172 Ct. Cl. 687 (Court of Claims, 1965)
Farnsworth & Chambers Co., Inc. v. The United States
346 F.2d 577 (Court of Claims, 1965)
Hunt & Willett, Inc. v. United States
351 F.2d 980 (Court of Claims, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
340 F.2d 645, 166 Ct. Cl. 39, 1964 U.S. Ct. Cl. LEXIS 96, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lee-hoffman-v-the-united-states-cc-1964.