Kiska Construction Corp.-U.S.A. v. Washington Metropolitan Area Transit Authority

736 F. Supp. 2d 171, 2010 U.S. Dist. LEXIS 93778, 2010 WL 3522234
CourtDistrict Court, District of Columbia
DecidedSeptember 9, 2010
DocketCivil Action 09-817 (CKK)
StatusPublished
Cited by1 cases

This text of 736 F. Supp. 2d 171 (Kiska Construction Corp.-U.S.A. v. Washington Metropolitan Area Transit Authority) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kiska Construction Corp.-U.S.A. v. Washington Metropolitan Area Transit Authority, 736 F. Supp. 2d 171, 2010 U.S. Dist. LEXIS 93778, 2010 WL 3522234 (D.D.C. 2010).

Opinion

MEMORANDUM OPINION

COLLEEN KOLLAR-KOTELLY, District Judge.

This action is brought by Plaintiff Kiska Construction Corporation-U.S.A. and Kajima Engineering and Construction Inc., a Joint Venture (“Kiska”) for review of an administrative determination issued by the Armed Services Board of Contract Appeals (“ASBCA”) relating to a contract dispute between Kiska and Defendant Washington Metropolitan Area Transit Authority (“WMATA”). On February 19, 2009, the ASBCA rendered a decision granting in part and denying in part Kiska’s contract appeals, and Kiska now seeks confirmation in part and reversal in part of the ASBCA’s decision. Kiska has filed a [12] Motion for Summary Judgment, and WMATA has filed a [14] Cross-Motion for Summary Judgment. The motions have been fully briefed and are now ripe for decision. Based on the parties’ briefs, the administrative record, the relevant authorities, and the case as a whole, the Court shall GRANT-IN-PART and DENY-IN-PART the parties’ motions for summary judgment. For the reasons explained below, the Court shall affirm the ASBCA’s decision with respect to all of the issues contested by the parties.

I. BACKGROUND

A. The Contract and the First Federal Action

On February 25, 1994, the Washington Metropolitan Area Transit Authority (“WMATA”) awarded Contract No. 1E0023 (the “Contract”) to Kiska Construction Corp. USA and Kajima Engineering and Construction, Inc., a Joint Venture (“Kiska”) for the construction of twin single-track earth tunnels, an access shaft, fan shaft, vent shaft, and related work as part of the Metrorail system. Pl.’s Stmt. 1 ¶ 1. During performance of the Contract, there were a number of disputes *174 about various terms of the Contract and the performance required. Id. ¶ 2.

On November 10, 1997, Kiska filed a lawsuit against WMATA in this Court. See J.A. vol. 3, tab 10 (Complaint, KiSKA Constr. Corp.-U.S.A. v. Wash. Metro. Area Transit Auth., Civ. No. 97-2677 (D.D.C. filed Nov. 10, 1997)). In that lawsuit, Kiska alleged that WMATA had made material misrepresentations regarding what would be required for the Contract and that WMATA had failed to perform its obligations as promised. Kiska asserted claims for (1) fraudulent misrepresentation, (2) negligent misrepresentation, (3) quantum meruit, (4) unilateral mistake, and (5) material breach of contract. See id.; Pl.’s Stmt. ¶2. This Court dismissed the first two causes of action, granted summary judgment for WMATA on the quantum meruit claim, and allowed the last two causes of action to be tried by a jury. Pl.’s Stmt. ¶ 2.

The complaint in the First Federal Action included a number of allegations that the parties believe are material to the claims before the ASBCA. For example, in Count IV of the complaint, for “Material Breach of Contract,” Kiska alleged as follows:

248. WMATA materially breached the Contract, including express and implied warranties, in at least the following ways:
a. WMATA failed to disclose necessary and vital information to KiSKA-Kajima relating to the performance and safety of the work to be performed;
b. The Contract plans and specifications and directed construction methods prepared by WMATA were defective, misleading, incomplete and unfit for their intended purpose;
c. WMATA breached its duty to cooperate with KiSKA-Kajima and not hinder or interfere with KiSKA-Kajima’s performance;
d. WMATA failed and refused to grant time for extensions for excusable and/or compensable delays encountered by KiSKA-Kajima;
e. WMATA directed that extra work beyond the scope of the Contract be performed and has failed and/or refused to pay for such extra work;
f. WMATA failed and refused to administer the Contract in accordance with its terms and with good faith and fair dealing;
g. WMATA failed to coordinate the Project with the numerous Washington, D.C. utility companies and permit-granting agencies;
h. WMATA failed to coordinate the work of its other contractors, including Blake Construction;
i. WMATA failed to obtain necessary permits for construction in a timely manner;
j. WMATA failed and refused to review and approve shop drawings in a timely manner;
k. WMATA failed to provide timely and complete access to the jobsite;
l. WMATA directed the acceleration of the work without compensating KiS-KA-Kajima;
m. WMATA arbitrarily and unreasonably directed pervasive changes to the Contract which constituted a cardinal change.

AR, vol. 3, tab 10 (Complaint) ¶ 248. Although subparagraph (e) referenced “extra work beyond the scope of the Contract,” Kiska’s complaint did not identify the alleged extra work to which it was referring. Kiska also alleged the following: “Despite repeated requests by KiS-KA-Kajima throughout Contract perform *175 anee for change orders and appropriate time extensions to compensate KiSKA-Kajima for the additional costs and delays to the Project schedule caused by WMA-TA, WMATA continuously refused to accept responsibility for its numerous acts and omissions.” Id. ¶ 185. Kiska did not specifically allege in its complaint that WMATA wrongfully withheld the balance of the contract price or that it had breached the contract by failing to pay the contract retainage. See generally id.; Pl.’s Stmt. ¶ 3.

During the trial, the Court allowed Kiska to present evidence of damages based on the “modified total cost” method, which calculates the amount of damages as the total actual costs incurred the contractor (Kiska) in performing the contract minus the contractor’s bid price, adjusted to account for the costs of harms for which the contractor is itself responsible. See AR, vol. 3, tab 28 (Mem.Op. Nov. 1, 2000); Def.’s Stmt. ¶ 5. One of Kiska’s experts, Mr. Kelley, testified at the trial that Kiska’s damages had to be calculated using the modified total cost method because, in his opinion, the breaches involved in the litigation were so complex and “inextricably intertwined” that there was no other method available to compute damages. AR, vol. 3, tab 23 (Trial Tr.) at 2258-64. Mr. Kelley testified that in his calculations, he subtracted amounts for contract modifications paid by WMATA. See id. at 2421. Another of Kiska’s experts, Mr. Jeffrey E. Fuchs, also testified about the modified total cost method of calculating damages. In his calculation of damages, Mr. Fuchs added $650,000 retainage, explaining it as “monies that have been earned by the contractor during the course of its work that the owner withholds and gives back at the end of the project.” Id. at 2609. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BRDC, a Joint Venture
Armed Services Board of Contract Appeals, 2019

Cite This Page — Counsel Stack

Bluebook (online)
736 F. Supp. 2d 171, 2010 U.S. Dist. LEXIS 93778, 2010 WL 3522234, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kiska-construction-corp-usa-v-washington-metropolitan-area-transit-dcd-2010.