BRDC, a Joint Venture

CourtArmed Services Board of Contract Appeals
DecidedJuly 8, 2019
DocketASBCA No. 60130, 60668, 61611
StatusPublished

This text of BRDC, a Joint Venture (BRDC, a Joint Venture) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BRDC, a Joint Venture, (asbca 2019).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) BRDC, a Joint Venture ) ASBCA Nos. 60130, 60668, 61611 ) Under Contract No. N69450-10-C-1262 )

APPEARANCE FOR THE APPELLANT: Michael T. Ambroso, Esq. DCK Worldwide, LLC Pittsburgh, PA

APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq. Navy Chief Trial Attorney Matthew D. Bordelon, Esq. Russell A. Shultis, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE MCILMAIL

In this construction matter, appellant seeks additional compensation for concrete, aggregates, and concrete testing, and for sand for masonry and stucco. The parties decided to submit this case on the record pursuant to Board Rule 11. Only entitlement is before us.

FINDINGS OF FACT

Appellant is a joint venture consisting ofDCK Worldwide, LLC, and Burns and Roe Services Corporation (BRSC) (R4, tab 73.2 at 7061-62). On June 3, 2010, the government contracted with appellant for the construction of family housing units, and the renovation of a fitness center, at Naval Base Guantanamo Bay (GTMO), and to begin work within 10 calendar days after receiving the award (rev. R4, tab 6 at 109-91, 1096).

In June 2009, prior to contract award, the solicitation provided, by way of Amendment 0013:

The following clarification is provided regarding the pricing of concrete for this project:

The Government cannot guarantee the pricing of concrete, aggregate or concrete testing at Guantanamo Bay after 30 November 2010 when the contract pricing under BRSC' s existing contract expires. Offeror 's [sic] should do their best to realistically estimate what this cost may be after 1 December 2010 [emphasis added].

The successful offeror will be required to purchase concrete, aggregate and concrete testing services from the follow on supplier after 1 December 2010. The Government does guarantee that the price provided to the successful offeror will be no more than the best price available to the Government under the successor contract which will replace this contract in December of 2010.

The successful Contractor will be allowed to request an equitable adjustment to the contract after award to adjust their price if the price for concrete, aggregate and concrete testing varies more than 10% as of 1 December 2010 from the estimated price. This adjustment may be an increase if the price for these commodities in the Government's contract goes up, or a reduction in price if the Government's price is less. An adjustment will only be made if the Government's price varies more than 10% in either direction (up or down) from the Contractor's estimated price. The Contractor will be required to substantiate (provide supporting documentation) their request for adjustment.

(Rev. R4, tab 3 at 2270-71) (secondary emphasis omitted)

Section 1.3.23 of the contract, Concrete Batch Plant, provides:

A concrete batch plant is located on Naval Base Guantanamo Bay [GTMO]. Up to 5,000 cubic yards of concrete can be purchased for specific projects at GTMO ....

The government cannot guarantee the pricing of the concrete, aggregate or concrete testing at Guantanamo Bay after 30 November 2010 when the contract pricing under BRSC's existing contract expires. Offeror's [sic] will be required to purchase concrete, aggregate and concrete testing services from the follow on supplier after 1 December 2010. The Government does guarantee that the price provided to the successful offeror will be no more

I than the best price available to the Government under the successor contract which will replace this contract in December of 2010.

The successful Contractor will be allowed to request an equitable adjustment to the contract after award to adjust their price if the price for concrete, aggregate and concrete testing varies more than 10% as of 1 December 2010 from the estimated price. This adjustment may be an increase if the price for these commodities in the Government's Contract goes up or a reduction in price if the Government's price is less. An adjustment will only be made if the Government's price varies more than 10% in either direction (up or down) from Contractor's estimate price. The Contractor will be required to substantiate (provide supporting documentation) their request for adjustment.

(R4, tab 56 at 4475) (emphasis added)

The contract also provided, at section 1.3 .4.1, Availability and Cost of Government Materials and Services:

... The cost of Government materials, equipment, and services reflected in this specification are subject to fluctuation, revision, and adjustment.... [S]hould the actual rate required to be paid by the Contractor vary by more than 15 percent from that specified, the contract price will be adjusted to reflect the amount by which the rate actually paid varies by more than 15 percent from that specified.

(Id. at 4467) (emphasis added) Finally, in January 2010, prior to awarding the contract, the government answered this way to a bidder's question:

Question RFI 0017-14: Previously, Amendment 0008 had a price listing titled Attachment J-1, Exhibit Line Item Numbers. Does this still apply? Does it need to be reissued? Please advise.

Answer RFI 0017-14: The proposer shall use the J-1 provided in amendment 001 7.

3 (Rev. R4, tab 3 at 2121, 2125) Attachment J-1 to Amendment 0017 lists prices for concrete, aggregate, and concrete testing (R4, tab 3 at 2121, 2152-53). Appellant relied upon and incorporated the Attachment J-1 unit prices to calculate its anticipated costs for concrete, aggregates, and testing (app. R4, supp. A-1 at 3110 & attachs. 5, 7; A-2 at 3 1 11 & attachs. 5, 7; gov't br. at 9). BRSC held the contract to operate the concrete batch plant at GTMO from December 1, 2005 through November 30, 2010 (R4, tab 76 at 2966-75). On December 1, 2010, Bums and Roe Enterprises, Inc., was awarded the follow-on contract to operate the plant from December 1, 2010 through November 30, 2015 (app. R4, supp. A-3, attach. 2).

In March 2013, appellant requested a $2,364,246 increase in the contract price, citing section 1.3.23 (R4, tab 36 at 1283-84). The government, also citing section 1.3.23, responded by unilaterally modifying the contract to add $909,920.13 to the contract price (R4, tab 31 at 1187, 1190), as the government now explains (by way of a proposed finding of fact), '"to compensate [appellant] for concrete price costs increases exceeding 10 percent of the J-1 concrete prices that [appellant] cited" (gov't br. at 7121).

DECISION

ASBCA Nos. 60130 & 61611

The government says that appellant cannot rely on the J-1 price list as its "estimated price" for purposes of section 1.3.23 (see gov't br. at 9).* Section 1.3.23 provides that '"[t]he successful Contractor will be allowed to request an equitable adjustment to the contract after award to adjust their price if the price for concrete, aggregate and concrete testing varies more than 10% as of 1 December 2010 from the estimated price." (R4, tab 56 at 44 75) A concurrent interpretation by the parties of contract terms prior to a dispute is entitled to great, if not controlling, weight. Ver-Val Enterprises, Inc., ASBCA No. 43766, 95-1BCA127,334 at 136,232. Prior to this dispute, the government at least implicitly agreed with appellant that J-1 prices could be used as the estimated price benchmark for purposes of section 1.3 .23: appellant requested a contract price adjustment to take into account an increase above J-1 prices, and the government increased the contract price.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
BRDC, a Joint Venture, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brdc-a-joint-venture-asbca-2019.