United States Ex Rel. E & H Steel Corp. v. C. Pyramid Enterprises, Inc.

509 F.3d 184, 2007 U.S. App. LEXIS 27347, 2007 WL 4166245
CourtCourt of Appeals for the Third Circuit
DecidedNovember 27, 2007
Docket06-4209
StatusPublished
Cited by6 cases

This text of 509 F.3d 184 (United States Ex Rel. E & H Steel Corp. v. C. Pyramid Enterprises, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. E & H Steel Corp. v. C. Pyramid Enterprises, Inc., 509 F.3d 184, 2007 U.S. App. LEXIS 27347, 2007 WL 4166245 (3d Cir. 2007).

Opinion

OPINION

WEIS, Circuit Judge.

In this Miller Act case, we decide that a firm acted as a subcontractor when it supplied fabricated steel to the prime contractor that then used the material to construct the framework for a large Air Force facility. The subcontractor defaulted in payments due the company that it hired to fabricate the steel and deliver it to the *185 construction site. The District Court denied recovery to the steel fabricator in this suit against the prime contractor and its sureties. We will reverse and remand for entry of judgment in favor of the steel company.

In September 2002, C. Pyramid Enterprises, Inc. was awarded a contract by the United States Army Corps of Engineers to design and build a large C-17 Maintenance Hangar and Shops facility at the McGuire Air Force Base in New Jersey. The original contract price was $24,119,450.00.

Pyramid issued a standard form “purchase order” to Havens Design-Build to provide custom fabricated structural steel for the building’s framework at a cost of $2,230,000.00. The agreement provided that Havens was also to arrange for the preparation of shop drawings and erection drawings, design the connectors for the steel, and perform some “design assist engineering” that primarily involved material substitution.

Havens in turn contracted with E & H Steel Company to fabricate the steel and deliver it to the construction site. E & H delivered 50 trailers of fabricated steel between November 13, 2003 and April 16, 2004. 1 Pyramid erected the steel framework for the building and did most of the remaining construction itself, including the electrical, mechanical, site utilities, plumbing, and concrete work.

In accordance with the Miller Act, 40 U.S.C. § 3131(b)(2), Pyramid issued a payment bond in favor of “all persons having a direct relationship with [Pyramid] or a subcontractor of [Pyramid] for furnishing labor, material or both in the prosecution of the work provided for in the contract.” Defendants Fidelity & Deposit Company of Maryland and Zurich American Insurance Company acted as sureties on the bond.

Although it had been paid by Pyramid during the construction process, Havens filed for bankruptcy owing E & H $565,125.40 for the delivered steel. E & H brought suit against Pyramid and its sureties, asserting entitlement to reimbursement from the payment bond. After a bench trial, the District Court found in favor of defendants.

The Court correctly determined that because of a statutory limitation E & H’s right to recover on the bond hinged on whether Havens was a “subcontractor” under § 3133(b)(2) of the Miller Act. However, case law did not provide a uniform rule for determining whether a company such as Havens, which acted as a middleman between a general contractor and a supplier of materials or services, was a “subcontractor.” In resolving that issue, the Court considered a number of factors, including the nature of the material or service supplied, the cost of the material or service in relation to the total contract price, the payment terms and exchange of information, and the overall relationship between the contractor and the middleman.

The District Court concluded that Havens furnished standard work customarily performed by steel fabricators, a role similar to that of a supplier of pre-cut wooden beams for residential construction. Havens supplied material from non-inventory stock and Pyramid used the steel to erect the building’s substantial frame. Although Havens’ work on the project comprised 7.8% of the total contract price, the District Court noted that Havens did not post a bond or provide insurance or payroll *186 data to Pyramid. Finally, the District Court observed that Pyramid and Havens did not have a prior relationship.

After evaluating these details, the District Court held that Havens was a material supplier and not a “subcontractor” under the Miller Act. Therefore, E & H was not entitled to recover on the bond.

E & H timely appealed. We have jurisdiction under 28 U.S.C. § 1291 and under the Miller Act, 40 U.S.C. § 3133(b)(3)(B).

I.

Congress recognized that sovereign immunity left suppliers of labor or materials for federal construction projects without the protection of the mechanics’ liens normally available in private industry. See Dep’t of Army v. Blue Fox, Inc., 525 U.S. 255, 264-65, 119 S.Ct. 687, 142 L.Ed.2d 718 (1999). To provide some protection for suppliers, Congress enacted the Heard Act 2 and later replaced it with the Miller Act, found in its current version at 40 U.S.C. § 3131, et seq. Id. 3

The Miller Act requires every contractor on a federal government contract exceeding $100,000 to provide “[a] payment bond with a surety ... for the protection of all persons supplying labor and material in carrying out the work provided for in the contract.” 40 U.S.C. § 3131(b)(2). In pertinent part, § 3133(b)(1) provides that “[ejvery person that has furnished labor or material ... and that has not been paid in full within 90 days after the day on which the person did or performed the last of the labor or furnished or supplied the material ... may bring a civil action on the payment bond.” 40 U.S.C. § 3133(b)(1).

However, § 3133(b)(2) limits the scope of those protected. It states:

“A person having a direct contractual relationship with a subcontractor but no contractual relationship, express or implied, with the contractor furnishing the payment bond may bring a civil action on the payment bond on giving written notice to the contractor within 90 days from the date on which the person did or performed the last of the labor or furnished or supplied the last of the material for which the claim is made.”

40 U.S.C. § 3133(b)(2).

Because the statute does not define the term “subcontractor,” the Supreme Court has been called upon to explain the meaning of the term. In Clifford F. MacEvoy Co. v. United States ex rel. Calvin Tomkins Co., 322 U.S. 102, 64 S.Ct. 890, 88 L.Ed. 1163 (1944), the Court recognized that the Miller Act “is highly remedial in nature.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
509 F.3d 184, 2007 U.S. App. LEXIS 27347, 2007 WL 4166245, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-e-h-steel-corp-v-c-pyramid-enterprises-inc-ca3-2007.