Brown & Root Development, Inc. v. Tennessee Valley Authority

681 F.2d 1313, 30 Cont. Cas. Fed. 70,180, 1982 U.S. App. LEXIS 16916
CourtCourt of Appeals for the Eleventh Circuit
DecidedAugust 2, 1982
Docket81-7390
StatusPublished
Cited by6 cases

This text of 681 F.2d 1313 (Brown & Root Development, Inc. v. Tennessee Valley Authority) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brown & Root Development, Inc. v. Tennessee Valley Authority, 681 F.2d 1313, 30 Cont. Cas. Fed. 70,180, 1982 U.S. App. LEXIS 16916 (11th Cir. 1982).

Opinion

KRAVITCH, Circuit Judge:

The Tennessee Valley Authority [TVA] appeals from an order of the district court assuming jurisdiction under the Contract Disputes Act of 1978, 41 U.S.C. §§ 601 et seq., of this contract dispute between TVA and appellee Brown & Root Development, Inc. [Brown & Root]. At issue is the validity of a TVA regulation requiring contractors who have the option of choosing to resolve disputes either under the “disputes” clause of their contracts or under the new Disputes Act to inform the TVA of that choice in writing at the initial submission of a claim. For the reasons stated below, we reverse the trial court.

I.

In 1978 Congress reformed the entire procedure for settlement of contract disputes between private contractors and agencies of the federal government by passing the Contract Disputes Act of 1978, Pub.L. No. 95-563, 41 U.S.C. §§ 601 et seq. Prior to the new Act, a contract dispute was resolved under the “disputes” clause of a contract. The usual disputes clause required a contractor to first submit a claim to the agency’s Contracting Officer in charge of the contract; if the decision was adverse, the contractor could take an administrative appeal 1 , then file for review in federal court. This court review, however, was limited to determining whether the final decision was arbitrary or capricious, in bad faith, or not supported by substantial evidence.

The new Act significantly changed this procedure by permitting a contractor, after receiving the decision of the contracting officer, to choose whether to prosecute an administrative appeal to the agency’s Board of Contract Appeals or to file an action in *1315 federal court 2 for de novo review of the contract claim. The new Act also required claims to be certified, and as a financial incentive to settle claims, made the contractor liable for any misrepresented or fraudulent claims and costs and the government liable for prejudgment interest on valid claims. This was a significant departure from the former disputes clause claim procedure, since many government contracts contained a “no interest” clause and no penalties attached to a contractor’s filing an inflated claim in the hope of a favorable compromise decision.

By its terms the Act automatically applies to any contract entered into 120 days after the date of enactment. 3 Section 16 of the Act, however, permits contractors who had contracts entered into prior to the effective date to elect to proceed under the Act for any claim pending before a contracting officer at the effective date or initiated thereafter. The Act did not specify when or how this election was to be made, but in regulations passed to implement the Act, the TVA required that a contractor wishing to proceed under the new law must inform the TVA of that choice in writing. For contractors with claims pending on the effective date, the regulations required that a contractor' give this written notice to the TVA within 30 days of the contractor’s receipt of the contracting officer’s decision. 18 C.F.R. § 1308.4(b). For claims initiated after the effective date, the contractor had to include the notice in the document first requesting a decision by the contracting officer. Id.

Brown & Root submitted a claim on a pre-Act contract to the TVA on August 16, 1979, approximately five and one-half months after the Act’s effective date and two and one-half months after publication of TVA’s implementing regulations. The claim did not contain the election notice required by TVA regulations. Nevertheless, after the contracting officer issued an unfavorable decision on its claim, Brown & Root instituted an action for de novo review in federal court as permitted by the Act and moved for a protective order prohibiting TVA from processing Brown & Root’s claim under the disputes clause of the contract. 4 The court, holding TVA’s election regulation invalid, assumed jurisdiction of Brown & Root’s claim under the Act and entered the requested order. TVA then requested certification for an interlocutory appeal under 28 U.S.C. § 1292(a)(1). The district court granted certification which this court accepted.

II.

In Patton Wrecking & Demolition Co. v. TVA, 465 F.2d 1073 (5th Cir. 1972), the former Fifth Circuit 5 held that a district court may not entertain an action on a contract dispute between a private contractor and a government agency until the contractor has exhausted the administrative remedies available under the contract’s disputes clause. Thus unless the Disputes Act, which specifically provides for actions in federal court without administrative exhaustion, applies to Brown & Root’s claim, the district court improperly assumed jurisdiction in this ease. The TVA asserts that *1316 the Act does not apply to Brown & Root’s claim because the contractor waived his right to proceed under the Act by failing to include the written election notice when it submitted its claim to the contracting officer in accordance with TVA regulations. Brown & Root contends that the election regulation is invalid because it is arbitrary, unreasonable, and contrary to both the purpose and language of the Act. 6

We disagree with Brown & Root’s contentions. Few principles of law are as well-settled as the proposition that regulations of a government agency must be upheld if in accord with law and not unreasonable. 5 U.S.C. § 706 (court may set aside agency action only if “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.”); National Muffler Dealers Ass’n v. United States, 440 U.S. 472, 476, 99 S.Ct. 1304, 1306, 59 L.Ed.2d 519 (1979) (interpretive rules); Vermont Yankee Nuclear Power Corp. v. Natural Resources Defense Council, 435 U.S. 519, 543-44, 98 S.Ct. 1197, 1211, 55 L.Ed.2d 460 (1978) (procedural rules); American Hospital Management Corp. v. Harris, 638 F.2d 1208, 1212 (9th Cir. 1981); Randolph-Sheppard Vendors of America, Inc. v. Harris,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coca-Cola Co. v. Commissioner
106 T.C. No. 1 (U.S. Tax Court, 1996)
State Department of Revenue v. Jones Manufacturing Co.
589 So. 2d 206 (Court of Civil Appeals of Alabama, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
681 F.2d 1313, 30 Cont. Cas. Fed. 70,180, 1982 U.S. App. LEXIS 16916, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brown-root-development-inc-v-tennessee-valley-authority-ca11-1982.