Bethlehem Steel Corporation, and Bethlehem Steel Company v. Grace Line, Inc.

416 F.2d 1096
CourtCourt of Appeals for the D.C. Circuit
DecidedApril 24, 1969
Docket21050_1
StatusPublished
Cited by29 cases

This text of 416 F.2d 1096 (Bethlehem Steel Corporation, and Bethlehem Steel Company v. Grace Line, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bethlehem Steel Corporation, and Bethlehem Steel Company v. Grace Line, Inc., 416 F.2d 1096 (D.C. Cir. 1969).

Opinion

SPOTTSWOOD W. ROBINSON, III, Circuit Judge:

Bethlehem Steel Company, an appellant, 1 entered into substantially identical contracts in which it agreed to build four ships for Grace Line, Inc., the appellee. The United States, 2 through the Federal Maritime Board, made this a tripartite venture by awarding Grace a construction-differential subsidy. 3 The contracts required Bethlehem to construct the vessels in accordance with plans and specifications which, among many other things, designated the cubic capacities for each ship’s refrigerated holds (reefers) for banana cargoes. The contracts also fixed staggered delivery dates which, however, were extendible to absorb delays beyond Bethlehem’s control, and provided for liquidated damages for unexcused tardiness. The contracts further provided for predelivery inspections and trials, and *1098 for a guaranty period and a final guarantee survey after delivery. 4 Additionally, a “disputes clause” in each contract required “[a]ny dispute arising under this contract” which the parties did not settle to be submitted to the Maritime Administration for' resolution. 5

During the course of and upon completion of performance, Grace questioned Bethlehem’s compliance with certain of its contractual obligations. The initial disagreement arose from delays in deliveries of each of the four ships. Bethlehem asked the Maritime Administration to extend the contract delivery dates for the first three vessels on the ground that it had encountered obstacles beyond its control, and Grace opposed the requested extension. The questions in this regard remained pending before the Maritime Administration when the parties’ difficulties reached court. 6

As each completed ship was handed over to Grace, and again six months thereafter, Grace compiled and presented to Bethlehem and the Maritime Administration lists of alleged defects in material and workmanship. The lists included faulty sea valves and related equipment in the salt water system of each vessel, which Bethlehem thereafter undertook to rectify. Upon each transfer, Grace also noted “an open question” with respect to the cubic capacities of the banana reefers. After the final guarantee surveys of the delivered ships, the Maritime Administration’s Survey Board, in each instance, disposed of Grace’s statement of “open question” with the comment that it “does not consider this above statement to be a deficiency in workmanship or material as defined by Article 14 [the guaranty clause] of the subject contract.” 7 Grace subsequently informed Bethlehem *1099 that it had verified substantial space shortages in the banana holds in each vessel, from which sizeable losses of revenue to Grace were anticipated.

Grace later brought an action against Bethlehem 8 in the District Court seeking damages for breach of contract resulting from the alleged banana reefer deficiencies, late deliveries and defective sea valves. 9 Invoking the disputes clause, 10 Bethlehem then requested the Maritime Administration to add to the pending contest over the belated deliveries the claims respecting the banana reefers and the sea valves. Grace, on the other hand, resisted administrative consideration of these problems insisting that the disputes clause was limited in operation to disputes “arising under” the contracts, and thus to those deferable to adjustment procedures afforded by the contracts, and that it did not apply to the breach of contract bids for damages.

Bethlehem thereafter filed a motion in the District Court to dismiss the counts incorporating the banana reefer and sea valve claims and three of the counts based on overdue deliveries, 11 without prejudice to their litigation after the completion of administrative proceedings thereon. As grounds for the motion, Bethlehem urged that the court lacked subject matter jurisdiction and that Grace had failed to exhaust the administrative remedies provided by the disputes clause. In opposition, Grace contended that the banana reefer issue was not subject to the disputes clause procedure. Grace added that it would not object to administrative consideration of the late delivery and sea valve questions, and urged that the suit as to them should be stayed, rather than dismissed, pending the outcome of such proceedings. 12 Bethlehem then modified its motion so as to request a stay, instead of a dismissal, of all three controversies pending their administrative resolution.

The District Court accepted the motion as an application for a stay. With Grace’s acquiescence, it stayed the action as to the delayed delivery and sea valve counts, but denied a stay with respect to the banana reefer controversy. The court held that “as a matter of law” Grace’s claims of undersized banana reefers “are not subject to the ‘disputes clause’ of the contracts in suit or to administrative proceedings thereunder.” This appeal by Bethlehem contests the validity of that ruling, and presents for our decision the question whether the disputes clause encompasses Grace’s demand for damages on account of the asserted deficiencies in the banana reefers. 13

*1100 I

In United States v. Utah Construction and Mining Company, 14 the Supreme Court had occasion to delineate the scope of the fact-disputes clause constituting Article 15 of the standard government-wide construction contract. That clause requires “all disputes concerning questions of fact arising under this contract” to be submitted to the government’s contracting officer, and provides that the officer’s decision, subject to a departmental appeal, “shall be final and conclusive upon the parties thereo.” 15 In Utah Construction, a contractor who, by the standard contract, had undertaken the construction of a facility for the Atomic Energy Commission, subjected several demands to the administrative proceedings contemplated by Article 15. After adverse determinations, the contractor framed a breach of contract action in the Court of Claims against the Government predicated upon those demands. The Court of Claims construed Article 15 as confined to “disputes concerning questions of fact arising under this contract,” meaning “a dispute over the rights of the parties given by the contract,” and not “a dispute over a violation of the contract.” 16 In other cases, to which the Supreme Court in Utah Construction referred, 17

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Norment Security Group, Inc. v. Travelers Casualty & Insurance
505 F. Supp. 2d 97 (District of Columbia, 2007)
District of Columbia v. Savoy Construction Co.
515 A.2d 698 (District of Columbia Court of Appeals, 1986)
Gary Aircraft Corp. v. United States
698 F.2d 775 (Fifth Circuit, 1983)
United States v. Medico Industries, Inc.
685 F.2d 230 (Seventh Circuit, 1982)
Carlisle Tire & Rubber Co. v. United States
517 F. Supp. 704 (Court of International Trade, 1981)
United States v. H. H. Reisman
611 F.2d 325 (Ninth Circuit, 1980)
Kyle Engineering Co. v. Kleppe
600 F.2d 226 (Ninth Circuit, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
416 F.2d 1096, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bethlehem-steel-corporation-and-bethlehem-steel-company-v-grace-line-cadc-1969.