Techniquex Specialty Flooring, Inc. v. Philadelphia Idemnity Insurance Company

CourtDistrict Court, M.D. Pennsylvania
DecidedOctober 22, 2024
Docket3:21-cv-00286
StatusUnknown

This text of Techniquex Specialty Flooring, Inc. v. Philadelphia Idemnity Insurance Company (Techniquex Specialty Flooring, Inc. v. Philadelphia Idemnity Insurance Company) is published on Counsel Stack Legal Research, covering District Court, M.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Techniquex Specialty Flooring, Inc. v. Philadelphia Idemnity Insurance Company, (M.D. Pa. 2024).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE MIDDLE DISTRICT OF PENNSYLVANIA THE UNITED STATES OF AMERICA : No. 3:21cv286 by and for the use of TECHNIQUEX : SPECIALTY FLOORING, INC.., : (Judge Munley) Plaintiff :

V. : PHILADELPHIA INDEMNITY : INSURANCE COMPANY, : Defendant :

MEMORANDUM This is an action filed by Plaintiff Techniquex Specialty Flooring, Inc. (“Techniquex”) pursuant to the Miller Act, 40 U.S.C. §§ 3131-34, for breach of a payment bond issued by Defendant Philadelphia Indemnity Insurance Company (‘PIIC”).1 Before the court is a motion for summary judgment filed by the defendant. Having been fully briefed and argued, this motion is ripe for disposition. Background This dispute involves a construction project to renovate the Mission Operation Facility at the Tobyhanna Army Depot in Tobyhanna, Pennsylvania. 2

' The Miller Act requires Techniquex to pursue this matter “in the name of the United States fc the use of the person bringing the action.” 40 U.S.C. § 3133(b)(3)(A). 2 Unless noted otherwise, the court cites to the defendant’s statement of material facts (“SOF” (Doc. 41-22), for facts which the plaintiff admitted in its response to the SOF, (“CSOF”), (Doc.

(Doc. 41-5, Subcont. Agreement, ECF p. 27). To proceed with the renovation of this 210,000 square foot building, the United States Department of the Army executed a prime contract with Benaka, Inc. (“Benaka’) and Benaka served as the prime contractor for the project. (Id.; Doc. 41-22, SOF {| 1). On September 29, 2014, and pursuant to the Miller Act, PIIC issued a payment bond for the project on behalf of Benaka. (Doc. 41-22, SOF ¥[ 2). Among other things, the bond obligated defendant as the surety to pay persons furnishing labor and materials to the project in the event Benaka failed to do so. (Id. ff 3). Thereafter, pursuant to the prime contract, Benaka executed a subcontract with Techniquex. (Id. J] 1). Techniquex and Benaka agreed that the plaintiff would furnish epoxy flooring work for the project as required by the subcontract. (Id.) Work on the project was broken into six (6) phases: Phases A, B, C, D, E(a), and E(b). (Id. 4). Techniquex completed Phases A, B, and C on the project on or before October 15, 2017. (Id. {| 5). Under the subcontract, Techniquex would submit periodic payment applications to Benaka as the project moved forward. (See id. {| 6). Per

46). All facts from the record are construed in a light most favorable to plaintiff as the nonmoving party. See Daniels v. Sch. Dist. of Philadelphia, 776 F.3d 181, 187 (3d Cir. 2015)(citation omitted).

Techniquex, a dispute arose in April 2017, where Benaka reduced an invoice payment by approximately $95,000. (Doc. 45, B. Adelmann Decl. ¥] 3). Nonetheless, work on the floors of the Mission Operation Facility continued. On August 18, 2017, Techniquex submitted Payment Application No. 7 for work on the project. (Doc. 41-22, SOF 9/6). Techniquex also executed a waiver that was attached to Payment Application No. 7. (Doc. 45, B. Adelmann Decl. ¥] 2). PIIC advances that Benaka approved and paid this application subject to waiver and release language that forecloses part of Techniquex’s claim. Techniquex takes the position that Payment Application No. 7 underbilled Benaka for labor and materials supplied in the amount of $241,316, which plaintiff attempted to recoup in later payment applications. (Id. J] 3, 8). Techniquex asserts that it has not waived its claim to this amount. On October 25, 2017, Techniquex submitted Payment Application No. 8 fol work on the project. (Doc. 41-22, SOF J 8). Benaka rejected this application on November 9, 2017. (Id. J] 9). In November 2017, Benaka informed Techniquex that work on the project was temporarily suspended due to delays unrelated to epoxy flooring. (Doc. 45, B. Adelmann Decl. J] 7). Techniquex removed its employees from the project anc did not commence work on Phases D, E(a), and E(b). (Id. 9] 6-7).

Techniquex then filed a bond claim with PIIC on January 4, 2018. (Doc. 41- 22, SOF J 10). PIIC rejected the bond claim. (Id. 11). Techniquex admits that it decided not to pursue this 2018 bond claim or litigation at that time. (Doc. 46, CSOF J 13). Techniquex advances that it operated under an assumption that it would remobilize and complete work later. (Doc. 41-8, Techniquex 30(b)(6) Dep., B. Adelmann 167:1-168:3). The project apparently languished for various reasons. But on June 11, 2020, Benaka contacted Techniquex to resume flooring work. (Doc. 41-22, SOF q 14). On September 10, 2020, after COVID-19 interruptions, Techniquex’s vice president, Caleb Wilhelm, travelled to the Tobyhanna Army Depot to meet with representatives from the depot and Benaka to walk the site, discuss the remaining scope of work, and schedule Techniquex’s remobilization. (Doc. 45, B. Adelmann Decl. 7] 11). During this site visit, Wilhelm discovered dozens of epoxy containers in various sizes, which had been on the job site since 2017. fld. Jf] 12-13; Doc. 44- 23, Pl. Ex. 22, Photographs). At that time, Techniquex took the position that the materials were expired and needed to be removed and replaced as part of resuming work. (Id.) In reporting back to Techniquex in an email, Wilhelm indicated that the job site was “too much of a mess to dig through[.]” (Id., C. Wilhelm Email 09/17/2020). Per Techniquex, over the course of several hours,

Wilhelm manually lifted and carried the epoxy containers and placed them back

on pallets. (Doc. 45, Decl. of B. Adelmann, Decl. J 13). The expired materials and other issues eventually soured the relationship between Techniquex and Benaka. On November 4, 2020, Benaka terminated Techniquex from the project. (Doc. 41-22, SOF ff 16). After it was terminated, Techniquex resubmitted Payment Application No. 8 to Benaka on December 17, 2020 and simultaneously provided PIIC with notice of its second payment bond claim. (Id. | 17). Per Techniquex, the resubmitted payment application and bond claim concerned the amount of $401,756.95, which included: 1) unpaid retainage of approximately $64,048.93; 2) the amount billed in the original Payment Application No. 8 in the amount of $96,391.31, and 3) $241,316.00 in underbilled items from Payment Application No. 7. (Doc. 45, Decl. of B. Adelmann § 9). On February 17, 2021, Techniquex filed this instant action seeking recovery of $401,756.95 from the payment bond issued by PIIC. (Doc. 1, Compl.). After a period of discovery, PIIC filed the instant motion for summary judgment. This matter is ripe for a decision. Jurisdiction Because this case is brought pursuant to the Miller Act, the court has jurisdiction pursuant to 28 U.S.C. § 1331. (“The district courts shall have original

jurisdiction of all civil actions arising under the Constitution, laws, or treaties of the United States.”). The court also has jurisdiction pursuant to the diversity statute, 28 U.S.C. § 1332. Techniquex is a corporation organized under the laws of the State of Arizona with its principal place of business in Arizona. (Doc. 1, Compl. f] 2). PIIC is a corporation organized under the laws of the Commonwealth of Pennsylvania with its principal place of business in Pennsylvania. (Id. □ 4, Doc. 22, Answer, 14). Additionally, the amount in controversy exceeds $75,000.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Lanci v. Metropolitan Insurance
564 A.2d 972 (Supreme Court of Pennsylvania, 1989)
Welsh v. State Employees' Retirement Board
808 A.2d 261 (Commonwealth Court of Pennsylvania, 2002)
Taylor v. Solberg
778 A.2d 664 (Supreme Court of Pennsylvania, 2001)
Sparler v. Fireman's Insurance Co. of Newark
521 A.2d 433 (Supreme Court of Pennsylvania, 1987)
Buttermore v. Aliquippa Hospital
561 A.2d 733 (Supreme Court of Pennsylvania, 1989)
Roth v. Old Guard Insurance
850 A.2d 651 (Superior Court of Pennsylvania, 2004)
United Metro Materials, Inc. v. Pena Blanca Properties, L.L.C.
4 P.3d 1022 (Court of Appeals of Arizona, 2000)
Dorothy Daniels v. Philadelphia School District
776 F.3d 181 (Third Circuit, 2015)
Hart v. Arnold
884 A.2d 316 (Superior Court of Pennsylvania, 2005)
International Milling Co. v. Hachmeister, Inc.
110 A.2d 186 (Supreme Court of Pennsylvania, 1955)
United States v. Zurich American Insurance
99 F. Supp. 3d 543 (E.D. Pennsylvania, 2015)
Camreta v. Greene
179 L. Ed. 2d 1118 (Supreme Court, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Techniquex Specialty Flooring, Inc. v. Philadelphia Idemnity Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/techniquex-specialty-flooring-inc-v-philadelphia-idemnity-insurance-pamd-2024.