Skanska USA Building, Inc. v. Smith Management Construction, Inc.

967 A.2d 827, 184 Md. App. 659, 2009 Md. App. LEXIS 23
CourtCourt of Special Appeals of Maryland
DecidedMarch 10, 2009
Docket221, September Term, 2008
StatusPublished
Cited by2 cases

This text of 967 A.2d 827 (Skanska USA Building, Inc. v. Smith Management Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Skanska USA Building, Inc. v. Smith Management Construction, Inc., 967 A.2d 827, 184 Md. App. 659, 2009 Md. App. LEXIS 23 (Md. Ct. App. 2009).

Opinion

JAMES R. EYLER, Judge.

This case turns on the interpretation of dispute resolution provisions in a subcontract relating to federal procurement. The contract relates to the construction of a biomedical re *661 search facility (“the project”), on property owned by FSK Land Corporation (“FSK”), located on the Johns Hopkins University Bayview campus, and leased to the National Institutes of Health of the federal Department of Health and Human Services. (“NIH”). On December 31, 2001, FSK entered into a contract, entitled the Development Management Services Agreement (“DMSA”), with Smith Management Construction, Inc. (“SMCI”), an appellee, pursuant to which SMCI agreed to serve as “Development Manager” for the project. BRC Lease Co., LLC (“BRC”), another appellee, was formed for the sole purpose of entering into a long term lease with NIH. FSK assigned its interests under the lease and the DMSA to BRC.

On May 20, 2004, SMCI entered into a contract with Skanska USA Building, Inc. (“Skanksa”), appellant, pursuant to which appellant agreed to serve as construction manager for the project. The contract consisted of an “Agreement for Construction Services” (“the Agreement”) and a “Supplement to the Agreement for Construction Services” (“Supplement”) (collectively, “the Contract”). Section 7.6.1 of the Supplement expressly incorporated, along with other documents, the lease with NIH and the DMSA, expressly including the dispute resolution provisions contained in the DMSA.

Appellant asserts that, after it began work, SMCI made substantial changes in the project for which appellant was not adequately compensated. Ultimately, on August 30, 2007, appellant filed suit against appellees in the Circuit Court for Baltimore City.

SMCI and BRC filed motions to dismiss, asserting primarily that the court lacked subject matter jurisdiction. The circuit court, by order and memorandum opinion dated February 6, 2008, granted, without prejudice, SMCI’s motion to dismiss, and by order dated March 14, 2008, granted, without prejudice, BRC’s motion to dismiss, on the ground that the court lacked subject matter jurisdiction.

Appellant filed a motion to alter or amend judgment. The court denied it, and appellant noted this appeal.

*662 The resolution of this case turns on the interpretation of the Contract and DMSA, specifically, the dispute resolution provisions. The issue is whether appellant is required to pursue its claims under the procedure applicable to federal procurement contracts, specifically, the Contract Disputes Act of 1978, as amended, 41 U.S.C. §§ 601-613 and Federal Acquisition Regulation (“FAR”) § 52.233-1, 1 or whether appellant can proceed in this civil action. The circuit court held that the court lacked subject matter jurisdiction, directed the parties to proceed under the Contract Disputes Act, and dismissed the complaint without prejudice.

We agree with the circuit court that appellant may not pursue its claims in this action at this time, but conclude that the court erred in dismissing the complaint. We shall vacate the orders dismissing the complaint and remand the case to circuit court with the direction that the circuit court enter an order staying any further proceedings on the merits pending the completion of proceedings under the Contract Disputes Act. 2 We see no need to address the remaining contentions of the parties.

Background

In its complaint, appellant alleged that, pursuant to the Contract, it was to be paid costs plus a fee, the total not to exceed the guaranteed maximum price (“GMP”) in the amount of $168,276,652.00, as adjusted by various events, including *663 approved changes in the work. The adjusted figure was designated the “Contract Sum.” Changes in the project were reflected by “construction change directives” (“CCDs”), and “change orders” (“CO”). Appellant alleged that it complied with CCDs and CCs but did not receive a time extension or increase in the Contract Sum. Appellant alleged 20 specific instances in which SMCI breached the Contract and engaged in grossly negligent and intentional conduct.

Appellant included counts for breach of contract, breach of fiduciary duty, promissory estoppel/detrimental reliance, quantum meruit, and unjust enrichment against SMCI. Appellant expressly alleged that all non-contract counts were pled as alternatives to the contract count. Appellant also included counts for quantum meruit and unjust enrichment against BRC. Appellant requested monetary damages, interest, costs, attorney’s fees, and an extension of the completion date under the Contract through the date of actual substantial completion. The Contract, a CCD log, and pending COs were filed as exhibits to the complaint and incorporated therein.

The Agreement provides that SMCI serves in the capacity of “owner” of the project but recognizes that it is not the true owner, reciting that FSK/BRC is the owner and lessor and NIH is the lessee. The Agreement further provides that SMCI serves as the contractor, responsible for all construction services necessary to fulfill SMCI’s obligations under the DMSA. Section 7.6.1 of the Supplement provides, in part: “For disputes involving NIH or Lessor [BRC], Contractor [SMCI] shall adhere to the dispute resolution provisions contained in the DMSA.”

Section 10.2 of the DMSA provides, in pertinent part:

10.2 Disputes. All claims, disputes or other matters in controversy between Lessor [3] and Development Manager [4] relating to or arising out of the performance of this Agreement and the Project (“Disputes”) and not resolved pursu *664 ant to the ADR Procedures shall be resolved in accordance with the provisions of this Section 10.2.
(a) Disputes Involving NIH. Disputes for which Lessor or Development Manager contend that the NIH may be responsible (the “Government Disputes”) shall be resolved pursuant to the Disputes Clause, FAR [Federal Acquisition Regulations] § 52.233-1. Both Lessor and Development Manager agree to cooperate in the presentation and prosecution or defense of Government Disputes. If Development Manager requests an extension of time or additional compensation and alleges that the event causing the delay or additional compensation is the responsibility of the Government, then Lessor will cooperate with and assist Development Manager in timely presenting a request for an extension of time or additional compensation to the Government, including sponsoring a claim against the Government. Such assistance may include, with Lessor’s consent (which consent shall not be unreasonably withheld) and to the extent permitted by applicable law, permitting Development Manager to present and negotiate the proposal directly with NIH.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conway Commercial Warehousing, LLC v. Fedex Freight East, Inc.
2011 Ark. App. 51 (Court of Appeals of Arkansas, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
967 A.2d 827, 184 Md. App. 659, 2009 Md. App. LEXIS 23, Counsel Stack Legal Research, https://law.counselstack.com/opinion/skanska-usa-building-inc-v-smith-management-construction-inc-mdctspecapp-2009.