Nello L. Teer Co. v. Jones Bros., Inc.

641 S.E.2d 832, 182 N.C. App. 300, 2007 N.C. App. LEXIS 576
CourtCourt of Appeals of North Carolina
DecidedMarch 20, 2007
DocketCOA06-340
StatusPublished
Cited by9 cases

This text of 641 S.E.2d 832 (Nello L. Teer Co. v. Jones Bros., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nello L. Teer Co. v. Jones Bros., Inc., 641 S.E.2d 832, 182 N.C. App. 300, 2007 N.C. App. LEXIS 576 (N.C. Ct. App. 2007).

Opinion

MARTIN, Chief Judge.

The North Carolina Department of Transportation (“NCDOT”) initiated public highway construction projects to widen a 12-mile segment of U.S. Highway 15-501 in Chatham and Orange Counties. In January 2001, NCDOT contracted with Jones Brothers Incorporated (“Jones Bros.”) to perform the work, the completion of which was originally scheduled for thirty-five months. Jones Bros, subcontracted all of the paving work for the project to Nello L. Teer Company (“Teer”). All facets of construction were to be performed in accordance with NCDOT’s contract and Teer agreed to be bound by these same conditions.

Teer used the Traffic Control Plan from NCDOT’s specifications to determine that it would be involved in the project for fifteen months. Completion of the project was substantially delayed; reasons for the delays are in controversy. Jones Bros, contended the delays came about due to NCDOT’s failure to timely relocate underground and overhead utilities that were impeding the construction. In addition, NCDOT redesigned the project, resulting in a further delay of six months. Teer contended that substantial delays were attributable to improper project management by Jones Bros. Teer alleged it ultimately spent more than forty-three months on the project, causing it significant monetary damages and constituting a material and cardinal change to the contract. On 30 June 2004, Teer filed a complaint seeking damages for such delays and declaratory relief excusing Teer from further performance under the contract. Jones Bros, filed an answer, moving to dismiss, asserting affirmative defenses, and asserting counterclaims. Pursuant to an order of the trial court, NCDOT was made a party to the litigation, and both Teer and Jones Bros, amended their pleadings. Jones Bros.’ amended pleading included cross-claims against NCDOT and a motion to dismiss Teer’s claims, citing Teer’s failure to exhaust its administrative remedies. NCDOT moved to dismiss the claims of both Teer and Jones Bros.

On 11 January 2005, the trial judge granted partial summary judgment denying Teer’s claims for declaratory relief. Jones Bros, moved for a stay in the litigation between Jones Bros, and Teer as well as the cross-claims between Jones Bros, and NCDOT until resolution of the *303 administrative process as outlined in the job’s contract, which could not begin until the job was finished. By order dated 11 October 2005, the trial court denied the motion. On 18 November 2005, NCDOT’s motion to dismiss Jones Bros.’ cross-claims was denied.

Defendants-appellants Jones Bros, and Fireman’s Fund Insurance Company appeal from the order entered on 11 October 2005 denying their motion for a stay and determining that NCDOT was not a necessary party to the litigation at issue. Defendant-appellant NCDOT appeals the order entered 18 November 2005 denying its motion to dismiss cross-claims asserted by Jones Bros. Plaintiff-appellee and cross-appellant Teer cross-appeals from the order entered 11 January 2005 granting Jones Bros.’ motion for partial summary judgment.

At the outset, we note that each of the appeals before this Court is from an interlocutory order. “An interlocutory order is one made during the pendency of an action, which does not dispose of the case, but leaves it for further action by the trial court in order to settle and determine the entire controversy.” Veazey v. City of Durham, 231 N.C. 357, 362, 57 S.E.2d 377, 381 (1950). A party cannot immediately appeal an interlocutory order unless (1) a trial court enters a final judgment to fewer than all of the claims or parties in an action and certifies that there is no reason to delay the appeal or (2) the failure to grant immediate review would affect a substantial right. Davis v. Davis, 360 N.C. 518, 524-25, 631 S.E.2d 114, 119 (2006) (citation omitted). A right is substantial if it will be lost or irremediably and adversely affected if the trial court’s order is not reviewed before a final judgment. RPR & Assocs. v. University of N.C. Chapel Hill, 153 N.C. App. 342, 347, 570 S.E.2d 510, 514 (2002). “Whether a substantial right is affected is determined on a case-by-case basis and should be strictly construed.” Flitt v. Flitt, 149 N.C. App. 475, 477, 561 S.E.2d 511, 513 (2002).

I.

Jones Bros, first challenges the trial court’s denial of its motion to stay. The denial of a motion to stay is an interlocutory order with no absolute right to an immediate appeal. Howerton v. Grace Hosp., Inc., 124 N.C. App. 199, 201, 476 S.E.2d 440, 442 (1996). The order did not dispose of any of the claims or parties. Id., 476 S.E.2d at 442-43. As a result, Jones Bros, must demonstrate that the trial court’s decision deprived it of a substantial right which will be lost absent immediate review. Id., 476 S.E.2d at 443. A party’s right *304 to avoid separate trials of the same factual issues may constitute a substantial right. Green v. Duke Power Co., 305 N.C. 603, 606, 290 S.E.2d 593, 595 (1982) (citation omitted). This Court has interpreted Green as creating a two-part test requiring that a party show “(1) the same factual issues would be present in both trials and (2) the possibility of inconsistent verdicts on those issues exists.” N.C. Dep’t of Transp. v. Page, 119 N.C. App. 730, 735-36, 460 S.E.2d 332, 335 (1995) (citation omitted).

Jones Bros, argues that it is entitled to an immediate appeal because the denial of the motion to stay exposes it to multiple trials on overlapping issues and the possibility of inconsistent verdicts on the delay claims. Jones Bros.’ motion requested that Teer’s claims “be stayed pending resolution of claims against NCDOT through the administrative process[.]” The liability of NCDOT, as third-party defendants to Jones Bros., is dependent upon the resolution of the issue of Jones Bros.’ liability to Teer. Further, the delay claims depend upon similar factual issues and similar proof. The delays alleged by Teer during its subcontracting work are the same delays that affected Jones Bros, and which involve NCDOT. In addition, inconsistent verdicts could occur. For example, Jones Bros, could be found liable to Teer on some issues, but could be precluded from raising those same issues against NCDOT during the administrative process. Haying found a substantial right to be affected, Jones Bros, motion for a stay, which was denied by the trial court, is immediately appealable.

Jones Bros, argues that the trial court erred by denying the motion to stay. We agree. Contractual agreements that call for the parties to exhaust administrative procedures are binding unless such procedures are shown to be “inadequate or unavailable.” U.S. v. Grace & Sons, Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Finks v. Middleton
795 S.E.2d 789 (Court of Appeals of North Carolina, 2016)
Smith v. Lake Bay East, LLC
743 S.E.2d 684 (Court of Appeals of North Carolina, 2013)
Builders Mutual Ins. v. Meeting Street Builders, LLC
736 S.E.2d 197 (Court of Appeals of North Carolina, 2012)
Reese v. Mecklenburg County
694 S.E.2d 453 (Court of Appeals of North Carolina, 2010)
High Rock Lake Partners, LLC v. North Carolina Department of Transportation
693 S.E.2d 361 (Court of Appeals of North Carolina, 2010)
GEMINI DRILLING AND FOUNDATION, LLC v. National Fire Ins. Co.
665 S.E.2d 505 (Court of Appeals of North Carolina, 2008)
Durham County v. Graham
663 S.E.2d 467 (Court of Appeals of North Carolina, 2008)
Jones v. County of Carteret
643 S.E.2d 669 (Court of Appeals of North Carolina, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
641 S.E.2d 832, 182 N.C. App. 300, 2007 N.C. App. LEXIS 576, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nello-l-teer-co-v-jones-bros-inc-ncctapp-2007.