Techniquex Specialty Flooring, Inc. v. Philadelphia Idemnity Insurance Company

CourtDistrict Court, M.D. Pennsylvania
DecidedMay 20, 2022
Docket3:21-cv-00286
StatusUnknown

This text of Techniquex Specialty Flooring, Inc. v. Philadelphia Idemnity Insurance Company (Techniquex Specialty Flooring, Inc. v. Philadelphia Idemnity Insurance Company) is published on Counsel Stack Legal Research, covering District Court, M.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Techniquex Specialty Flooring, Inc. v. Philadelphia Idemnity Insurance Company, (M.D. Pa. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE MIDDLE DISTRICT OF PENNSYLVANIA THE UNITED STATES OF AMERICA by and for the use of TECHNIQUEX SPECIALTY FLOORING, INC., Plaintiff, : V. 3:21-CV-00286 (JUDGE MARIANI) PHILADELPHIA INDEMNITY INSURANCE COMPANY, : Defendant. MEMORDANDUM OPINION |. INTRODUCTION Pending before the Court is Defendant Philadelphia Indemnity Company's Motion to Dismiss (Doc. 9). Philadelphia argues that Plaintiff Techniquex Specialty Flooring’s Complaint is untimely because it was filed after the Miller Act’s one-year statute of limitation and Techniquex has not pled facts sufficient to support equitable tolling. (Doc. 9 at 2-4). For the reasons set forth below, the court will deny Philadelphia’s Motion to Dismiss (Doc. 9). ll. FACTUAL ALLEGATIONS Techniquex entered into a subcontract with Benaka, who had a prime contract with the Department of Defense (“DOD”), on or about August 17, 2015, to complete interior and exterior epoxy flooring work at the Mission Operation Facility on Building 1A at the Tobyhanna Army Depot in Tobyhanna Pennsylvania (“the Project”). (Doc. 1 at ff] 9, 10; see also Doc. 1-2). Philadelphia Indemnity issued Payment Bond No. PB12048700012 with

Benaka as the principal and the United States as the obligee, for the labor and materials provided by contractors to the Project. (/d. at J] 26-27). Techniquex was a subcontractor for Benaka and provided labor and materials for the Project, which made Techniquex “a claimant under the Bond and an intended beneficiary of the Bond.” (/d. at 28). “Under the Bond, Philadelphia Indemnity is obligated, as surety for Benaka, to pay Techniquex for all labor and materials that Techniquex provided on the Project for Benaka’s benefit and that Benaka has failed to pay Techniquex.” (/d. at J 29). After Techniquex completed Phase C of the Project, DOD ordered that the Project be “temporarily suspended until further notice” on or about October 11, 2017. (/d. at □□□□ At the time DOD suspended the Project, Techniquex had completed Phases A through C of its work, which constituted approximately 90% of Techniquex’s work on the Project. (Doc. 1 at {J 12, 13). Techniquex still had to perform Phases D, E(a), and E(b) to complete its obligations under the subcontract. (/d. at 12). “At the time of the suspension of the Project, Benaka was withholding portions of the amounts owed to Techniquex for its work on the Project, including retainage withheld for work that Techniquex properly performed in Phases A through C, and which was accepted by Benaka and [DOD].” (/d. at ] 14). “Upon the Project being recommenced more than two years later, Techniquex initiated and responded to multiple communications with Benaka regarding the previously agreed upon Project schedule.” (/d. at 15). On or about October 23, 2020, however, “in complete disregard of these scheduling communications related to

the completion of the Project, Benaka sent a 48-hour ‘Notice to Cure’ letter to Techniquex demanding that Techniquex comply with an unreasonable acceleration to the originally agreed-upon work durations in the Project schedule.” (/d. at ] 16). Techniquex expressed its willingness to complete the Project according to Benaka’s updated scheduling demands “by offering to redirect resources from other projects and perform work during ‘off hours’ such as evenings, weekend, and national holidays.” (Doc. 1 at 17). Techniquex remained ready, willing, and able to complete the Project in accordance with Benaka’s scheduling demands. (/d. at 19). Similarly, “[t]hroughout Techniquex’s performance of work on the Project, including during the hiatus caused by [DOD’s] temporary halt to the Project, Techniques was ready, willing, and able to perform its work but was negatively impacted, frustrated, and delayed by Benaka’s mismanagement of the Project,” which included “Benaka’s failure to properly coordinate and communicate with Techniquex regarding the remaining work to be completed.” (/d. at J 18). In its Notice of Termination for Cause letter, dated November 4, 2020, “Benaka wrongfully terminated Techniquex without cause.” (/d. at ] 20). According to Article 15 of the Subcontract, “Benaka’s wrongful termination of Techniquex is deemed a ‘cancellation for convenience’ and Techniquex is entitled to be paid the reasonable value of all work in place.” (/d. at ] 21). To date, however, Techniquex has only been paid $480,049.08, but the value of its completed work is $881,806.03, resulting in an unpaid balance of $401,756.95. (Doc. 1 at ] 22). “Techniquex submitted Application for Payment No. 8 on or

about December 17, 2020, seeking payment of all amounts remaining owed under the Subcontract but Benaka failed and refused to make payment of the amounts owned to Techniquex.” (/d. at 23). Ill. STANDARD OF REVIEW A complaint must be dismissed under Federal Rule Civil Procedure 12(b)(6), if it does not allege “enough facts to state a claim to relief that is plausible on its face.” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007). The plaintiff must aver “factual content that allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged.” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009). “While a complaint attacked by a Rule 12(b)(6) motion to dismiss does not need detailed factual allegations, a plaintiff's obligation to provide the grounds of his entitlement to relief requires more than labels and conclusions, and a formulaic recitation of the elements of a cause of action will not do.” Twombly, 550 U.S. at 555 (internal citations, alterations, and quotations marks omitted). In other words, “[fjactual allegations must be enough to raise a right to relief above the speculative level.” Covington v. Int'l Ass'n of Approved Basketball Offs., 710 F.3d 114, 118 (3d Cir. 2013) (internal citations and quotation marks omitted). A court “take[s] as true all the factual allegations in the Complaint and the reasonable inferences that can be drawn from those facts, but. . . disregard[s] legal conclusions and threadbare recitals of the elements of a cause of action, supported by mere conclusory statements.” Ethypharm S.A. France v. Abbott Labs., 707 F.3d 223, 231 n.14

(3d Cir. 2013) (internal citation, alteration, and quotation marks omitted). Thus, “the presumption of truth attaches only to those allegations for which there is sufficient ‘factual matter’ to render them ‘plausible on [their] face.” Schuchardt v. President of the U.S., 839 F.3d 336, 347 (3d Cir. 2016) (alteration in original) (quoting Iqbal, 556 U.S. at 679). “Conclusory assertions of fact and legal conclusions are not entitled to the same presumption.” /d. “Although the plausibility standard ‘does not impose a probability requirement,’ it does require a pleading to show ‘more than a sheer possibility that a defendant has acted unlawfully.” Connelly v. Lane Constr. Corp., 809 F.3d 780, 786 (3d Cir. 2016) (internal citation omitted) (first quoting Twombly, 550 U.S. at 556; then quoting /qbal, 556 U.S. at 678). “The plausibility determination is ‘a context-specific task that requires the reviewing court to draw on its judicial experience and common sense.” /d. at 786-787 (quoting /qbal, 556 U.S. at 679).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jackson v. Astrue
506 F.3d 1349 (Eleventh Circuit, 2007)
Arbaugh v. Y & H Corp.
546 U.S. 500 (Supreme Court, 2006)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Henderson v. Shinseki
131 S. Ct. 1197 (Supreme Court, 2011)
United States v. Montgomery
253 F.2d 509 (Third Circuit, 1958)
Ethypharm S.A. France v. Abbott Laboratories
707 F.3d 223 (Third Circuit, 2013)
Phillips v. County of Allegheny
515 F.3d 224 (Third Circuit, 2008)
Lien Huynh v. Chase Manhattan Bank
465 F.3d 992 (Ninth Circuit, 2006)
Sandra Connelly v. Lane Construction Corp
809 F.3d 780 (Third Circuit, 2016)
Schuchardt v. President of the United States
839 F.3d 336 (Third Circuit, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Techniquex Specialty Flooring, Inc. v. Philadelphia Idemnity Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/techniquex-specialty-flooring-inc-v-philadelphia-idemnity-insurance-pamd-2022.