Patton Wrecking and Demolition Co., Inc., and Patton Bros., Inc., a Joint Venture v. Tennessee Valley Authority

465 F.2d 1073, 1972 U.S. App. LEXIS 7607
Court of Appeals for the Fifth Circuit·Decided September 8, 1972·No. 71-2363·Published·Cited by 8 cases

Opinion

INGRAHAM, Circuit Judge:

The issue on this interlocutory appeal is whether a government contractor’s suit for a declaratory judgment of the government’s asserted anticipatory breach of contract was barred by virtue of the contractor’s failure to exhaust the contractually established disputes procedure.

The contract, let after competitive bidding and inspection, was for the resurfacing of one of the Tennessee Valley Authority’s dams. The bid invitation was based upon 2700 square feet of chipping and cleaning eroded concrete surfaces and 2700 cubic feet of drilling and setting steel anchors and placing concrete aggregate and intrusion grout. The unit price provided in the contract for each kind of work brought the total estimated contract amount to $197,100. While the contract allowed for upward adjustments of the cost of additional units of work, it was silent on decreases in quantities.

Appellee Patton Wrecking, the successful bidder, undertook and completed a substantial portion of the available work when it discovered that the total amount of work was far less than that specified (approximately 49% of the bid invitation quantity). Patton halted further performance and sought a declaratory judgment that the government’s projected failure to supply adequate work constituted an anticipatory breach of contract freeing Patton from further performance on its part and entitling it to damages on the theory of quantum meruit. Tennessee Valley Authority an *1075 swered and asserted Patton’s failure to submit the dispute to the contracting officer under the contract’s dispute clause. 1

The district court in an opinion reported as Patton Wrecking and Demolition Co., Inc. v. TVA, 324 F.Supp. 143 (N.D., Miss.1971) sustained Patton’s complaint against TVA’s motion to dismiss and motion for summary judgment. The district court certified TVA’s interlocutory appeal and a panel of this court accepted that appeal. 28 U.S.C. § 1292(b). We reverse and remand.

The district court, after studiously tracing the development of the “standard” dispute clause, 2 found the dispute clause here at issue [for clarity hereafter called “amended” or all disputes clause] to be ambiguous in the scope of the jurisdiction that the parties had contractually conferred upon the contracting officer. The court, therefore, construed the amended dispute clause *1076 against its proponent TVA and pro tan-to held that the dispute provision was inapplicable when the claim for anticipatory relief was not redressable under some other specific contract article. United States v. Utah Construction & Mining Co., 384 U.S. 394, 86 S.Ct. 1545, 16 L.Ed.2d 642 (1966).

The presence of a “standard” dispute clause in government contracts has a long history. See annotation, Government Contracts — “Dispute” Clause, 2 A.L.R.Fed. 691. In Edward R. Marden Corporation v. United States, 442 F.2d 364 (Ct.Cl., 1971), the court said:

“It is a familiar principle in the law of Government contracts that, to the extent complete relief is available under a specific provision of the contract, a controversy is regarded as being within the standard Disputes clause, i. e., as arising ‘under the contract.’ Such a controversy is susceptible of initial administrative resolution under the Disputes clause, and the administrative decision is subject to judicial review under the standards of the Wunderlich Act, 41 U.S.C. §§ 321, 322 (1964). Judicial review is strictly limited to the record established in the administrative proceedings. United States v. Carlo Bianchi & Co., 373 U.S. 709, 714, 83 S.Ct. 1409, 10 L.Ed.2d 652 (1963). A corollary principle is that, to the extent complete relief is not made available under a specific contract provision, a controversy is not subject to administrative determination via the Disputes clause and may be tried de novo in the proper court. Len Co. & Assoc, v. United States, 385 F.2d 438, 442, 181 Ct.Cl. 29, 36 (1967).”

The role and meaning of the “standard” clause has been extensively considered by the Supreme Court in United States v. Utah, supra; United States v. Anthony Grace & Sons, 384 U.S. 424, 86 S.Ct. 1539, 16 L.Ed.2d 662 (1966) and Crown Coat Front Co. v. United States, 386 U.S. 503, 87 S.Ct. 1177, 18 L.Ed.2d 256 (1966). In Utah the Supreme Court distinguished between claims “arising under” the contract [contract claims] for which some other contractual article provided avenues for redress and breach of contract claims. In holding administrative remedies available only for contract claims, the Court said:

Free access — add to your briefcase to read the full text and ask questions with AI

Patton Wrecking and Demolition Co., Inc., and Patton Bros., Inc., a Joint Venture v. Tennessee Valley Authority, 465 F.2d 1073, 1972 U.S. App. LEXIS 7607 (5th Cir. 1972).

465 F.2d 1073 (Patton Wrecking and Demolition Co., Inc., and Patton Bros., Inc., a Joint Venture v. Tennessee Valley Authority) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related