MasTec North America, Inc. and Mastec, Inc. v. El Paso Field Services, L.P. and Gulfterra South Texas, L.P. F/N/A El Paso South Texas, L.P.

CourtCourt of Appeals of Texas
DecidedJuly 23, 2009
Docket01-07-00319-CV
StatusPublished

This text of MasTec North America, Inc. and Mastec, Inc. v. El Paso Field Services, L.P. and Gulfterra South Texas, L.P. F/N/A El Paso South Texas, L.P. (MasTec North America, Inc. and Mastec, Inc. v. El Paso Field Services, L.P. and Gulfterra South Texas, L.P. F/N/A El Paso South Texas, L.P.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MasTec North America, Inc. and Mastec, Inc. v. El Paso Field Services, L.P. and Gulfterra South Texas, L.P. F/N/A El Paso South Texas, L.P., (Tex. Ct. App. 2009).

Opinion

Opinion issued July 23, 2009







In The

Court of Appeals

For The

First District of Texas





NO. 01-07-00319-CV





MASTEC NORTH AMERICA, INC. AND MASTEC, INC., Appellants


V.


EL PASO FIELD SERVICES, L.P. AND GULFTERRA SOUTH TEXAS, L.P. F/K/A EL PASO SOUTH TEXAS, L.P., Appellees






On Appeal from the 334th District Court

Harris County, Texas

Trial Court Cause No. 2004-39579





O P I N I O N


          This is a breach of contract dispute brought by appellants, MasTec North America, Inc., and Mastec, Inc. (collectively, “MasTec”), against appellees, El Paso Field Services, L.P. and Gulfterra South Texas, L.P., f/k/a El Paso South Texas, L.P. (collectively, “El Paso”). El Paso engaged MasTec to replace a butane pipeline for a lump sum of $3.6 million, known as the “Butane Shuttle Replacement Project” (“Project”). MasTec submitted its bid on the Project based on information in El Paso’s bid package, which included, inter alia, the “Station and Land Pipeline Construction Contract” (“Contract”) and El Paso’s specifications, which were incorporated into the Contact. In the Contract specifications, El Paso asserted that it used due diligence in locating any “foreign crossings” in the pipeline right-of-way and that there were 280 such crossings. During construction, however, MasTec encountered 794 foreign crossings, which required additional construction measures and increased its costs substantially. MasTec sued El Paso to recoup the additional expenses. A jury found that El Paso breached the due diligence provision of the Contract specifications and awarded $4,763,890 in damages to MasTec. Subsequently, on the motion of El Paso, the trial court granted judgment notwithstanding the verdict (“JNOV”) in favor of El Paso, concluding that the lump-sum provisions of the Contract allocated the risk of unidentified foreign crossings to MasTec and holding that MasTec take nothing by its claims. MasTec appeals.

          In its sole issue, MasTec contends that the trial court erred by granting JNOV in favor of El Paso because the trial court’s interpretation of the Contract improperly rendered the due diligence provision a nullity and shifted the risk of costs associated with unidentified foreign crossings to MasTec. In the alternative, MasTec contends that (a) the Contract is ambiguous and must be strictly construed against El Paso, or (b) that MasTec is entitled to recover under its quantum meruit theory.

          We reverse and remand for entry of judgment consistent with the jury’s verdict and for assessment of attorney’s fees in favor of MasTec.

FACTS AND PROCEDURAL HISTORYEl Paso is one of the world’s largest energy companies. MasTec is a construction company that was established in the 1930s and that has annual gross revenue exceeding $1 billion.

          At the time of the events, El Paso owned a butane pipeline that extended from Houston to Corpus Christi. The pipeline was originally constructed in the 1940s as an emergency supply line during the war. Because of its age and because it was deemed too shallow (buried less than 12 inches underground), El Paso contracted for its replacement, which took place in phases. This lawsuit involves Phase II of the replacement—a 68-mile, 8-inch diameter line extending from Victoria to Nueces Bay.

          El Paso invited MasTec to bid on the replacement Project, which was to include removal of the existing pipeline and the construction of a new pipeline in the same location. MasTec hired Bill White, who is considered by MasTec to be “a pipeline-construction veteran,” as its general manager. White attended El Paso’s “pre-bid meeting” on April 22, 2003, at which El Paso distributed bid packages containing the job description, the location of the pipeline, drawings or maps, known as “alignment sheets,” and the Contract.

          According to El Paso’s bidding instructions, “The Contractor’s bid shall be based on the Contract documents as issued, without modifications. All clarifications or changes during the bid period will be communicated to all Contractors. . . . Significant exceptions to the provisions of the Proposed Contract documents may cause rejection of the bid. . . . The Scope of Work is believed to be complete.”

          The purpose of the alignment sheets was to show “foreign crossings,” which are obstacles that cross the pipeline right of way—such as other pipelines, utilities, roads, rivers, fences, wells, cables, and concrete structures. Substantial costs are involved in maneuvering around these structures during pipeline construction and de-construction. El Paso had hired Gullett & Associates, an engineering company, to produce the alignment sheets.

          The invitation to the pre-bid meeting stated, “No guided tour of the proposed pipeline is now scheduled. Each contractor will be required to review the construction requirements individually. Aerial inspection is highly recommended.” At the meeting, Jackie Ross, who was initially a consultant to El Paso and later became the full-time assistant to the project manager on this Project, told the contractors that El Paso would normally conduct a tour of the pipeline, but that there would be too many cars in this case and that each of the contractors was encouraged to “fly the route.”

          After the pre-bid meeting, White and his son, Mike, flew by helicopter over the pipeline route, familiarizing themselves with the topography and landing several times to check soil conditions. Mike testified by deposition that he carried the alignment sheets in his lap during the flight for orientation, but that he could not see foreign crossings from the air. White also drove along portions of the pipeline to which he had access. According to White, MasTec and the other contractors were specifically prohibited from entering certain private properties along the route, including the O’Connor Ranch. El Paso later claimed that the contractors were permitted to enter the restricted areas for inspection if they arranged for an escort by an El Paso representative.

          Pursuant to El Paso’s written bidding instructions, MasTec’s bid and completed Contract, including lump-sum price schedule, were due 12 business days later, on May 8, 2003. This date was later amended to May 15, 2003.

The Contract and Specifications

          

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hollerbach v. United States
233 U.S. 165 (Supreme Court, 1914)
J.M. Davidson, Inc. v. Webster
128 S.W.3d 223 (Texas Supreme Court, 2003)
Frost National Bank v. L & F Distributors, Ltd.
165 S.W.3d 310 (Texas Supreme Court, 2005)
IT Corp. v. Motco Site Trust Fund
903 F. Supp. 1106 (S.D. Texas, 1994)
Williams v. Briscoe
137 S.W.3d 120 (Court of Appeals of Texas, 2004)
Coker v. Coker
650 S.W.2d 391 (Texas Supreme Court, 1983)
Transcontinental Gas Pipeline Corp. v. Texaco, Inc.
35 S.W.3d 658 (Court of Appeals of Texas, 2001)
Tiller v. McLure
121 S.W.3d 709 (Texas Supreme Court, 2003)
Shintech Inc. v. Group Constructors, Inc.
688 S.W.2d 144 (Court of Appeals of Texas, 1985)
Burroughs Wellcome Co. v. Crye
907 S.W.2d 497 (Texas Supreme Court, 1995)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Wheeler v. Methodist Hospital
95 S.W.3d 628 (Court of Appeals of Texas, 2002)
McCreary v. Bay Area Bank & Trust
68 S.W.3d 727 (Court of Appeals of Texas, 2001)
Southeastern Pipe Line Co., Inc. v. Tichacek
997 S.W.2d 166 (Texas Supreme Court, 1999)
Sage Street Associates v. Northdale Construction Co.
863 S.W.2d 438 (Texas Supreme Court, 1993)
Reilly v. Rangers Management, Inc.
727 S.W.2d 527 (Texas Supreme Court, 1987)
Heritage Resources, Inc. v. NationsBank
939 S.W.2d 118 (Texas Supreme Court, 1997)
IO I SYSTEMS, INC. v. City of Cleveland, Tex.
615 S.W.2d 786 (Court of Appeals of Texas, 1980)
Emerald Forest Utility District v. Simonsen Construction Co.
679 S.W.2d 51 (Court of Appeals of Texas, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
MasTec North America, Inc. and Mastec, Inc. v. El Paso Field Services, L.P. and Gulfterra South Texas, L.P. F/N/A El Paso South Texas, L.P., Counsel Stack Legal Research, https://law.counselstack.com/opinion/mastec-north-america-inc-and-mastec-inc-v-el-paso--texapp-2009.