United States v. H. H. Reisman

611 F.2d 325, 27 Cont. Cas. Fed. 80,058, 1980 U.S. App. LEXIS 21592
CourtCourt of Appeals for the Ninth Circuit
DecidedJanuary 7, 1980
Docket77-2335
StatusPublished
Cited by4 cases

This text of 611 F.2d 325 (United States v. H. H. Reisman) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. H. H. Reisman, 611 F.2d 325, 27 Cont. Cas. Fed. 80,058, 1980 U.S. App. LEXIS 21592 (9th Cir. 1980).

Opinion

SNEED, Circuit Judge:

The United States filed suit in district court seeking actual damages for defendant Reisman’s breach of a contract to purchase chromite ore, following a Board of Contract Appeals ruling that the liquidated damages provision was unenforceable. The District Court for the Central District of California dismissed the complaint and the United States appealed. We reverse and remand.

Jurisdiction is based on 28 U.S.C. § 1291.

I.

Factual Background.

This is a government contracts case in which the central issue is the availability to the government of a remedy in court for the total breach of the contract by the other party thereto.

The contract came into existence on August 14, 1970 when the defendant Reisman agreed to purchase from the General Services Administration (GSA) 803,527 tons of metallurgical grade chromite ore. The contract required that Reisman furnish to GSA an irrevocable sight commercial letter of credit for the full amount of the purchase price by August 24, 1970. Reisman failed to meet this deadline and obtained time extensions from the contracting officer on August 24, 1970 and August 27, 1970. The extension of August 27 expired on September 2, 1970. Again Reisman failed to furnish the required letter of credit and the *327 contracting officer mailed to Reisman a notice of default which stated that unless the default was cured by September 18, 1970 Reisman would lose his right to purchase the chromite and the government would exercise its rights to assess liquidated damages pursuant to General Condition 9 of the contract. 1

Once more Reisman failed to furnish the letter of credit and, in exchange for Reisman’s offer to increase the purchase price by $50,000, the government agreed to an extension of approximately 10 working days. On October 2, 1970, Reisman made his fourth request for an extension of time within which to supply the letter of credit. This was refused and the contracting officer’s notice of September 2, 1970 became effective.

Thereafter in a timely manner Reisman exercised his request to appeal under the standard Disputes provisions of the contract. 2

More than a year later, December 15, 1971, the GSA Board of Contract Appeals, after holding that it had jurisdiction to determine the enforceability of the liquidated damages provision of the contract, held that Reisman’s failure to furnish the letter of credit constituted a default permitting the invocation of the liquidated damage provision and that under the facts of the case that provision was an unenforceable penalty.

All the while the chromite ore remained in the hands of the GSA. Finally, on August 18, 1974, GSA sold the ore to another for $353,026.10 less than Reisman had *328 agreed to pay. The government, acting on the belief that the Disputes Clause does not afford a means by which this difference could be recovered, merely presented its claim to Reisman for this sum through certificates of indebtedness issued by the General Accounting Officer under 31 U.S.C. §§ 71, 93. Reisman refused to pay and this suit was commenced by the United States against Reisman on July 29, 1976 in which it sought recovery of this difference plus 6% interest from June 18, 1971 to August 19, 1974.

Reisman’s defense in the district court was that the Disputes Clause is applicable to claims such as the government presented and that as a consequence the government’s complaint should be dismissed. The district court agreed and dismissed the complaint “for failure to exhaust administrative remedies.” We believe this constituted error.

II.

Applicability of Disputes Clause.

The fundamental principle that governs the disposition of this case was stated in United States v. Utah Construction and Mining Co., 384 U.S. 394, 404, 86 S.Ct. 1545, 1551, 16 L.Ed.2d 642 (1966). It is that “[t]he power of the administrative tribunal to make final and conclusive findings on factual issues rests on the contract . .” That is, whether the government is entitled to bring this suit depends on the proper interpretation of the contract. If the contract, properly interpreted, requires the government to resolve its damage claim under the Disputes Clause, then the district court’s dismissal was proper. However, if no such requirement exists, then we must reverse.

Only recently did we recognize this principle when in Kyle Engineering Co. v. Kleppe, 600 F.2d 226, 230-31 (9th Cir. 1979) we said:

“It is important to note, however, that not all contractual disputes are subject to the exhaustion requirement; exhaustion is required only for disputes ‘arising under the contract.’ Utah Construction Co., 384 U.S. at 407, 86 S.Ct. 1545. The test to be employed in distinguishing claims within the disputes clause procedure from those outside that procedure ‘is whether the controversy is fully redressable under a provision of the contract other than the disputes clause itself.’ Bethlehem Steel Corp. v. Grace Line, Inc., 135 U.S.App. D.C. 81, 86, 416 F.2d 1096, 1101 (1969). In other words, a fact-dispute ‘arises under the contract’ only when the disputed fact is capable of complete resolution by a procedure specified in the contract:
‘In consequence claims which are adjustable under contractual provisions must be submitted for the administrative determinations prescribed by the contract, while claims for breach of contract — those not adjustable in that fashion — may be litigated in a court of competent jurisdiction without previous resort to that procedure. Id.’ ”

Nothing in S & E Contractors, Inc. v. United States, 406 U.S. 1, 92 S.Ct. 1411, 31 L.Ed.2d 658 (1972) is to the contrary. That case merely held “that absent fraud or bad faith the federal agency’s settlement under the disputes clause is binding on the Government; that there is not another tier of administrative review . . . .” Id. at 4, 92 S.Ct. at 1414. This holding presupposes that the contract made the Disputes Clause procedures applicable; it merely held that another tier of administrative review, such as the United States was insisting upon in the case, did not exist.

Turning to the contract between Reisman and the United States, the strength of Reisman’s contentions is found in General Condition 9. Supra n. 1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Medico Industries, Inc.
685 F.2d 230 (Seventh Circuit, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
611 F.2d 325, 27 Cont. Cas. Fed. 80,058, 1980 U.S. App. LEXIS 21592, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-h-h-reisman-ca9-1980.