Martin K Eby Const v. Dallas Area Rapid

Court of Appeals for the Fifth Circuit·Decided May 19, 2004·No. 03-10728·Published

Opinion

United States Court of Appeals Fifth Circuit

F I L E D

REVISED MAY 18, 2004

April 29, 2004

IN THE UNITED STATES COURT OF APPEALS Charles R. Fulbruge III

FOR THE FIFTH CIRCUIT Clerk

No. 03-10728

MARTIN K EBY CONSTRUCTION COMPANY INC Plaintiff - Appellant

v.

DALLAS AREA RAPID TRANSIT Defendant - Appellee

Appeal from the United States District Court for the Northern District of Texas

Before KING, Chief Judge, and BENAVIDES and CLEMENT, Circuit Judges.

KING, Chief Judge:

Plaintiff-Appellant Martin K. Eby Construction Company, Inc.

(Eby) appeals the district court’s judgment dismissing its action against Defendant-Appellee Dallas Area Rapid Transit (DART). Agreeing with the lower court that Eby must exhaust administrative remedies before pursuing this action, we affirm.

I. Background

A. Facts DART is a regional transportation authority created under

Chapter 452 of the Texas Transportation Code. See Williams v. Dallas Area Rapid Transit, 242 F.3d 315, 317 (5th Cir. 2001); see also In re Dallas Area Rapid Transit, 967 S.W.2d 358, 359 (Tex. 1998). In April 2002, after a competitive-bidding process, DART awarded to Eby a contract to build a section of DART’s light-rail transit line near downtown Dallas. Construction commenced in June 2002. During the first six months of work on the project, Eby made little progress. According to Eby, this delay was caused by numerous deficiencies and inaccuracies in the designs that were contained in DART’s bid solicitation. In DART’s view, however, Eby bears significant responsibility for the construction delays. Regardless of the cause of the delays, we must determine whether Eby can pursue its suit without first exhausting administrative remedies.

DART’s Administrative Dispute-Resolution Process DART’s bid solicitation for the light-rail project--which is incorporated into the parties’ contract as an exhibit--contains a provision stating that the bidder, by responding to the solicitation, “agrees to exhaust its administrative remedies under . . . [1] [DART]’s Procurement Regulations or [2] the Disputes Clause of any resulting contract” before “seeking judicial relief of any type in connection with any matter related to this solicitation, the award of any contract, and any dispute under any resulting contract.” DART’s procurement regulations contain procedures for resolving disagreements with its

contractors. They were promulgated in accordance with express statutory authority; the Texas Legislature has empowered regional transportation authorities, such as DART, to “adopt and enforce procurement procedures, guidelines, and rules . . . covering: [inter alia] the resolution of . . . contract disputes.” TEX. TRANSP. CODE ANN. § 452.106(a)(2)(C) (Vernon 1999). Also, the contract between DART and Eby contains a disputes clause, which requires the contractor, Eby, to submit its grievances to DART’s administrative process before seeking judicial review.

DART’s procurement regulations and the contract’s disputes clause both provide for a similar administrative dispute- resolution process, and the regulations contain greater detail. Both encompass a broad range of potential disagreements. The disputes clause applies to “any dispute concerning a question of fact or law arising under or related to [the] contract.” Expounding on the coverage of DART’s administrative process, DART’s regulations state that the process covers “controversies between [DART] and a contractor which arise under, or by virtue of, a contract between them,” including, “without limitation, controversies based upon breach of contract, mistake, misrepresentation, or other cause for contract modification, reformation, or rescission.” The regulations further explain that the “word ‘controversy’ is meant to be broad and all- encompassing,” applying to “the full spectrum of disagreements from pricing of routine contract changes to claims of breach of

contract.”

The regulations and the disputes clause both mandate that controversies be submitted to the contracting officer--the person executing the contract on behalf of DART--for resolution.1 The decision of the contracting officer is final unless the contractor appeals within ninety days. Administrative appeals are heard by DART’s authorized representatives, who are mostly current or former members of the federal Armed Services Board of Contract Appeals. DART also has promulgated a set of extensive procedural rules for adjudicating appeals; the rules envision a quasi-judicial proceeding that includes, among other things, discovery and a de novo hearing where the contractor can be represented by counsel.

Regarding the finality of the administrative decision, the regulations and the disputes clause contain nearly identical language: “The decision . . . shall be final and conclusive as to questions of fact unless determined by a court of competent jurisdiction to have been fraudulent, capricious, arbitrary, so grossly erroneous as necessarily to imply bad faith, or not

1 Eby complains that the disputes clause does not require DART to submit its grievances to the administrative process. But both DART’s regulations and the disputes clause indicate that the dispute-resolution process is intended to resolve all conflicts between the parties. Further, DART’s regulations contain a provision explicitly stating that “[a]ll controversies involving claims asserted by [DART] against a contractor which cannot be resolved by mutual agreement shall be the subject of a decision by the Contracting Officer.”

supported by substantial evidence.”2 Further, the administrative resolution is not final on questions of law. The regulations and the disputes clause permit a dissatisfied contractor to seek judicial review of the administrative decision within two years of the contractor’s receipt of the decision.

Although Eby did not submit its grievances to the administrative process described above, it asserts that it complained to DART regarding the allegedly inadequate bid specifications. According to Eby, DART neither accepted responsibility for the design defects nor compensated Eby for most of the cost overruns that it had incurred in performing the work.3 Substantial construction remains to be done, and Eby anticipates significant additional losses if it is forced to complete the project. Frustrated with this state of affairs, Eby filed suit in federal court against DART in January 2003. B. Proceedings in the District Court In its complaint, Eby pleaded two causes of action: breach

2 At various places in its brief, Eby claims that DART’s administrative process intends to resolve conclusively any questions of fact. But, as shown here, DART’s procurement regulations and the disputes clause of the parties’ contract both provide for substantial-evidence review of DART’s findings of fact. Regardless, we do not, in this appeal, express any opinion on the extent to which a subsequent court should defer to any findings of fact made during DART’s administrative process.

3 Eby’s complaint acknowledges that DART has paid Eby for individual change-order claims filed by Eby in accordance with the contract. But Eby maintains that this procedure is inadequate to compensate it for the losses it has suffered and will continue to suffer.

of contract and misrepresentation. As remedies, Eby sought rescission of the agreement and compensation on a quantum meruit basis. In response, DART moved to dismiss, contending first that Eby had failed to state a claim on which relief could be granted because it had not exhausted its administrative remedies. Second, DART asserted that Eby’s misrepresentation claim should be dismissed because it is a tort claim and governmental immunity bars tort claims against DART.

Free access — add to your briefcase to read the full text and ask questions with AI

Martin K Eby Const v. Dallas Area Rapid, (5th Cir. 2004).

Martin K Eby Const v. Dallas Area Rapid (Martin K Eby Const v. Dallas Area Rapid) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Gregson v. Zurich American Insurance
322 F.3d 883 (Fifth Circuit, 2003)
Chiu v. Plano Independent School District
339 F.3d 273 (Fifth Circuit, 2003)
Mayo v. Hartford Life Insurance
354 F.3d 400 (Fifth Circuit, 2004)
United States v. Wunderlich
342 U.S. 98 (Supreme Court, 1951)
TEXAS STATE BOARD OF EXAMINERS IN OPTOMETRY v. Carp
343 S.W.2d 242 (Texas Supreme Court, 1961)
Tribble & Stephens Co. v. Consolidated Services, Inc.
744 S.W.2d 945 (Court of Appeals of Texas, 1987)
Webb County Appraisal District v. New Laredo Hotel, Inc.
792 S.W.2d 952 (Texas Supreme Court, 1990)
Caspary v. Corpus Christi Downtown Management District
942 S.W.2d 223 (Court of Appeals of Texas, 1997)
State v. Fidelity & Deposit Co. of Maryland
127 S.W.3d 339 (Court of Appeals of Texas, 2004)
Graco Robotics, Inc. v. Oaklawn Bank
914 S.W.2d 633 (Court of Appeals of Texas, 1996)
Shintech Inc. v. Group Constructors, Inc.
688 S.W.2d 144 (Court of Appeals of Texas, 1985)
Texas Education Agency v. Cypress-Fairbanks I.S.D.
830 S.W.2d 88 (Texas Supreme Court, 1992)
General Services Commission v. Little-Tex Insulation Co.
39 S.W.3d 591 (Texas Supreme Court, 2001)