United States Ex Rel. DDC Interiors, Inc. v. Dawson Construction Co.

895 F. Supp. 270, 40 Cont. Cas. Fed. 76,851, 1995 U.S. Dist. LEXIS 10643, 1995 WL 449607
CourtDistrict Court, D. Colorado
DecidedJuly 25, 1995
DocketCiv. A. 94-B-2699
StatusPublished
Cited by7 cases

This text of 895 F. Supp. 270 (United States Ex Rel. DDC Interiors, Inc. v. Dawson Construction Co.) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. DDC Interiors, Inc. v. Dawson Construction Co., 895 F. Supp. 270, 40 Cont. Cas. Fed. 76,851, 1995 U.S. Dist. LEXIS 10643, 1995 WL 449607 (D. Colo. 1995).

Opinion

MEMORANDUM OPINION AND ORDER

BABCOCK, District Judge.

This is a Miller Act case. 40 U.S.C. § 270a. Dawson Construction Co., Inc. (Dawson or prime contractor) and United States Fidelity and Guaranty Company (USF & G) (collectively, defendants) move to stay proceedings. Hearing was held on the motion on July 21, 1995. For the following reasons, I will deny defendants’ motion.

I.

In January, 1992, Dawson contracted with the United States General Services Administration (GSA) for the renovation/conversion of the Byron White United States Courthouse at 1823 Stout Street, Denver, Colorado. Dawson was to be paid over $20 million dollars under the contract. Dawson, as principal and surety, obtained from defendant United States Fidelity and Guarantee Company (USF & G), a $2,500,000 payment bond as required by the Miller Act, 40 U.S.C. § 270b, for the protection of all persons supplying labor and materials. Plaintiff DDC Interiors, Inc. (DDC or subcontractor) is a Colorado corporation which subcontracted with Dawson to furnish labor, materials, and equipment required for framing, drywalling, plastering, painting, wallpaper, and other associated work. The contract specifically excluded “skim coating or resurfacing of existing plaster walls unless shown or specified.” DDC was to be paid $1,585,000 by Dawson, payable as work progressed. During the contract performance, the subcontract amount was increased by approved change orders to over $2,250,000. The last labor was performed by DDC on August 17, 1994.

DDC filed this action under the Miller Act, 40 U.S.C. § 270a and b for the balance due of *272 over $600,000 for alleged approved change orders and extra work. Dawson, the general contractor, moves to stay this action pending completion of its disputes resolution process with GSA. Dawson argues that the stay should issue based on terms of the subcontract. The dispositive issue is whether, and under what circumstances, a government subcontractor can surrender its rights to seek prompt payment under the Miller Act, 40 U.S.C. § 270a and b. I conclude that under the circumstances here, DDC did not clearly and expressly waive its Miller Act rights. Accordingly, I will deny the motion for stay of proceedings.

II.

The predecessor of the Miller Act was the Heard Act, Act of Aug. 13, 1894, ch. 280, 28 Stat. 278. The Heard Act was passed because “many contractors constructing public buildings for the government were insolvent when entering into the contracts or at the completion of the work and because mechanics and materialmen’s liens were not [allowed] on public buildings, persons furnishing labor or material to the contractors [subcontractors] were left without a remedy.” United States v. Daniel, Urbahn, Seelye and Fuller, 357 F.Supp. 853, 857 (N.D.Ill.1973). Before the Heard Act, the practice was for contractors to post a bond for the protection of the United States. Then a statute was passed giving material and labor suppliers (subcontractors) the right to sue on the bond. H.R.Rpt. No. 97, 53d Cong., 1st Sess. 1 (1893). Contractors were obligated to “promptly make payments” to those providing materials and labor (subcontractors). If they did not, the subcontractors could bring suit “in the name of the United States for his or their use and benefit.” Heard Act, 33 Stat. 811-12. However, the Heard Act provided that the subcontractors had to wait six months after completion of all construction before they could sue. On lengthy projects, this was often long after the subcontractors had supplied their labor and material. United States v. Daniel, Urbahn, Seelye and Fuller, 357 F.Supp. at 858-59. The “resultant hardship” on subcontractors was one reason for the repeal of the Heard Act and enactment of the Miller Act. Id. at 859. H.R.Rpt. No. 1263, 74th Cong. 1st Sess. 1 (1935).

The purpose of the Miller Act is “to provide security for those who furnish labor and material in the performance of government contracts. F.D. Rich Co., Inc. v. United States ex rel. Indus. Lumber Co., Inc., 417 U.S. 116, 124, 94 S.Ct. 2157, 2162, 40 L.Ed.2d 703 (1974); Warrior Constructors Inc. v. Harders, Inc., 387 F.2d 727, 729 (5th Cir.1967); Fand erlik-Locke Co., v. United States for Use of Morgan, 285 F.2d 939, 941 (10th Cir.1960), cert. denied, 365 U.S. 860, 81 S.Ct. 826, 5 L.Ed.2d 823 (1961). The Miller Act is “highly remedial in nature,” and its terms should be liberally construed. J.W. Bateson Co., Inc. v. U.S. ex rel. Bd. of Trustees of Nat. Automatic Sprinkler Industry Pension Fund, 434 U.S. 586, 594, 98 S.Ct. 873, 877, 55 L.Ed.2d 50 (1978). The Miller Act is not designed to benefit the prime contractor. Fanderlik-Locke, 285 F.2d 939, 941. Rather, it was enacted for “the especial protection of the subcontractor on a government construction contract.” United States for and on Behalf of Delta Metals, Inc. v. R.M. Wells Co., Inc., 497 F.Supp. 541, 544 (S.D.Ga.1980); see United States for Use of F.E. Robinson Co. of N.C., Inc. v. Alpha-Continental, 273 F.Supp. 758, 774 (E.D.N.C.1967), aff'd, 404 F.2d 343 (4th Cir.1968), cert. denied, 395 U.S. 922, 89 S.Ct. 1774, 23 L.Ed.2d 239 (1969). The risk of nonpayment for goods and services provided for a government project should be borne by the surety — not the laborers or materialmen. United States for Use and Benefit of Mariana v. Piracci Constr. Co., Inc., 405 F.Supp. 904, 905 n. 2 (D.D.C.1975). Thus, the purpose of the payment bond required under the Miller Act is to “shift the ultimate risk of nonpayment from workmen and suppliers to the surety.” American Sur. Co. of New York v. Hinds, 260 F.2d 366, 368 (10th Cir.1958). Under the Miller Act, a subcontractor may sue 90 days after the last day on which it supplied labor or material. 40 U.S.C. § 270b(a).

Right to sue under the Miller Act may be waived by clear and express provisions in the contract between the prime contractor and the subcontractor. United *273 States for Use of B’s Co. v. Cleveland Elec. Co. of S.C.,

Related

Cite This Page — Counsel Stack

Bluebook (online)
895 F. Supp. 270, 40 Cont. Cas. Fed. 76,851, 1995 U.S. Dist. LEXIS 10643, 1995 WL 449607, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-ddc-interiors-inc-v-dawson-construction-co-cod-1995.