Shintech Inc. v. Group Constructors, Inc.

688 S.W.2d 144, 1985 Tex. App. LEXIS 6116
CourtCourt of Appeals of Texas
DecidedJanuary 31, 1985
DocketA14-82-552CV
StatusPublished
Cited by39 cases

This text of 688 S.W.2d 144 (Shintech Inc. v. Group Constructors, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shintech Inc. v. Group Constructors, Inc., 688 S.W.2d 144, 1985 Tex. App. LEXIS 6116 (Tex. Ct. App. 1985).

Opinion

OPINION

DRAUGHN, Justice.

On appellee’s motion for rehearing, the Court’s opinion issued on November 8,1984 is withdrawn and the following is substituted therefor. Appellant’s motion for rehearing is overruled.

Appellee, Group Constructors, Inc., as prime contractor, filed suit against appellant and owner, Shintech Inc., for breach of a construction contract and alternatively for recovery under quantum meruit. A nonjury trial resulted in judgment for Group Constructors, Inc. against Shintech for $483,400.28 with prejudgment interest of $33,771.79 plus attorney’s fees.

Appellant, Shintech, raises points of error relating to the following matters: 1) interpretation of the contract; 2) whether Shintech breached the contract; 3) whether appellee had a right to recover under quantum meruit; 4) whether there existed a mutual mistake; 5) whether Shintech made misrepresentations to appellee; 6) whether the parties abandoned the construction contract; and 7) the amount of damages which were awarded to appellee. Shintech also contends that the trial erred in its failure to find in favor of its affirmative defenses which include failure of condition precedent, assumption of risk, waiver, estoppel, and payment. We affirm the judgment of the trial court.

In 1979, appellant contracted with H.B. Zachry Company for expansion of its polyvinyl chloride (PVC) plant. Zachry was responsible for performing all work on the expansion project, including the mechanical construction and the electrical and instrumental work. The contract was on a cost-plus basis which meant that appellant, as owner, was to pay all costs incurred by Zachry plus a fee.

During the summer of 1980, appellant determined that the expense of Zachry’s work was exceeding the initial projection and decided to obtain bids for the remainder of the work. On August 27, 1980, appellee, Group Constructors, Inc., submitted a bid proposal to furnish all labor, construction services, and supplies necessary to construct mechanical or piping work on the plant expansion project for the lump sum price of $1,119,478. After discussions of the bid and contemplated work, appellant issued a letter of intent on September 19, 1980. This was signed by ap-pellee. Appellee was required to begin work on September 22, 1980. The formal contract, which stated it was entered into on September 19, 1980, was not actually signed by the parties until December 2, 1980. Under the agreement appellant was to furnish materials for appellee's work.

Appellee brought suit against appellant for damages allegedly caused by appellant’s interference with the efficiency of its work. Appellant allegedly interfered in the following ways: 1) appellant failed to *148 timely and continuously furnish material for use by appellee; 2) appellant furnished materials for installation which were erroneously prefabricated by the previous contractor, Zachry; 3) appellant made excessive design errors, changes, and extra work orders; 4) appellant constructively accelerated appellee’s work by delaying it through the acts mentioned above while refusing to extend the work schedule; and 5) appellant accelerated work through imposition of an additional swing shift. Appellee contends that appellant assumed liability for the damages resulting from these acts on the basis of Attachment A, paragraph 4 of the contract which provides:

4. A construction schedule will be established as early as feasible in the project which will be reviewed and approved by the client. Upsets of this schedule caused by acts of the client or those over which he controls causing undue expense on the Contractor shall be for the Owner’s account, (emphasis added)

We also recognize that a contractor is entitled to recover damages from an owner for losses due to delay and hindrance of its work if it proves: (1) that its work was delayed or hindered, (2) that it suffered damages because of the delay or hindrance, and (3) that the owner was responsible for the act or omission which caused the delay or hindrance. City of Houston v. R.F. Ball Construction Co., 570 S.W.2d 75, 77 (Tex.Civ.App. — Houston [14th Dist.] 1978, writ ref’d n.r.e.). The trial court determined that appellee was entitled to $438,-400.28 as compensation for the loss in efficiency caused by appellant.

Appellant challenges the legal and factual sufficiency of the evidence to support the trial court’s findings that it committed each of the above mentioned acts and that each of these acts caused damage to appellee through loss of efficiency. Appellee, as plaintiff, had the burden of proof on each of these findings. In considering legal insufficiency points of error the court will consider only the evidence tending to support the finding, viewing it in the most favorable light in support of the finding, giving effect to all reasonable inferences that may be drawn therefrom, and disregarding all conflicting evidence. If upon such review the court finds there is a complete absence of evidence of probative force to support the finding, or there exists only a scintilla of evidence to support it, the point must be sustained. Glover v. Texas General Indemnity Co., 619 S.W.2d 400 (Tex.1981); Garza v. Alviar, 395 S.W.2d 821, 823 (Tex.1965). In considering factual insufficiency points of error, the court examines the whole record to determine not only that there is some evidence to support the finding, but also to determine whether considering all the evidence, the finding is not manifestly unjust. If it is so weak that the finding is manifestly unjust the court will sustain the point. Burnett v. Motyka, 610 S.W.2d 735 (Tex. 1980); In re King’s Estate, 150 Tex. 662, 244 S.W.2d 660 (1952).

We first review appellant’s points of error related to the trial court’s findings that:

1) Appellant represented that it had substantially all the materials on hand and that they would be furnished to appellee on a continuous basis.
2) On September 18, 1980, appellant sent appellee a letter, which advised appel-lee to give two weeks advance notice for unfabricated piping material to be furnished by appellant.
3) By reason of the expedited construction schedule desired by appellant and the need for immediate installation work to begin for such a schedule to be possible, appellant waived any requirement of two weeks advance notice for appellant’s filling of material requisitions during the early period of the construction and until October 15, 1980.
4) Appellant substantially and repeatedly failed to furnish material to appellee on a continuous basis and/or within 14 days of requisitioning, which hindered and interfered with the ability of ap-pellee to perform its work with reasonable efficiency and caused loss of *149 productivity and extra work for appel-lee.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southern Electrical Services, Inc. v. City of Houston
355 S.W.3d 319 (Court of Appeals of Texas, 2011)
Mastec North America, Inc. v. El Paso Field Services, L.P.
317 S.W.3d 431 (Court of Appeals of Texas, 2010)
West v. TRIPLE B SERVICES, LLP
264 S.W.3d 440 (Court of Appeals of Texas, 2008)
Interstate Contracting Corp. v. City of Dallas
407 F.3d 708 (Fifth Circuit, 2005)
Beard Family Partnership v. Commercial Indemnity Insurance Co.
116 S.W.3d 839 (Court of Appeals of Texas, 2003)
Cisneros, Xavier Mario v. State
Court of Appeals of Texas, 2002
Argee Corp. v. Solis
932 S.W.2d 39 (Court of Appeals of Texas, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
688 S.W.2d 144, 1985 Tex. App. LEXIS 6116, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shintech-inc-v-group-constructors-inc-texapp-1985.