A.H. Beck Foundation Co. v. Jones Bros.

603 S.E.2d 819, 166 N.C. App. 672, 2004 N.C. App. LEXIS 2023
CourtCourt of Appeals of North Carolina
DecidedNovember 2, 2004
DocketCOA03-1431
StatusPublished
Cited by4 cases

This text of 603 S.E.2d 819 (A.H. Beck Foundation Co. v. Jones Bros.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A.H. Beck Foundation Co. v. Jones Bros., 603 S.E.2d 819, 166 N.C. App. 672, 2004 N.C. App. LEXIS 2023 (N.C. Ct. App. 2004).

Opinion

TIMMONS-GOODSON, Judge.

The North Carolina Department of Transportation (“NCDOT”) appeals the trial court order denying its motion to dismiss the third-party complaint of Jones Brothers, Inc. (“Jones”). For the reasons discussed herein, we reverse.

The facts and procedural history pertinent to the instant appeal are as follows: In 1996, NCDOT began receiving bids for Highway Project No. 8.1631701 (“the project”), which involved the construction of a new bridge on Highway 49 over the Yadkin River at *674 Tuckertown Lake. On 17 December 1996, Jones submitted the lowest bid for the project, and on 5 February 1997, NCDOT awarded Jones a contract to perform the work on the project. Jones subsequently received bids from subcontractors for separate portions of the work required by the project. On 13 February 1997, Jones entered into a subcontract with A.H. Beck Foundation Company, Inc. (“Beck”), whereby Beck would drill vertical subsurface shafts and install casings therein, in order to stabilize and retain the hillside slopes above and adjacent to the roadway approaching the bridge.

In June 1997, Beck began drilling the slope-stabilization shafts and immediately encountered hard, dense rock below the surface. On 6 August 1997, Beck advised Jones that it was encountering significant problems related to the subsurface conditions, and that it would require additional compensation and a time extension in order to complete the work. In response, Jones submitted a claim to NCDOT on Beck’s behalf on 11 August 1997. On 20 August 1997, NCDOT Resident Engineer K.E. Raulston (“Raulston”) replied by letter as follows:

I have received your letter dated August 11, 1997, which contained notification of intent to file a claim. The claim is filed on behalf of [Beck] who claim that they are encountering conditions different than that shown in the subsurface plans.
I refer you to Section 102-07 on the North Carolina Standard Specifications “subsurface information.” The department does not warrant or guarantee the accuracy of the subsurface information. The contractor shall have no claim for additional compensation or for an extension of time for any reason resulting from the actual conditions encountered at the site differing from those indicated in the subsurface information. Therefore any claim regarding subsurface conditions is denied.

Beck continued to encounter dense rock at the drill sites, and as a result was unable to finish the slope-stabilization portion of the work until 17 April 1998. Beck thereafter submitted to Jones a “Claim for Adjustment in Compensation Relative to Slope Stabilization Piles,” which detailed Beck’s “unanticipated delays, disruptions, denials, interference, [and] altered and/or extra work” in the form of “force account records.” Jones forwarded Beck’s claim to NCDOT on 12 August 1998, but subsequently requested return of the claim. On 15 October 1998, Raulston advised Jones that “initial review of the claim indicates that it would have been denied for the same reason it was *675 denied the first time.” Subsequent claims were filed by Jones on behalf of Beck; however, each claim was denied by NCDOT.

On 23 April 2Q00, Beck filed a complaint against- Jones, alleging, inter alia, breach of subcontract, breach of implied warranty, unfair and deceptive trade practices, wrongful termination, and mutual mistake. The complaint requested “at least” $7,973,528.14 in damages. On 10 October 2000, Jones filed an answer, counterclaim, and third-party complaint against NCDOT. In its third-party complaint, Jones alleged that its contract with NCDOT “contained terms and conditions providing for the preparation of Supplemental Agreements and change orders to compensate the contractor for modifications to the contract and any alterations in the plans or the details of construction for extra work, for suspensions of work, and for quantity adjustments.” Jones further alleged that “supplemental agreements should have been issued by NCDOT,” and that “[t]o the extent that the [project] conditions differ from those represented by NCDOT in its plans and specifications and amount to an alteration of the plans or the details of construction,” Jones was entitled to “indemnity and reimbursement from NCDOT in full payment of any and all damages that may be due to Beck.”

On 29 January 2001, NCDOT filed a motion to dismiss in lieu of answer. On 2 May 2001, the trial court granted NCDOT’s motion to dismiss, concluding that Jones “ha[d] not yet exhausted the administrative remedies provided under N.C.G.S. § 136-29.” The trial court granted the motion to dismiss without prejudice to Jones’ right to reassert its third-party complaint against NCDOT, “in the event the administrative process does not fully resolve the disputes between the parties.”

Jones and NCDOT continued to correspond regarding the resolution of their dispute. On 22 June 2001, R.C. Martin (“Martin”), Jones’ Chief Operating Officer, sent to NCDOT “the three completed documents required for the closeout and the release of retainage” on the project, including an affidavit delineating Jones’ third-party claim. On 24 September 2001, Martin wrote NCDOT again, whereby he advised NCDOT as follows:

[W]e are submitting, in accordance with Section 109-10 of the NCDOT Standard Specifications, our intent to continue to pursue the claims filed on behalf of our subcontractor, [Beck]. Their request for additional compensation and time has been filed and received by NCDOT. Upon receipt of our Final Estimate, it is our *676 intent to file a verified claim for the areas in dispute in accordance with section 107-25.

On 19 October 2001, NCDOT State Construction Engineer Steven D. DeWitt (“DeWitt”) sent Jones a letter regarding Jones’ claim. The letter was sent via certified mail and its subject line read “Payment of Final Estimate.” The letter stated as follows:

Attached is final estimate warrant number 1212064 in the amount of $5,299.81 which represents the final payment of the contract. Also attached for your files is a copy of the final estimate which is your final statement.

As stated, attached to the letter was a check in the amount of $5,299.81 (“final pay warrant”) and a copy of estimate number 40 (“Estimate 40”). Estimate 40 was entitled “Contract Final Estimate.” Next to the “Remarks” section of Estimate 40 was the phrase “The Final Estimate.” Next to the “Percent Complete” section of Estimate 40 was the number 100, and next to the “% Complete By Progress Chart” section of Estimate 40 was the number 100. Estimate 40 further indicated that the “Amount Transferred To Trust Account This Estimate” was $149,420.58.

On 30 October 2001, NCDOT received confirmation through a certified return receipt that the 19 October letter was delivered to Jones on 24 October 2001. On 25 October 2001, Jones tendered the final pay warrant. On 21 December 2001, Martin sent NCDOT Construction Estimates & Claims Engineer Phil Watts (“Watts”) an email which stated:

When you have a spare moment, could you please check on the status of Final Quantities and Retainage for the above referenced project, your NCDOT PROJECT 8.1631701.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doe v. Roman Catholic Diocese Charlotte
775 S.E.2d 918 (Court of Appeals of North Carolina, 2015)
New Hanover County Child Support Enforcement ex rel. Beatty v. Greenfield
219 N.C. App. 531 (Court of Appeals of North Carolina, 2012)
NEW HANOVER COUNTY v. Greenfield
723 S.E.2d 790 (Court of Appeals of North Carolina, 2012)
Nello L. Teer Co. v. Jones Bros., Inc.
641 S.E.2d 832 (Court of Appeals of North Carolina, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
603 S.E.2d 819, 166 N.C. App. 672, 2004 N.C. App. LEXIS 2023, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ah-beck-foundation-co-v-jones-bros-ncctapp-2004.