Seal & Company, Incorporated v. A.S. McGaughan Company, Incorporated, and Third Party v. John J. Kirlin Company, Third Party

907 F.2d 450, 1990 U.S. App. LEXIS 11022, 1990 WL 89744
CourtCourt of Appeals for the Third Circuit
DecidedJuly 2, 1990
Docket89-1441
StatusPublished
Cited by7 cases

This text of 907 F.2d 450 (Seal & Company, Incorporated v. A.S. McGaughan Company, Incorporated, and Third Party v. John J. Kirlin Company, Third Party) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seal & Company, Incorporated v. A.S. McGaughan Company, Incorporated, and Third Party v. John J. Kirlin Company, Third Party, 907 F.2d 450, 1990 U.S. App. LEXIS 11022, 1990 WL 89744 (3d Cir. 1990).

Opinion

BUTZNER, Senior Circuit Judge:

The principal issue raised in this appeal is whether the district court should have stayed this action pending the outcome of contractual dispute resolution proceedings. The district court denied a stay and awarded damages to a subcontractor against the general contractor engaged in work for the Washington Metropolitan Area Transit Authority (WMATA). We vacate the judgment and remand the case for the imposition of a stay and further proceedings consistent with this opinion.

A.S. McGaughan Co., Inc., is a general contractor which contracted with WMATA to perform the “finish work” on the Forest Glen Metro Station. Subsequently, McGau-ghan entered into subcontracts with Seal & Company, Inc., and John J. Kirlin Company to perform, respectively, the work described in the electrical specifications and mechanical specifications of the Contract Documents. The dispute in this case arose when McGaughan required Seal to perform work which Seal believed was outside the scope of its subcontract. Seal demanded additional money for the work and McGau-ghan refused to pay.

After Seal sued McGaughan for breach of contract, McGaughan moved to stay the proceedings, claiming the subcontract required Seal to follow the dispute resolution procedures outlined in the prime contract before seeking relief in court. The district court denied McGaughan’s motion. McGaughan then filed a third party complaint against Kirlin, seeking indemnity on the basis that either Seal or Kirlin had been obligated to do the work.

Following a two day bench trial, the court dismissed McGaughan’s third party complaint against Kirlin and ruled in favor of Seal on its complaint for damages. On appeal, McGaughan contends that the trial court erred in denying the motion to stay the proceedings and in finding that neither Seal nor Kirlin was responsible for the work in question.

I

This dispute is about payment for fire line bonding. The fire line is a water pipe *452 which runs through the tunnels of the Metro and is part of the fire suppression system. It is made of metal pipe which is four inches in diameter and ten or twenty feet in length. The sections of pipe are joined by a mechanical coupling device. The fire line must be grounded to discharge any stray electrical current that comes in contact with it. Unfortunately, the mechanical couplings have gaskets in them which interrupt the flow of electricity along the pipe and interfere with grounding. To restore the flow of electricity and allow for proper grounding, the sections of pipe can be electrically connected (bonded) across the joints by attaching a cable (bonding strap) to the pipe on each side of the joint. This procedure is called fire line bonding.

The dispute began when Kirlin received a letter from a contractor specializing in bonding which suggested that the bonding normally required by WMATA was mistakenly deleted from the contract specifications by the Special Provisions for section 1526 of the Contract Documents. The contractor offered to bid on the bonding work and suggested that Kirlin ask WMATA to clarify the matter. The contractor sent copies to McGaughan and Seal.

McGaughan forwarded the letter, along with a Request for Information, to WMA-TA. WMATA replied that the bonding work was required by the Contract Documents and referred to both section 1605 of the electrical specifications and section 1526 of the mechanical specifications. Consequently, WMATA maintained that the bonding work should be done at no additional cost. McGaughan forwarded WMA-TA’s decision to Seal and Kirlin and eventually asked each of them to do the bonding. Kirlin refused. Seal agreed to do the work under protest and then filed its breach of contract suit after McGaughan refused to pay Seal additional money.

The underlying question in this case is who will pay for the fire line bonding which was performed under protest by Seal. The answer depends on whether the prime contract requires fire line bonding and, if so, whether it should have been performed by Kirlin pursuant to section 1526 of the mechanical specifications or by Seal pursuant to section 1605 of the electrical specifications. The threshold question, however, is whether the trial court should have stayed Seal’s breach of contract suit pending the results of the dispute resolution process outlined in the prime contract. The answer depends on how the dispute resolution provisions of the prime contract and subcontracts are interpreted.

II

Section 3 of the prime contract between WMATA and McGaughan, entitled “Changes,” allows WMATA’s Contracting Officer to “make any change in the work within the general scope of the Contract.” Such “change orders” are compensable if they increase the contractor’s costs. Disputes over whether certain work constitutes a change order or whether it is within the original contract are settled pursuant to section 6, “Disputes.” Section 6 provides that the contractor must submit its claims to the Contracting Officer who, upon request, issues a written Final Decision. That decision is reviewable by WMA-TA’s Board of Directors or their authorized representative, which in this case is the Army Corps of Engineers Board of Contract Appeals. The board’s decision, if adopted by WMATA’s Board of Directors, is final and binding on the parties unless a court finds the decision fraudulent or not supported by substantial evidence.

In effect, the changes and disputes provisions transform potential breach of contract claims into claims under the contract. By agreeing to these provisions, McGau-ghan has agreed to rely on administrative procedures to resolve disputes over work within the general scope of the contract, subject to limited judicial review. The general provisions of Seal’s and Kirlin’s subcontracts are identical. Their subcontracts include the following provision regarding change orders and dispute settlement:

7. Changes
a. Contractor may ... make changes in the work covered by this Subcontract. ... Subcontractor shall perform the work as changed without delay.
*453 b. Subcontractor shall submit in writing any claims for adjustment in price, ... for changes directed by Owner or as a result of deficiencies or discrepancies in the Contract Documents, to Contractor in time to allow Contractor to comply with the applicable provisions of the Contract Documents. Contractor shall process said claims in the manner provided by and according to the provisions of the Contract Documents. Subcontractor adjustments shall be made only to the extent that Contractor is entitled to relief from or must grant relief to Owner....
c. For changes ordered by Contractor independent of Owner or Contract Documents, Subcontractor shall be entitled to equitable adjustment in the Subcontract price.
9. Settlement of Disputes
a. In case of any dispute between Contractor and Subcontractor, due to any action of Owner or involving the Contract Documents, Subcontractor agrees to be bound to Contractor to the same extent that Contractor is bound to Owner, by the terms of the Contract Documents, and by any and all preliminary and final decisions or determinations made thereunder....

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States ex rel. Kitchens to Go v. John C. Grimberg Co.
283 F. Supp. 3d 476 (E.D. Virginia, 2017)
Skanska USA Building, Inc. v. Smith Management Construction, Inc.
967 A.2d 827 (Court of Special Appeals of Maryland, 2009)
Norment Security Group, Inc. v. Travelers Casualty & Insurance
505 F. Supp. 2d 97 (District of Columbia, 2007)
Nello L. Teer Co. v. Jones Bros., Inc.
641 S.E.2d 832 (Court of Appeals of North Carolina, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
907 F.2d 450, 1990 U.S. App. LEXIS 11022, 1990 WL 89744, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seal-company-incorporated-v-as-mcgaughan-company-incorporated-and-ca3-1990.