Patton Wrecking and Demolition Co., Inc., and Patton Bros., Inc., a Joint Venture v. Tennessee Valley Authority

465 F.2d 1073, 1972 U.S. App. LEXIS 7607
CourtCourt of Appeals for the Fifth Circuit
DecidedSeptember 8, 1972
Docket71-2363
StatusPublished
Cited by8 cases

This text of 465 F.2d 1073 (Patton Wrecking and Demolition Co., Inc., and Patton Bros., Inc., a Joint Venture v. Tennessee Valley Authority) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Patton Wrecking and Demolition Co., Inc., and Patton Bros., Inc., a Joint Venture v. Tennessee Valley Authority, 465 F.2d 1073, 1972 U.S. App. LEXIS 7607 (5th Cir. 1972).

Opinion

INGRAHAM, Circuit Judge:

The issue on this interlocutory appeal is whether a government contractor’s suit for a declaratory judgment of the government’s asserted anticipatory breach of contract was barred by virtue of the contractor’s failure to exhaust the contractually established disputes procedure.

The contract, let after competitive bidding and inspection, was for the resurfacing of one of the Tennessee Valley Authority’s dams. The bid invitation was based upon 2700 square feet of chipping and cleaning eroded concrete surfaces and 2700 cubic feet of drilling and setting steel anchors and placing concrete aggregate and intrusion grout. The unit price provided in the contract for each kind of work brought the total estimated contract amount to $197,100. While the contract allowed for upward adjustments of the cost of additional units of work, it was silent on decreases in quantities.

Appellee Patton Wrecking, the successful bidder, undertook and completed a substantial portion of the available work when it discovered that the total amount of work was far less than that specified (approximately 49% of the bid invitation quantity). Patton halted further performance and sought a declaratory judgment that the government’s projected failure to supply adequate work constituted an anticipatory breach of contract freeing Patton from further performance on its part and entitling it to damages on the theory of quantum meruit. Tennessee Valley Authority an *1075 swered and asserted Patton’s failure to submit the dispute to the contracting officer under the contract’s dispute clause. 1

The district court in an opinion reported as Patton Wrecking and Demolition Co., Inc. v. TVA, 324 F.Supp. 143 (N.D., Miss.1971) sustained Patton’s complaint against TVA’s motion to dismiss and motion for summary judgment. The district court certified TVA’s interlocutory appeal and a panel of this court accepted that appeal. 28 U.S.C. § 1292(b). We reverse and remand.

The district court, after studiously tracing the development of the “standard” dispute clause, 2 found the dispute clause here at issue [for clarity hereafter called “amended” or all disputes clause] to be ambiguous in the scope of the jurisdiction that the parties had contractually conferred upon the contracting officer. The court, therefore, construed the amended dispute clause *1076 against its proponent TVA and pro tan-to held that the dispute provision was inapplicable when the claim for anticipatory relief was not redressable under some other specific contract article. United States v. Utah Construction & Mining Co., 384 U.S. 394, 86 S.Ct. 1545, 16 L.Ed.2d 642 (1966).

The presence of a “standard” dispute clause in government contracts has a long history. See annotation, Government Contracts — “Dispute” Clause, 2 A.L.R.Fed. 691. In Edward R. Marden Corporation v. United States, 442 F.2d 364 (Ct.Cl., 1971), the court said:

“It is a familiar principle in the law of Government contracts that, to the extent complete relief is available under a specific provision of the contract, a controversy is regarded as being within the standard Disputes clause, i. e., as arising ‘under the contract.’ Such a controversy is susceptible of initial administrative resolution under the Disputes clause, and the administrative decision is subject to judicial review under the standards of the Wunderlich Act, 41 U.S.C. §§ 321, 322 (1964). Judicial review is strictly limited to the record established in the administrative proceedings. United States v. Carlo Bianchi & Co., 373 U.S. 709, 714, 83 S.Ct. 1409, 10 L.Ed.2d 652 (1963). A corollary principle is that, to the extent complete relief is not made available under a specific contract provision, a controversy is not subject to administrative determination via the Disputes clause and may be tried de novo in the proper court. Len Co. & Assoc, v. United States, 385 F.2d 438, 442, 181 Ct.Cl. 29, 36 (1967).”

The role and meaning of the “standard” clause has been extensively considered by the Supreme Court in United States v. Utah, supra; United States v. Anthony Grace & Sons, 384 U.S. 424, 86 S.Ct. 1539, 16 L.Ed.2d 662 (1966) and Crown Coat Front Co. v. United States, 386 U.S. 503, 87 S.Ct. 1177, 18 L.Ed.2d 256 (1966). In Utah the Supreme Court distinguished between claims “arising under” the contract [contract claims] for which some other contractual article provided avenues for redress and breach of contract claims. In holding administrative remedies available only for contract claims, the Court said:

“Thus the settled construction of the disputes clause excludes breach of contract claims from its coverage, whether for purposes of granting relief or for purposes of making binding findings of fact that would be reviewable under Wunderlich Act standards rather than de novo. This is not to say that the Government does not have a powerful argument for construing the disputes clause to afford administrative relief for a wider spectrum of disputes arising between the contracting parties. It can be argued, as the Government persuasively does, that the same considerations which initially led to providing an administrative remedy in those situations covered by such clauses as Articles 3, 4 and 9 of the contract also support the broader reading of the disputes clause permitting and requiring administrative fact finding with respect to all disputes arising between the contracting parties. But the coverage of the disputes clause is a matter susceptible of contractual determination, United States v. Moorman, 338 U.S. 457, 70 S.Ct. 288, 94 L.Ed. 256, subject to the limitations on finality imposed by the Wunderlich Act, and one would have expected modification of the disputes clause to encompass breach of contract disputes if the restrictive interpretation of Article 15 was thought unduly to hinder government contracting. In fact the contracting departments have not rejected the narrower judicial reading of the disputes clause nor attempted any wholesale revision of its language to cover all factual disputes. Instead they have acted to create alternative administrative remedies for some breach of contract claims and to disestablish others by fashioning additional specific adjustment provisions contemplating relief under the con *1077

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
465 F.2d 1073, 1972 U.S. App. LEXIS 7607, Counsel Stack Legal Research, https://law.counselstack.com/opinion/patton-wrecking-and-demolition-co-inc-and-patton-bros-inc-a-joint-ca5-1972.