Washington Metropolitan Area Transit Authority v. Buchart-Horn, Inc.

886 F.2d 733, 1989 WL 113155
CourtCourt of Appeals for the Fourth Circuit
DecidedJanuary 5, 1990
Docket88-2965
StatusPublished
Cited by4 cases

This text of 886 F.2d 733 (Washington Metropolitan Area Transit Authority v. Buchart-Horn, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Washington Metropolitan Area Transit Authority v. Buchart-Horn, Inc., 886 F.2d 733, 1989 WL 113155 (4th Cir. 1990).

Opinion

ERVIN, Chief Judge:

The defendant, Buchart-Horn, Inc., appeals from summary judgment entered against it after the Army Corps of Engineers Board of Contract Appeals ruled that Buchart-Horn provided substandard design specifications to its client, the Washington Metropolitan Area Transit Authority. Because we find that the parties’ contract did not confer jurisdiction over this dispute upon the Board of Contract Appeals, we reverse and remand for trial.

I.

This construction contract dispute arises from structural problems that developed in the roof of Grosvenor Station on the Wash *734 ington, D.C., Metro subway. The Washington Metropolitan Transit Authority (“WMATA”) hired Buchart-Horn to design and prepare construction plans and specifications for the station. In December of 1975, Buchart-Horn delivered the design plans and was paid $930,000 under the terms of its contract with WMATA. In the Spring of 1978, before construction on the station was complete, WMATA noticed cracking in the station’s mezzanine roof. WMATA hired several consultants to inspect the problem, determine its origin, and recommend remedial action. One of these reports, prepared by the engineering firm of Amman & Whitney, attributed the cracking to Buchart-Horn’s design. The Amman & Whitney report concluded that cracking in the roofs concrete surface occurred due to torsion stress in the roofs spandrel beams and that Buchart-Horn failed to conform to industry standards in anticipating and planning for this stress. WMATA subsequently demanded that Buc-hart-Horn bear the roughly one million dollars in costs required to repair the cracks.

When Buchart-Horn denied liability for the repair costs, WMATA filed this action in district court alleging professional negligence and breach of contract. Shortly thereafter, however, WMATA moved to stay the district court proceedings. WMA-TA asked for the stay to allow liability to be determined through administrative channels established by a “Disputes” clause in the parties’ contract. 1 Buchart-Horn opposed this motion on the grounds that WMATA’s professional negligence and breach claims were beyond the scope of the Disputes clause. The district court granted WMATA’s motion and, pursuant to the Disputes clause, the matter was heard by WMATA’s Contracting Officer.

The Contracting Officer determined that Buchart-Horn was liable for the full cost of repairs. Buchart-Horn timely appealed his ruling to the Army Corps of Engineers Board of Contract Appeals (“the Board”) which serves as WMATA’s duly authorized representative for reviewing Contracting Officer decisions. Before the Board, Buc-hart-Horn again argued that WMATA’s professional negligence and breach of contract claims were beyond the scope of the Disputes clause and thus not subject to administrative determination. The Board rejected this argument and, after a hearing, found that Buchart-Horn’s plans for Grosvenor Station failed to adhere to industry standards promulgated by the American Concrete Institute. The Board also found that this design failure caused the roof cracking and ordered Buchart-Horn to pay $824,550 toward the costs of repair.

WMATA then shifted the dispute back to the district court where the case was reopened. On WMATA’s motion for summary judgment, the district court found that the Board’s decision was supported by substantial evidence and, accordingly, enforced the Board’s order.

*735 II.

In this appeal, Buchart-Horn renews its argument that WMATA’s professional negligence and breach claims are beyond the scope of the Disputes clause and therefore beyond the Board’s administrative jurisdiction. If Buchart-Horn is correct, the Board’s decision, including its findings of fact, were beyond its authority, see United States v. Utah Construction & Mining Co., 384 U.S. 394, 407-408, 86 S.Ct. 1545, 1552-1553, 16 L.Ed.2d 642 (1965) (“Utah Construction”), and Buchart-Horn will be entitled to trial de novo in the district court. See Len Company and Associates v. United States, 385 F.2d 438, 440, 181 Ct.Cl. 29 (1967). Whether or not WMA-TA’s claims fall within the Disputes clause depends, of course, on the parties’ intentions and for that determination we must look to the language of their contract.

Fortunately, we have considerable guidance in making that determination for the Disputes clause “is a standard feature of government contracts, and arguments concerning [its] scope and appropriate function are not novel.” Rohr Industries v. WMATA, 720 F.2d 1319, 1322 (D.C.Cir.1983). The operative language of the clause requires “any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided by the contracting officer.” In Utah Construction, the Supreme Court addressed the scope of a Disputes clause nearly identical to the one at issue here. See Utah Construction, 384 U.S., at 399, note 2, 86 S.Ct., at 1548, note 2. The Court squarely rejected the government’s contention “that the disputes clause authorizes and compels administrative action in connection with all disputes arising between the parties in the course of completing the contract.” Id., at 404, 86 S.Ct., at 1551. Instead, after conducting an extensive review of how Disputes clauses had been interpreted in lower courts, the Court found that administrative resolution of a given claim is only authorized if some other provision of the contract establishes an administrative remedy sufficient to afford full relief for the claim. 2 Thus a Disputes clause is best understood as merely establishing an administrative procedure for resolving quarrels. Other contractual provisions, by granting a contract administrator authority to afford some remedy for the quarrel, must in effect confer jurisdiction.

WMATA asserts that by reason of the “Responsibility for Work” clause, the parties’ contract does contain a specific provision establishing an administrative remedy for its claims of professional negligence and breach. 3 We disagree. On a straightforward reading, Article 7 simply does not, as required by Utah, confer upon the Contracting Officer the power to make any

*736 determination or adjustment m connection with a contractor’s failure to provide professionally accurate designs. Indeed, neither the Contracting Officer or the Board are mentioned in the text of Article 7.

In this respect Article 7 stands in sharp contrast to other standard clauses in the parties’ contract which have traditionally been recognized as being within the scope of a Disputes clause.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
886 F.2d 733, 1989 WL 113155, Counsel Stack Legal Research, https://law.counselstack.com/opinion/washington-metropolitan-area-transit-authority-v-buchart-horn-inc-ca4-1990.